BLD-Final | 2/19/2003 | 2/19/2003 | 2/19/2003 | P | PASS |
Jim Sly
|
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie C/C issued. 2/19/2003 4:01:06 PM
|
DOC - Permit Finaled | 2/19/2003 | 2/19/2003 | 2/19/2003 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 2/19/2003 4:01:13 PM
|
BLD-Framing/Rough-in | 12/26/2002 | 12/26/2002 | 12/26/2002 | P | PASS |
Russ Owen
|
|
|
TODD- ###-#### will insulate kitchen at side wall. 12/26/2002 2:51:49 PM
|
BLD-Energy code compliance | 12/23/2002 | 12/24/2002 | 12/24/2002 | A | NR |
Russ Owen
|
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Marsha Smyliecorrections not made at this time. 12/24/2002 9:49:44 AM
|
BLD-Framing/Rough-in | 12/24/2002 | 12/24/2002 | 12/24/2002 | P | FAIL |
Russ Owen
|
|
|
todd- ###-####needs attic access in kitchen so that insulastion can be blown in. 12/26/2002 10:00:42 AM
|
BLD-Framing/Rough-in | 12/19/2002 | 12/20/2002 | 12/20/2002 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/19/2002 at 15:49:18. Contact: ###-####. C/N 12/20/2002 5:00:06 PM
|
BLD-Wall cover | 12/5/2002 | 12/6/2002 | 12/6/2002 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/05/2002 at 09:28:34. Contact: ###-####. Shear OK. 12/5/2002 12:57:51 PM
|
BLD-Foundation | 10/29/2002 | 10/29/2002 | 10/29/2002 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/29/2002 at 06:31:08. Contact: ###-####. wip ok 10/29/2002 8:28:38 AM
|
BLD-Footing | 10/28/2002 | 10/28/2002 | 10/28/2002 | P | PART |
Dave Hannah
|
|
|
###-#### work in progress setbacks ok crew only about 10% complete 10/28/2002 2:54:34 PM
|
Inspection Record Card- Bld | | | 10/17/2002 | | |
|
|
|
|
Telephone call | | | 10/17/2002 | | DONE |
|
|
|
talked to todd to verify plans are ready
|
Issue PAID IN FULL permit | | | 10/17/2002 | | |
|
|
|
|
Plan assigned to (DJO) | 10/16/2002 | 10/16/2002 | 10/16/2002 | | PASS |
Dan Overy
|
|
|
10/16/2002 13:03:43 DJO - activity updated through activity BLDA022 from case BLD02-02482.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/16/2002 | | |
|
|
|
|
Case Summary (BLD) | | | 10/16/2002 | | DONE |
|
|
|
|
Plan Review Report | | | 10/16/2002 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 10/16/2002 | | |
|
|
|
|
Routing - PUBLIC WORKS | 10/9/2002 | | 10/10/2002 | | PASS |
|
|
|
|
Application received | | | 10/9/2002 | | |
|
|
|
|
Routing - PLANNING | 10/9/2002 | | 10/9/2002 | | PASS |
|
|
|
need 3rd set.
|
Pending Assignment by DJO | 10/9/2002 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 10/10/2002 | | | | |
|
|
|
|