(MK PLAZA I - BASMENT, 2ND, 3RD, AND 5TH FLOORS) This building is fire sprinklered to help mitigate risks associated with the 4 story atrium. To remodel areas in the basement (about 1,000 square feet), on the 2nd floor (about 6,600 square feet), on the 3rd floor (about 5,000 square feet), and on the 5th floor (about 5,800 square feet) within an existing 111,000 square foot 6 story building. Work is to include demolition of interior nonbearing walls, repair to an existing access floor system, and repair to finishes all per approved drawings and plan review conditions on file. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. Fire sprinkler and alarm related work shall require separate permitting and approval. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection3/29/20043/29/20043/29/2004 PASS
DetailsDave Hannah
DOC - Permit Expired3/29/20043/29/20043/29/2004APASS
DetailsDave Hannah
Expired by inspector at 3/29/2004 8:08:19 AM
Letter of compliance  11/10/2003 DONE
Letter of Compliance #24319 issued 11-4-03 by Barbara.
BLD-Final8/13/20038/14/20038/14/2003APASS
DetailsDave Hannah
ok for c.c 8/14/2003 10:17:12 AM
BLD-Final8/13/20038/13/20038/13/2003PCANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 8/13/2003 at 9:40:09 AM. Contact: ###-####. OUT OF TIME RESCHDULE FOR TOMORROW 8/13/2003 5:25:47 PM
FIRE-Final Inspection8/7/20038/8/20038/8/2003APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 8/7/2003 at 9:09:47 AM. Contact: ###-####.
BLD-Aging Inspection8/5/20038/5/20038/5/2003 PASS
DetailsDave Hannah
8/11/2003 9:33:27 AM work in progress 8/11/2003 9:33:39 AM
BLD-Aging Inspection6/4/20036/4/20036/4/2003 PASS
DetailsDave Hannah
work in progress 6/4/2003 10:08:10 AM
BLD-Aging Inspection4/1/20034/1/20034/1/2003 DONE
DetailsDave Hannah
work in progress 4/2/2003 2:59:54 PM
BLD-Aging Inspection1/27/20031/27/20031/27/2003 PASS
DetailsDave Hannah
work in progress 1/28/2003 4:57:38 PM
Issue PAID IN FULL permit  10/28/2002 DONE
Plan assigned to (CJW)10/11/2002 10/24/2002 PASS
DetailsCarl Westfall
10/24/2002 09:52:31 CJW - activity updated through activity BLDA022 from case BLD02-02458.
Routing - FIRE10/21/2002 10/24/2002 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  10/24/2002 DONE
Routing - PLAN CHECK10/24/2002 10/24/2002 PASS
PLANS/APPL TAKEN TO FRONT DESK  10/24/2002 PASS
Inspection Record Card- Bld  10/24/2002  
Telephone call  10/24/2002 DONE
left mess that permit is ready
Routing - PLAN CHECK10/16/2002 10/21/2002 PASS
UBC plan review started October 18, 2002 and finished October 21, 2002. The drawings were approved with conditions. See the conditions list.
Routing - PUBLIC WORKS10/11/2002 10/16/2002 PASS
Plans ACCEPTED BY PLAN TECH  10/8/2002 DONE
Application received  10/7/2002  
Recd Pcfee & Taken To Pln CK  10/7/2002 DONE
Fee Review-notes10/7/200210/7/2002