Fee Review-notes | 10/2/2002 | 10/2/2002 | 8/10/2004 | | DONE |
|
|
|
|
MISC ACTIONS | | | 11/6/2003 | | DONE |
|
|
|
88.20 additional fees due for 2 hr after hour inspections
|
First Notice | | 10/22/2003 | 10/22/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/22/2003 | | DONE |
|
|
|
Perm. Occ. Cert. # 9849 issued 10-22-03 to Lithia Motors.
|
BLD-Final | 10/20/2003 | 10/21/2003 | 10/21/2003 | A | PASS |
Russ Owen
|
|
|
Dennis; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Ok perm oc. 10/20/2003 6:00:02 PM
|
BLD-Final | 10/8/2003 | 10/8/2003 | 10/8/2003 | P | FAIL |
Russ Owen
|
|
|
Dennis, ###-#### - please call 1st so he can meet you there! Still has corrections not completed from prior c/n. 10/8/2003 5:00:34 PM
|
FIRE-Final Inspection | 10/6/2003 | 10/6/2003 | 10/6/2003 | A | PASS |
Rick Jackson
|
|
|
|
Code Occupancy Approval | 10/3/2003 | 10/3/2003 | 10/3/2003 | A | PASS |
Wm. Michael Meloy
|
|
|
Compliance met. 10/3/2003 12:21:47 PM
|
FIRE-Final Inspection | 10/1/2003 | 10/2/2003 | 10/2/2003 | A | FAIL |
Rick Jackson
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Darla Downs need"Fire lane no parking" on red curbing; page 2 of sprinkler certificates 10/2/2003 11:20:17 AM
|
FIRE-Final Inspection | 9/30/2003 | 10/1/2003 | 10/1/2003 | A | NR |
Rick Jackson
|
|
|
dennis--; Phone #: ###-#### Internet Inspection Request from: Marsha Smyliem rescheduled for 10/2 10/1/2003 3:54:01 PM
|
FIRE-Final Inspection | 7/21/2003 | 7/22/2003 | 7/22/2003 | A | FAIL |
Troy Cobbley
|
|
|
dennis; Phone #: ###-#### Inspection was actually a conference for fire dept access. I met with the superintendant and marked on the city approved plans the curbing that needed painting and locations for signage at the entrance to the property. I also spoke with Dennis on the phone about the fire hydrant off the south east corner of the main dealership building needing to be turned so the 4" barrell faces the parking lot 7/22/2003 11:02:21 AM
|
Temporary occupancy | | | 7/21/2003 | | DONE |
|
|
|
Temp. Occ. Cert. #4973 issued 7-21-03 to Lithia Motors.
|
BLD-Final | 7/17/2003 | 7/18/2003 | 7/18/2003 | A | NR |
Russ Owen
|
|
|
late morning dennis; Phone #: ###-#### Internet Inspection Request from: Barbara Moore (contractor called not ready. 7/18/2003 12:08:45 PM
|
FIRE-Sprinkler Rough-in | 7/18/2003 | 7/18/2003 | 7/18/2003 | P | FAIL |
Troy Cobbley
|
|
|
This inspection was apparently for life safety. The only items inspected was the emergency lights and exit signs. No other items looked at 7/18/2003 6:10:03 PM
|
BLD-Final | 7/18/2003 | 7/18/2003 | 7/18/2003 | P | PART |
Russ Owen
|
|
|
would be ok for a temp oc pending life safety inspection. c/n posted by me for other items.7/18/2003 5:37:17 PM 7/18/2003 5:37:33 PM
|
FIRE-Final Inspection | 7/15/2003 | 7/16/2003 | 7/16/2003 | A | FAIL |
Rick Jackson
|
|
|
need to complete fire alarms; see alarm permit corrections; overhead door didn't release with detectors; need to test emergency and exit lighting; door hardware from show room not openable from the inside without special knowledge; fusiblelinks painted on overhead doors; need sign on riser/FACP door 7/16/2003 11:26:10 AM
|
Code Occupancy Approval Temp | | | 7/16/2003 | | DONE |
|
|
|
LOOKS REAL GOOD BUT NEEDS PARKING STRIPPING, THIS IS BEING DONE NOW SO I SIGNED TEMP WITHOUT BOND AND WILL RECHECK FRIDAY TO MAKE SURE THIS IS DONE.
|
BLD-Other | 7/14/2003 | 7/15/2003 | 7/15/2003 | A | PART |
Russ Owen
|
|
|
restroom round lights and 2 small rooms at south not complete rest ok. 7/15/2003 10:08:34 AM
|
BLD-Other | 7/11/2003 | 7/14/2003 | 7/14/2003 | A | PART |
Russ Owen
|
|
|
ok except some lower floor areas not complete at south side, also restrooms need can lights tied.. 7/14/2003 12:02:30 PM
|
BLD-Framing/Rough-in | 7/11/2003 | 7/11/2003 | 7/11/2003 | P | PART |
Russ Owen
|
|
|
dennis ceiling grid; Phone #: ###-#### Internet Inspection Request from: Barbara Moore. ok need some light at lower floor area to the waiting areas and support for lights in all rest rooms. 7/11/2003 3:20:08 PM
|
BLD-Framing/Rough-in | 6/25/2003 | 6/25/2003 | 6/25/2003 | A | PART |
Russ Owen
|
|
|
still needs 1 rated exp joint6/25/2003 11:00:20 AM 6/25/2003 11:00:42 AM
|
BLD-Framing/Rough-in | 6/24/2003 | 6/24/2003 | 6/24/2003 | P | CANC |
Russ Owen
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 6/16/2003 | 6/17/2003 | 6/17/2003 | A | PART |
Russ Owen
|
|
|
went over 2 hr wal still inprogress and needs the 1 hr epansion joint completed also noted with contractor that the cut in the cmu for the roll up door at the 2hr fire wall did not indicate any details for support, the engineer is addressing this. 6/18/2003 1:52:35 PM
|
BLD-Conference | 6/16/2003 | 6/16/2003 | 6/16/2003 | P | PART |
Russ Owen
|
|
|
stoped by to check progrees talked with job supper will need to return at am to meet with fraing contractor. 6/16/2003 5:39:28 PM
|
FIRE-Conference | 6/11/2003 | 6/11/2003 | 6/11/2003 | P | DONE |
Troy Cobbley
|
|
|
oil storage tank venting, John ###-#### I met with John with Debest plumbing and telephone conference with sam. There are no code requirements found for venting of the oil storage tanks to the outside of the facility. I did refer the contractor to the UFC 7902 minimum requirements for venting of any storage tank. 6/11/2003 2:29:38 PM
|
BLD-Framing/Rough-in | 6/4/2003 | 6/4/2003 | 6/4/2003 | P | PART |
Russ Owen
|
|
|
DENNIS; Phone #: ###-#### Internet Inspection Request from: Darla DownsPosted a c/n to fire caulk and put in rated control joit at 1 hr to 2 hr wall. 6/4/2003 5:07:32 PM
|
BLD-Framing/Rough-in | 5/27/2003 | 5/28/2003 | 5/28/2003 | A | PART |
Russ Owen
|
|
|
2nd floor ok pending fire stoping of plumbing in floor of restrooms and , also posted a c/n for columns in 2hr walls. 5/29/2003 12:49:18 PM
|
BLD-Framing/Rough-in | 5/27/2003 | 5/27/2003 | 5/27/2003 | P | PART |
Russ Owen
|
|
|
DENNIS; Phone #: ###-#### Internet Inspection Request from: Darla Downs. Unable to locate framer will try am inspedction talked with contractor on phone, note a fire stop a the 2nd floor hvac would be required. 5/27/2003 5:25:08 PM
|
BLD-Framing/Rough-in | 5/13/2003 | 5/14/2003 | 5/14/2003 | A | PART |
Russ Owen
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Barbara MooreLower floor area A ok left a c/n for the mechanical runing up 2nd floor to provide a 1 hr shaft etc. 5/14/2003 1:22:21 PM
|
BLD-Framing/Rough-in | 5/6/2003 | 5/6/2003 | 5/6/2003 | P | PART |
Russ Owen
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Annette Moore. need detail for parapet. 5/7/2003 5:02:44 PM
|
BLD-Framing/Rough-in | 4/21/2003 | 4/22/2003 | 4/22/2003 | A | PART |
Russ Owen
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Annette Moore. areas ok for drywall have been marked in the trailer office. 4/22/2003 5:06:53 PM
|
BLD-Framing/Rough-in | 4/9/2003 | 4/10/2003 | 4/10/2003 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung Misc. 1HR walls highlighted and initialed on plan. 4/10/2003 12:10:41 PM
|
BLD-Framing/Rough-in | 3/26/2003 | 3/26/2003 | 3/26/2003 | P | FAIL |
Russ Owen
|
|
|
DENNIS; Phone #: ###-#### Internet Inspection Request from: Darla Downsc/n on site. 3/27/2003 12:10:51 PM
|
BLD-Footing | 1/9/2003 | 1/10/2003 | 1/10/2003 | A | PART |
Russ Owen
|
|
|
dennis ###-#### ` 1/10/2003 4:53:16 PM MTI will perform special inspection. 1/10/2003 4:53:37 PM
|
BLD-Footing | 1/8/2003 | 1/9/2003 | 1/9/2003 | A | CANC |
Russ Owen
|
|
|
dennis- ###-####
|
Override - Parcel Holds | | | 1/9/2003 | | |
|
|
|
|
Print Occupancy Form | | | 1/8/2003 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/8/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/8/2003 | | DONE |
|
|
|
|
Telephone call | | | 1/8/2003 | | DONE |
|
|
|
permit ready and need ACHD
|
Override - Parcel Holds | | | 1/8/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/8/2003 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/8/2003 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/8/2003 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/8/2003 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/8/2003 | | |
|
|
|
|
Plan assigned to (JCM) | 10/3/2002 | | 1/7/2003 | | PASS |
John Menard
|
|
|
1/7/2003 15:55:45 JCM - activity updated through activity BLDA022 from case BLD02-02435.
|
Routing - PUBLIC WORKS | 1/2/2003 | | 1/7/2003 | | PASS |
|
|
|
|
Routing - PLANNING | 1/7/2003 | | 1/7/2003 | | PASS |
|
|
|
Approved per DRH02-69 (MGS). Signature from CU approved by Mark Pecchenino.
|
Routing - PLAN CHECK | 1/7/2003 | | 1/7/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2003 | | PASS |
|
|
|
|
Routing - FIRE | 1/2/2003 | | 1/2/2003 | | PASS |
|
|
|
|
Routing - FIRE | 12/30/2002 | | 12/30/2002 | | FAIL |
|
|
|
indoor storage of diesel is in excess of quantity limits
|
Routing Off Site - STRUCTURAL | 12/6/2002 | | 12/23/2002 | | PASS |
|
|
|
routed revised drawings and calculations of 12/6/02 to outside eng. kmm
|
Routing - PLANNING Land Div | 12/17/2002 | | 12/17/2002 | | PASS |
|
|
|
Approval to proceed on existing building with understanding that Nampa-Meridian Irrigation easement is being ratified and a new deed will be recorded that describes the entire parcel prior to issuing a Certificate of Occupancy.
|
Routing - PLAN CHECK | 12/2/2002 | | 12/17/2002 | | |
|
|
|
|
Plan resubmittals received | | | 12/6/2002 | | DONE |
|
|
|
Received three copies of revised sheets S0.1, S1.1, S1.2, S1.3, S1.4, S2.1, S2.2, S3.1, S3.2, S3.3, S4.1, S4.2, S4.3. Three copies of struct. design calculations and one copy of response letter. Routed one copy to outside eng. and routed two copies to John M. kmm
|
Routing - PUBLIC WORKS | 11/27/2002 | | 12/2/2002 | | FAIL |
|
|
|
send to public works to Bill Colson.
Requires street light plan per Bill Colson
|
Routing - PLAN CHECK | 11/19/2002 | | 11/27/2002 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 11/27/2002 | | PASS |
|
|
|
Reviewed and approved resubmitted plan sheets and specifications. JCM
|
Plan resubmittals received | | | 11/25/2002 | | DONE |
|
|
|
Received three copies of resubmittal sheet E1.0 with transmittal letter for Bill Colson. Routed to John Menard.
|
Plan resubmittals received | | | 11/21/2002 | | DONE |
|
|
|
Received two copies of revised sheets A2.2, A3.1, A5.1, A5.2, A7.1, A10.1, C1.8, one copy plan review response letter and attachments. Routed to John M. kmm
|
Routing - FIRE | 11/13/2002 | | 11/19/2002 | | FAIL |
|
|
|
|
Plan Review Completed(1st rev) | | | 11/19/2002 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 10/30/2002 | | 11/13/2002 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 11/13/2002 | | FAIL |
|
|
|
Mailed the architect of record a copy of the plan review comment list requesting revisions. JCM
|
Plan resubmittals requested | | | 11/4/2002 | | |
|
|
|
Faxed the architect of record a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 10/3/2002 | | 11/1/2002 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside eng. kmm Received comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLUMBING | 10/25/2002 | | 10/30/2002 | | PASS |
|
|
|
CLEANOUTS REQUIRED ON THE STORM SEWER MAINS OUTSIDE EVERY 100", UPSTREAM INTERCEPTOR CHAMBER VENT MUST GO THRU THE ROOF BY ITSELF, PROVIDE A SAMPLE PORT DOWNSTREAM OF INTERCEPTOR, USE NO SWEEP FITTING TO PROVIDE ACCESS FOR EQUIPMENT, USE BOISE CITY APPROVED INTERCEPTOR DETAIL, ATTACHED, ADDITIONAL CROSS CONNECTION PRETECTION MAY BE REQUIRED, NO ABS DRAINAGE SHALL BE INSTALLED IN THE GREASE LINE.
|
Routing - PLANNING | 10/17/2002 | | 10/25/2002 | | PEND |
|
|
|
Approved per CUP02-00056, routed to Design Review 10/22/02.
Design Review conditions not met; please refer to DRH02-69 action letter, dated June 13, 2002.
|
Routing - Erosion and Sediment | 10/15/2002 | | 10/17/2002 | | PASS |
|
|
|
ESC Plan passed on Bld02-02121
|
Routing - PUBLIC WORKS | 10/8/2002 | | 10/15/2002 | | FAIL |
|
|
|
Requires street light plan per Bill Colson. kmm
|
Routing - PLANNING Land Div | 10/7/2002 | | 10/8/2002 | | FAIL |
|
|
|
Need recorded deed with description of perimeter. Need new tax parcel #. Need to vacate 60' easment for Nampa-Meridian Irrigation Easement for Welch Drain as shown on ROS 3881. Called Mike Dahlberg of CSHQA on 10/8/02. David Abo
|
Plan routing begun/NEW & ADDTN | | | 10/7/2002 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/7/2002 | | DONE |
|
|
|
Received civil, landscape and esc plans marked for refrence only. Put with plans to start routing. Grading and drainage permit under Bld02-02121. Erosion and Sediment under ESC02-00407. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 10/3/2002 | | PEND |
|
|
|
Waiting for Civil, landscape, site and esc plans. Contacted Jim Otradosky of this need. kmm
|
Application received | | | 10/2/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/2/2002 | | DONE |
|
|
|
|