Fee Review-notes | 8/13/2003 | 8/13/2003 | 8/13/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 12/23/2002 | 12/23/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/23/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9491 issued 12-23-02 to Me Time Coffee House.
|
BLD-Final | 12/19/2002 | 12/20/2002 | 12/20/2002 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung ok for perm occ 12/20/2002 1:53:10 PM
|
FIRE-Final Inspection | 12/18/2002 | 12/19/2002 | 12/19/2002 | P | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Framing/Rough-in | 12/16/2002 | 12/16/2002 | 12/16/2002 | P | PART |
Dave Hannah
|
|
|
nick ###-####- t-bar ceiling ok to drop in panels 12/16/2002 2:43:43 PM
|
BLD-Framing/Rough-in | 11/27/2002 | 12/2/2002 | 12/2/2002 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: Amy Lawson ok to cover 12/2/2002 2:05:21 PM
|
Issue PAID IN FULL permit | | | 11/12/2002 | | |
|
|
|
|
(F) Reprint permit | | | 11/12/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/8/2002 | | 11/8/2002 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2002 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 11/8/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/8/2002 | | DONE |
|
|
|
|
Telephone call | | | 11/8/2002 | | DONE |
|
|
|
permit ready and fees due
|
Plan assigned to (JCB) | 10/25/2002 | | 11/8/2002 | | PASS |
Jason Blais
|
|
|
11/8/2002 13:32:08 JCB - activity updated through activity BLDA022 from case BLD02-02617.
|
Routing - FIRE | 11/4/2002 | | 11/7/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 10/31/2002 | | 11/4/2002 | | PASS |
|
|
|
Approved. There is enough parking left for the rest building at a 1/250 ratio as long as there are no more the 48 seats in the coffee house.
|
Plan resubmittals received | | | 11/4/2002 | | DONE |
|
|
|
Received two copies of revised sheets A-0, A-1, A-2 and A-3. One copy of response letter. Routed to Jason B. kmm
|
Plan resubmittals requested | | | 10/31/2002 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 10/30/2002 | | 10/31/2002 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Planning and Fire Dept. for review.
|
Routing - PLUMBING | 10/28/2002 | | 10/30/2002 | | PASS |
|
|
|
WATER HEATER NEEDS THERMAL EXPANSION PROTECTION
|
Routing - PUBLIC WORKS | 10/25/2002 | | 10/28/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/25/2002 | | DONE |
|
|
|
|
First Notice | 10/24/2002 | 10/24/2002 | 10/24/2002 | | DONE |
|
|
|
|
Application received | | | 10/24/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/24/2002 | | |
|
|
|
|