Case Summary (BLD) | | | 5/21/2009 | | DONE |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 5/21/2009 | | DONE |
Tisha Gallop
|
|
|
|
PubWorks Occupancy Approval | 1/18/2005 | 1/18/2005 | 1/18/2005 | | DONE |
|
|
|
No final inspection, occupancy was signed without our approval. Drive-by showed project complete 1/18/05 R.Rokovitz
|
Fee Review-notes | 10/8/2002 | 10/8/2002 | 8/10/2004 | | DONE |
|
|
|
|
Permanent Occupancy | | 9/18/2003 | 9/18/2003 | | DONE |
|
|
|
|
BLD-Final | 9/17/2003 | 9/18/2003 | 9/18/2003 | A | PASS |
Russ Owen
|
|
|
cameron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok perm oc 9/17/2003 6:55:15 PM
|
BLD-Final | 9/17/2003 | 9/18/2003 | 9/18/2003 | A | PASS |
Russ Owen
|
|
|
cameron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok perm oc 9/17/2003 6:55:15 PM
|
First Notice | | 9/18/2003 | 9/18/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/18/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9806 issued 9-18-03 to the Alzheimers Care Facility.
|
Code Occupancy Approval | | | 9/12/2003 | | PASS |
|
|
|
LOOKS TO BE IN COMPLIANCE WITH DRH02-00079 FINAL SIGNED OFF.
|
BLD-Final | 9/4/2003 | 9/5/2003 | 9/5/2003 | A | CANC |
Russ Owen
|
|
|
CAMRON; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
Temporary occupancy | | | 9/5/2003 | | DONE |
|
|
|
Temp. Occ. Cert. #4993 issued 9-5-03 to the Alzheimers Care Facility, area #1.
|
FIRE-Final Inspection | 9/3/2003 | 9/4/2003 | 9/4/2003 | A | FAIL |
Troy Cobbley
|
|
|
cameron; Phone #: ###-#### Re-install the covers on the duct smoke detectors 9/4/2003 9:43:18 AM
|
BLD-Final | 9/3/2003 | 9/4/2003 | 9/4/2003 | A | CANC |
Russ Owen
|
|
|
cameron; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Final | 9/3/2003 | 9/4/2003 | 9/4/2003 | P | PART |
Russ Owen
|
|
|
cameron; Phone #: ###-#### Internet Inspection Request from: Annette Moore OK for a temp oc needes all required signatures on card for a PERM OC. 9/4/2003 12:32:05 AM
|
FIRE-Final Inspection | 9/4/2003 | 9/4/2003 | 9/4/2003 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety and fire sprinklers finaled 9/4/2003 1:21:11 PM
|
BLD-Final | 8/28/2003 | 9/2/2003 | 9/2/2003 | A | PART |
Russ Owen
|
|
|
cameron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Went for walk thru , needs all req signatures, and some corrections noted with contractor. 9/2/2003 11:34:46 PM
|
FIRE-Sprinkler Rough-in | 8/29/2003 | 9/2/2003 | 9/2/2003 | A | FAIL |
Troy Cobbley
|
|
|
No items on the correction notice have been corrected 9/2/2003 10:37:37 AM
|
FIRE-Final Inspection | 8/29/2003 | 9/2/2003 | 9/2/2003 | A | FAIL |
Troy Cobbley
|
|
|
No items on the correction notice have been corrected 9/2/2003 10:38:57 AM
|
FIRE-Final Inspection | 8/28/2003 | 8/29/2003 | 8/29/2003 | A | FAIL |
Troy Cobbley
|
|
|
repair emergency light in the north dining area, provide emergency light in the visiting area 8/29/2003 2:33:42 PM
|
FIRE-Final Inspection | 8/28/2003 | 8/29/2003 | 8/29/2003 | A | FAIL |
Troy Cobbley
|
|
|
repair emergency light in the north dining area, provide emergency light in the visiting area 8/29/2003 2:33:42 PM
|
Code Occupancy Approval Temp | 8/28/2003 | 8/27/2003 | 8/27/2003 | A | DONE |
Scott M.Brown
|
|
|
BOND IN PLACE FOR LANDSCAPE TEMP OCCUPANCY SIGNED OFF. 8/28/2003 9:53:57 AM
|
BLD-Framing/Rough-in | 5/13/2003 | 5/14/2003 | 5/14/2003 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/13/2003 at 4:46:15 PM. Contact: ###-####. Extension of 5/8 gyp membrane around valve boxes (Laundry), and Boxed enclosures above ceiling speakers appears OK. 5/14/2003 9:56:18 AM
|
BLD-Framing/Rough-in | 5/12/2003 | 5/13/2003 | 5/13/2003 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 5/12/2003 at 7:55:32 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/11/2003 | 5/12/2003 | 5/12/2003 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 5/11/2003 at 8:57:58 PM. Contact: ###-####.needs speaker cans and some penetrations protected. 5/12/2003 10:45:15 AM
|
BLD-Framing/Rough-in | 5/12/2003 | 5/12/2003 | 5/12/2003 | P | PART |
Russ Owen
|
|
|
CAMERON; Phone #: ###-#### Internet Inspection Request from: Annette Moore.Ok to insulate all items complete except speakers not yet in boxes in hall. 5/12/2003 3:43:14 PM
|
BLD-Framing/Rough-in | 5/8/2003 | 5/9/2003 | 5/9/2003 | P | PART |
Russ Owen
|
|
|
###-#### Still has some areas to address went over this with contractor. 5/9/2003 3:38:27 PM 5/9/2003 3:39:14 PM
|
BLD-Framing/Rough-in | 5/7/2003 | 5/8/2003 | 5/8/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 5/7/2003 at 4:54:53 PM. Contact: ###-####.Meet with all trades, contractor and fire caulk rep about penetrations. 5/8/2003 11:28:00 AM
|
BLD-Framing/Rough-in | 5/7/2003 | 5/7/2003 | 5/7/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 5/7/2003 at 1:07:29 AM. Contact: ###-####. Went to job site, and talked with electrician and plumber about fire stoping. I have not yet been provided all of the various fire stoping details. I spoke with Cameron this moring about this. Also there are items in the ceiling that need to be addressed. Note: fire stoping was brought up at the first framing inspection when the only piping in the building was some abs vent pipe. Which was around the 14th of april. This is not ready for a frame inspection as I should not have to be adressing these issues they should have allready had these items completed, as this is a common 1 hour fire resistive building I should not have to be the one to instruct them how to maintaing the fire resistive construction. 5/7/2003 2:58:02 PM
|
BLD-Framing/Rough-in | 5/5/2003 | 5/6/2003 | 5/6/2003 | A | PART |
Russ Owen
|
|
|
Trusses ok need fire resistive assemblies. for products. 5/6/2003 2:41:08 PM
|
BLD-Framing/Rough-in | 5/2/2003 | 5/5/2003 | 5/5/2003 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 5/2/2003 at 5:35:59 PM. Contact: ###-####.out of time. 5/5/2003 5:44:59 PM
|
BLD-Framing/Rough-in | 5/1/2003 | 5/2/2003 | 5/2/2003 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 5/1/2003 at 12:12:47 PM. Contact: ###-####. Needs other trades before. calling for framing. called and left message. 5/2/2003 4:44:32 PM
|
BLD-Framing/Rough-in | 4/21/2003 | 4/21/2003 | 4/21/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 4/21/2003 at 6:53:36 AM. Contact: ###-####.ext drywall ok. 4/22/2003 10:26:01 AM
|
BLD-Framing/Rough-in | 4/17/2003 | 4/18/2003 | 4/18/2003 | A | PART |
Russ Owen
|
|
|
Ok to drywall front 4/18/2003 11:35:56 AM
|
BLD-Framing/Rough-in | 4/17/2003 | 4/17/2003 | 4/17/2003 | P | PART |
Russ Owen
|
|
|
camron; Phone #: ###-#### Internet Inspection Request from: Darla Downs. Rear wall ok frontwall needs addl staples. 4/18/2003 10:38:12 AM
|
FIRE-Conference | 4/15/2003 | 4/16/2003 | 4/16/2003 | A | CANC |
Troy Cobbley
|
|
|
conference was set up by the plumbing contractor . He wanted to know how to install the fire caulking for his plumbing pipe penatrations. I spoke to Dennis with Meridian Plumbling and told him to install it per the manufacturers recommendations and also gave him Russ Owens phone number 4/16/2003 4:20:03 PM
|
BLD-Framing/Rough-in | 4/15/2003 | 4/16/2003 | 4/16/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 4/15/2003 at 8:14:50 PM. Contact: ###-####. roof only ok to cover. 4/16/2003 4:50:02 PM
|
BLD-Framing/Rough-in | 4/14/2003 | 4/15/2003 | 4/15/2003 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 4/14/2003 at 7:45:11 PM. Contact: ###-####.posted a c/n. 4/16/2003 11:02:31 AM
|
BLD-Framing/Rough-in | 4/11/2003 | 4/14/2003 | 4/14/2003 | A | FAIL |
Russ Owen
|
|
|
posted c/n shear walls and roof. 4/14/2003 1:26:36 PM
|
FIRE-Supply Line Cover | 4/13/2003 | 4/14/2003 | 4/14/2003 | P | PASS |
Troy Cobbley
|
|
|
Underground sprinkler piping is ok to cover 4/14/2003 2:04:35 PM
|
BLD-Footing | 3/18/2003 | 3/19/2003 | 3/19/2003 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 3/18/2003 at 7:27:03 PM. Contact: ###-####. BILL CALLED TO CANC THIS INSPECTION, NOT READY.
|
BLD-Footing | 3/17/2003 | 3/18/2003 | 3/18/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 3/17/2003 at 5:08:30 PM. Contact: ###-####. interior 3/18/2003 11:07:48 AM
|
BLD-Footing | 3/14/2003 | 3/17/2003 | 3/17/2003 | A | NR |
Russ Owen
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Annette Moore. interior footings. 3/17/2003 10:23:43 AM
|
BLD-Footing | 3/17/2003 | 3/17/2003 | 3/17/2003 | P | FAIL |
Russ Owen
|
|
|
c/n posted in job trailer. 3/17/2003 4:04:40 PM
|
FIRE-Conference | 2/20/2003 | 2/21/2003 | 2/21/2003 | A | DONE |
Troy Cobbley
|
|
|
cameron; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Foundation | 2/18/2003 | 2/19/2003 | 2/19/2003 | A | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung out of time 2/19/2003 10:27:25 AM
|
BLD-Foundation | 2/19/2003 | 2/19/2003 | 2/19/2003 | P | PASS |
Dave Hannah
|
|
|
rebar in, forms 95% ,contractor and I went over hold down locations 2/19/2003 5:37:25 PM
|
BLD-Footing | 2/14/2003 | 2/14/2003 | 2/14/2003 | P | PART |
Russ Owen
|
|
|
bill; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie .footing 2/14/2003 4:53:47 PM
|
BLD-Footing | 2/6/2003 | 2/7/2003 | 2/7/2003 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 2/6/2003 at 6:07:21 PM. Contact: ###-####.
|
(F) Reprint permit | | | 2/3/2003 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/31/2003 | | DONE |
|
|
|
|
Telephone call | | | 1/23/2003 | | DONE |
|
|
|
permit ready and fees due
|
Routing - PLANNING Land Div | 1/22/2003 | | 1/22/2003 | | PASS |
|
|
|
Approved as per ROS 5930.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/22/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/22/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/22/2003 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 10/9/2002 | | 1/22/2003 | | PASS |
Mike Otto
|
|
|
1/22/2003 15:37:49 MLO - activity updated through activity BLDA022 from case BLD02-02471.
|
Routing Off Site - C.D.H | 1/17/2003 | | 1/21/2003 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 1/13/2003 | | 1/16/2003 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 1/16/2003 | | 1/16/2003 | | FAIL |
|
|
|
Still need recorded deed with legal description of entire parcel. Need new tax parcel #.
|
Routing - FIRE | 1/3/2003 | | 1/3/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/30/2002 | | 1/3/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 12/30/2002 | | DONE |
|
|
|
Received two sets of resubmittal sheets A0-1, A0-2, A1-1, A2-0, A2-1, A2-2, A2-3, A2-4, A2-5, A2-6, A2-7, A4-1, A4-2, A5-1, A5-2, A5-3, A5-4, A5-5, A6-1, A6-2, A7-1, A7-2, A7-4, A7-5, A7-7, A8-3, L-1, C1-1, M-1, M-2, P-1, P-2, M/P-1, E-1, E2-2, E2-3, E3-1, E3-2, E3-3, E4-2, E4-3, with (1) cover letter with comments, and (1) letter from Paramount Health Care. Routed to Mike Otto.
|
Routing - PUBLIC WORKS | 12/26/2002 | | 12/26/2002 | | FAIL |
|
|
|
Requires drainage plan.
|
Routing - FIRE | 11/5/2002 | | 11/13/2002 | | FAIL |
|
|
|
copy of review faxed to Teal architect
|
Routing - PLAN CHECK | 10/28/2002 | | 11/5/2002 | | FAIL |
|
|
|
corrections sent to architect
|
Routing - PLUMBING | 10/24/2002 | | 10/28/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 10/17/2002 | | 10/23/2002 | | PASS |
|
|
|
Design Review approved per DRH02-79. Pending CU Planner's signature.
|
Routing - Erosion and Sediment | 10/16/2002 | | 10/17/2002 | | PASS |
|
|
|
ESC plan approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 10/9/2002 | | 10/16/2002 | | FAIL |
|
|
|
Requires drainage plan.
|
Plans ACCEPTED BY PLAN TECH | | | 10/9/2002 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/9/2002 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 10/9/2002 | | 10/9/2002 | | FAIL |
|
|
|
Need recorded deed with legal description of entire parcel. Need new tax parcel #. Called Roger Smith at Pinnacle Engineers on October 9, 2002.
|
Application received | | | 10/8/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/8/2002 | | DONE |
|
|
|
|