Fee Review-notes | 10/4/2002 | 10/4/2002 | 8/10/2004 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/19/2004 | | |
|
|
|
|
First Notice | | 1/27/2004 | 1/27/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/27/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 9944 issued 1-27-04 to St. Mark's Cahtolic Church.
|
Print Occupancy Form | | | 1/27/2004 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety, fire alarm and fire sprinklers finaled 1/21/2004 11:23:09 AM
|
FIRE-Final Inspection | 1/20/2004 | 1/21/2004 | 1/21/2004 | P | CANC |
Troy Cobbley
|
|
|
duplicate inspection 1/21/2004 11:24:04 AM
|
BLD-Final | 1/21/2004 | 1/21/2004 | 1/21/2004 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/21/2004 at 7:05:37 AM. Contact: ###-####. OK for Perm Occ. :) 1/21/2004 3:13:19 PM
|
Permanent Occupancy | | 1/15/2004 | 1/15/2004 | | DONE |
|
|
|
|
BLD-Other | 1/13/2004 | 1/14/2004 | 1/14/2004 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/13/2004 at 9:03:51 AM. Contact: ###-####. Grid in alternate OK 1/15/2004 8:07:26 AM
|
BLD-Other | 12/23/2003 | 12/24/2003 | 12/24/2003 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/23/2003 at 1:47:54 PM. Contact: ###-####.
|
FIRE-Final Inspection | 12/22/2003 | 12/23/2003 | 12/23/2003 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave millers permission until the existing building is completed. Battery calcs, map, breaker locks and breaker box location. Existing building needs to be inspected 12/23/2003 1:23:58 PM
|
BLD-Final | 12/22/2003 | 12/23/2003 | 12/23/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/22/2003 at 9:13:59 AM. Contact: ###-####. Temp Occ. OK for Sanctuary (Bldg B) Verified approval from Dave Miller over the phone. 12/23/2003 4:09:23 PM 12/23/2003 4:14:38 PM
|
FIRE-Final Inspection | 12/22/2003 | 12/22/2003 | 12/22/2003 | P | FAIL |
Troy Cobbley
|
|
|
provide "no parking fire lane" text on the fire lane curbing, install door hardware and building address, secure new area from the existing area before a temp occupancy is signed 12/22/2003 4:12:08 PM
|
BLD-Wall cover | 12/10/2003 | 12/11/2003 | 12/11/2003 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/10/2003 at 10:35:14 AM. Contact: ###-####. Ceiling grid OK. 12/11/2003 11:19:36 AM
|
BLD-Wall cover | 10/21/2003 | 10/21/2003 | 10/21/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/21/2003 at 7:11:08 AM. Contact: ###-####. Need details and listed assemblies for type v1hr alternate. 10/21/2003 4:29:16 PM
|
BLD-Wall cover | 10/17/2003 | 10/20/2003 | 10/20/2003 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/17/2003 at 9:25:09 AM. Contact: ###-####.
|
BLD-Conference | 10/7/2003 | 10/8/2003 | 10/8/2003 | A | DONE |
Jim Sly
|
|
|
per your request
|
BLD-Framing/Rough-in | 9/5/2003 | 9/8/2003 | 9/8/2003 | A | PART |
Jim Sly
|
|
|
BRIAN; Phone #: ###-#### Internet Inspection Request from: Marc Lileks Looked at wood framing in Alternate section.....Archit to address V 1hr at ceiling this area. 9/8/2003 10:11:39 AM
|
Override - Parcel Holds | | | 9/5/2003 | | |
|
|
|
|
Override - Parcel Holds | | | 9/3/2003 | | |
|
|
|
|
Receive PAYMENT IN FULL PRINT | | | 9/3/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 7/23/2003 | | 7/28/2003 | | PASS |
|
|
|
Plan Modification
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2003 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 7/28/2003 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/28/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/28/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/28/2003 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 7/28/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/28/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/28/2003 | | DONE |
|
|
|
|
Telephone call | | | 7/28/2003 | | DONE |
|
|
|
permit ready and fees due
|
Plan assigned to (M_P) | 5/28/2003 | | 7/28/2003 | | PASS |
Mike Phillips
|
|
|
7/28/2003 14:30:20 M_P - activity updated through activity BLDA022 from case BLD02-02454.
|
BLD-Framing/Rough-in | 7/23/2003 | 7/24/2003 | 7/24/2003 | A | PART |
Jim Sly
|
|
|
###-#### bryaN Conf on Work in progress. 7/24/2003 9:40:03 AM
|
Override - Parcel Holds | | | 7/23/2003 | | |
|
|
|
|
Routing - FIRE | 7/17/2003 | | 7/23/2003 | | PASS |
|
|
|
Plan modification
|
Routing - PLAN CHECK | 6/9/2003 | | 7/17/2003 | | PEND |
|
|
|
Plan Modification.
Waiting for others to approve prior to issuing permit for plan modification.
|
Case Summary (BLD) | | | 7/17/2003 | | |
|
|
|
|
Routing - PLANNING | 6/4/2003 | | 6/9/2003 | | PASS |
|
|
|
Plan modification.
Approved per Mark.
|
Routing - PLAN CHECK | 5/28/2003 | | 6/4/2003 | | |
|
|
|
plan modification
Routing to Planning
|
Plan routing begun/NEW & ADDTN | | | 5/28/2003 | | DONE |
|
|
|
Plan modification.
|
Plan Modification Accepted | | | 5/28/2003 | | DONE |
|
|
|
Plan modification * 1. To modify wall configuration around lobby.
2. Adding (2) pair of doors @ lobby.
3. To modify portion of office area ( walls & doors )
4. To modify south elevation - was part of future buildout (bld02-02667) - propsed to be included within this permit.
|
BLD-Conference | 5/14/2003 | 5/15/2003 | 5/15/2003 | A | FAIL |
Jim Sly
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Annette Moore Architect to resubmit changes for plan modification review for alternate area. 5/15/2003 12:15:08 PM
|
Plan resubmittals received | | | 5/14/2003 | | DONE |
|
|
|
received a letter of transmittal, copy of one floor plan and routed to Mike P.
|
BLD-Footing | 5/2/2003 | 5/5/2003 | 5/5/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/2/2003 at 4:17:31 PM. Contact: ###-####. Footings at alternate sections 2 and 5 OK pending MTI insp and approvals. 5/5/2003 2:35:38 PM
|
BLD-Footing | 4/29/2003 | 4/30/2003 | 4/30/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/29/2003 at 12:19:23 PM. Contact: ###-####. Footing at South wall connecting New to old Bldg......OK pending MTI spec insp and approvals. 4/30/2003 9:16:21 AM
|
BLD-Footing | 4/7/2003 | 4/8/2003 | 4/8/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/7/2003 at 12:08:02 PM. Contact: ###-####. Footing (pads) at N.W. corner of new Bldg. OK pend Special insp and appr. 4/8/2003 2:58:29 PM
|
BLD-Footing | 3/19/2003 | 3/20/2003 | 3/20/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/19/2003 at 4:24:19 PM. Contact: ###-####. Last of the foundation...OK Pending MTI insp and approvals. 3/20/2003 3:41:07 PM
|
BLD-Footing | 3/12/2003 | 3/13/2003 | 3/13/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/12/2003 at 9:33:12 AM. Contact: ###-####. Footing for bell tower, S. E. section (using as drive thru) and Misc pads OK pending MTI insp and approvals. 3/13/2003 3:21:50 PM
|
BLD-Footing | 3/7/2003 | 3/10/2003 | 3/10/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/7/2003 at 9:01:44 AM. Contact: ###-####. OK pend MTI insp and appr. 3/10/2003 4:49:20 PM
|
BLD-Footing | 3/6/2003 | 3/6/2003 | 3/6/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/6/2003 at 7:54:53 AM. Contact: ###-####. West part of South wall..... OK pending MTI insp and approvals. 3/6/2003 12:27:29 PM
|
BLD-Footing | 3/3/2003 | 3/4/2003 | 3/4/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/3/2003 at 12:48:24 PM. Contact: ###-####. MTI insp and approvals. 3/4/2003 3:54:41 PM
|
BLD-Footing | 2/27/2003 | 2/28/2003 | 2/28/2003 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung Columns at West wall and footings (for columns) at North wall near bell tower. OK pending MTI insp and approvals. 2/28/2003 3:05:53 PM
|
BLD-Footing | 2/24/2003 | 2/25/2003 | 2/25/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/24/2003 at 1:06:19 PM. Contact: ###-####. MTI 2/25/2003 10:35:38 AM
|
BLD-Foundation | 2/20/2003 | 2/21/2003 | 2/21/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/20/2003 at 12:34:02 PM. Contact: ###-####. Found wall for west end and large pads for columns and large beams spanning sanctuary. OK pend insp and appr MTI. 2/21/2003 10:36:34 AM
|
BLD-Foundation | 2/18/2003 | 2/19/2003 | 2/19/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/18/2003 at 7:08:28 AM. Contact: ###-####. OK pend. MTI insp and appr. 2/19/2003 10:16:06 AM
|
BLD-Footing | 2/14/2003 | 2/18/2003 | 2/18/2003 | A | PART |
Tom Arcoraci
|
|
|
BRIAN; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Foundation | 2/13/2003 | 2/14/2003 | 2/14/2003 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung Octagon wall (East) MTI on site. 2/14/2003 4:15:21 PM
|
BLD-Footing | 2/11/2003 | 2/12/2003 | 2/12/2003 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung East wall footings OK pending special insp and approval....(MTI) 2/12/2003 3:36:38 PM
|
BLD-Foundation | 2/5/2003 | 2/6/2003 | 2/6/2003 | A | PART |
Jim Sly
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Part of the Footings were poured on an MIS permit for Early start......MTI has been on site full time for all footings.....Have finaled MIS permit. 2/6/2003 9:49:38 AM
|
(F) Reprint permit | | | 2/6/2003 | | |
|
|
|
|
Override - Parcel Holds | | | 2/5/2003 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/5/2003 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 2/5/2003 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/13/2003 | | 1/23/2003 | | PASS |
|
|
|
Third review required. Revised sheets of 1/13/03 sent to outside eng. kmm
|
Routing - PLAN CHECK | 12/23/2002 | | 1/23/2003 | | PASS |
|
|
|
1/17/03 * Waiting for outside engineering to approve prior to issuing permit.
|
Plan resubmittals received | | | 1/23/2003 | | DONE |
|
|
|
Received three copies of revised struc. calcs., review comments and sheetsS4.2, S5.0, S6.1, S6.3. ROUTED TO MIKE P. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/23/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/23/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/23/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/23/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/23/2003 | | DONE |
|
|
|
|
Telephone call | | | 1/23/2003 | | DONE |
|
|
|
permit ready and fees due
|
Plan assigned to (M_P) | 10/7/2002 | | 1/23/2003 | | PASS |
Mike Phillips
|
|
|
1/23/2003 13:05:16 M_P - activity updated through activity BLDA022 from case BLD02-02454.
|
Plan resubmittals received | | | 1/13/2003 | | DONE |
|
|
|
Received three copies of revised sheetsT2.1, A2.1, A2.2, A2.5, A2.6, A3.2, A9.2, A12.1, S1.0, S2.0, S2.1, S2.2, S2.3, S2.4, S3.0, S3.1, S4.0, S4.1, S4.2, S4.3, S4.4, S5.0, S5.1, S6.0, S6.1, S6.2, S6.3, S7.0, three copies of reviesed struct. calcs. one copy of resubmitted narrative. Arch. put with plans and I routed one copy to outside eng. kmm
|
Routing - Erosion and Sediment | 12/19/2002 | | 12/23/2002 | | PASS |
|
|
|
ESC plan approved on ESC02-00438
|
Routing - PLAN CHECK | 11/18/2002 | | 12/19/2002 | | FAIL |
|
|
|
12/18/02 * Talked to arcitect requested additional information to be submitted for further review.
|
Routing Off Site - STRUCTURAL | 12/11/2002 | | 12/18/2002 | | FAIL |
|
|
|
Rout one set of structural plans and calculation to engineering firm for follow up review when resubmittals are received. MJP
12/11/02 Contacted PDQ to take revised plans of 12/10/02 to outside eng. kmm
12/18/02 Second review failed. Faxed correction report to architect requesting additional information be submitted for further review. Outside engineering firm is requesting to review responces.
|
Plan resubmittals received | | | 12/10/2002 | | |
|
|
|
Received two copies of revised sheets T2.1, T2.2, A2.2 A2.5, A2.6, A3.0, A3.2, A9.2, M2.1A and 5 copies of revised sheets S1.0, S2.0, S2.1, S2.2, S2.3, S2.4, S3.0, S3.1, S4.0, S4.1, S4.2, S4.3, S4.4, S5.0, S5.1, S6.0, S6.1, S6.2, S6.3, S7.0. Three copies of struct. calcs. Routed one copy to outside eng and the rest to mike p. kmm
|
Plan Review Completed(1st rev) | | | 11/18/2002 | | FAIL |
|
|
|
|
Routing - FIRE | 11/13/2002 | | 11/18/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 11/18/2002 | | 11/18/2002 | | PASS |
|
|
|
Route back to Public Works for signatures. Grading permit already issued.
|
Routing Off Site - STRUCTURAL | 10/7/2002 | | 11/13/2002 | | FAIL |
|
|
|
called pdq to send to outside engineering. dkl
Second review required by the outside engineering firm.
|
Routing - PLAN CHECK | 10/28/2002 | | 11/13/2002 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information for further review prior to issuing permit.
|
Routing - PLUMBING | 10/28/2002 | | 10/28/2002 | | PASS |
|
|
|
1. only 3 wc allowed on 3 inch waste-see detail #2 sht p3.1(recommend 4 inch to wco) with 3 inch to each wc. 2. existing 2 inch water service may require backflow protection and thermal expansion protection
|
Routing - PLANNING | 10/14/2002 | | 10/28/2002 | | PASS |
|
|
|
Approved per CUP02-00038
|
Routing - Erosion and Sediment | 10/11/2002 | | 10/14/2002 | | FAIL |
|
|
|
Does not meet requirements of BCC 8-17 or Appendix A&C of Plan Designer Manual.
Discussed with Roylance.
|
Routing - PUBLIC WORKS | 10/8/2002 | | 10/11/2002 | | FAIL |
|
|
|
Requires drainage plan revisions per Brian M.
|
Routing - PLANNING Land Div | 10/7/2002 | | 10/8/2002 | | PASS |
|
|
|
Approved. ROS 3823.
|
Plans ACCEPTED BY PLAN TECH | | | 10/7/2002 | | DONE |
|
|
|
|
Pending Assignment by JCM | 10/7/2002 | | 10/7/2002 | | DONE |
John Menard
|
|
|
10/7/2002 10:29:11 JCM - activity updated through activity BLDA170 from case BLD02-02454.
|
Application received | | | 10/4/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/4/2002 | | DONE |
|
|
|
|