Case Summary (BLD) | | | 1/11/2012 | | |
|
|
|
|
Fee Review-notes | 10/30/2002 | 10/30/2002 | 8/10/2004 | | DONE |
|
|
|
|
Permanent Occupancy | | 5/15/2003 | 5/15/2003 | | DONE |
|
|
|
|
BLD-Final | 5/13/2003 | 5/15/2003 | 5/15/2003 | A | PASS |
Carl Dependahl
|
|
|
richard; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
FIRE-Final Inspection | 5/14/2003 | 5/15/2003 | 5/15/2003 | A | PASS |
Rick Jackson
|
|
|
richard; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
First Notice | | 5/15/2003 | 5/15/2003 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 5/15/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9649 issued 5-15-03 to Kinko's Copies. Outstanding fee issue approved per Linda Hartwell.
|
FIRE-Final Inspection | 5/13/2003 | 5/14/2003 | 5/14/2003 | A | FAIL |
Rick Jackson
|
|
|
richard; Phone #: ###-#### Internet Inspection Request from: Barbara Moore remote LED's for AHU shutdown don't reset the units; will need to test two detectors for the two new AHU's mounted on roof 5/14/2003 1:55:19 PM
|
FIRE-Final Inspection | 5/8/2003 | 5/9/2003 | 5/9/2003 | A | FAIL |
Rick Jackson
|
|
|
richard; Phone #: ###-#### Internet Inspection Request from: Annette Moore emergency lights not working; need to test duct detectors for AHU shutdown (two new units on roof); extinguisher mounted too high and need current tag on northeast extinguisher 5/9/2003 4:46:41 PM
|
BLD-Final | 5/8/2003 | 5/9/2003 | 5/9/2003 | P | FAIL |
Dave Hannah
|
|
|
richard; Phone #: ###-#### Internet Inspection Request from: Annette Moore c/n on site 5/12/2003 8:40:03 AM
|
Print Occupancy Form | | | 4/29/2003 | | DONE |
|
|
|
|
BLD-Wall cover | 4/9/2003 | 4/9/2003 | 4/9/2003 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 4/9/2003 at 7:13:29 AM. Contact: ###-####....bathroom clg ok, rec'd arch's letter...beam brg ok...existing pier below . 4/9/2003 3:15:57 PM
|
BLD-Other | 4/4/2003 | 4/7/2003 | 4/7/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/4/2003 at 3:23:58 PM. Contact: ###-####. restaroom walls only ok/ break rm walls only ok.. 4/7/2003 10:23:19 AM
|
BLD-Framing/Rough-in | 3/27/2003 | 3/28/2003 | 3/28/2003 | A | PART |
Carl Dependahl
|
|
|
richard; Phone #: ###-#### Internet Inspection Request from: Annette Moore part, conf rm wall only; c/n re post/beam brg for accordian door, need other trades at other areas. 3/28/2003 1:30:32 PM
|
Issue PAID IN FULL permit | | | 3/17/2003 | | |
|
|
|
|
Plan assigned to (JCB) | 11/4/2002 | | 2/13/2003 | | PASS |
Jason Blais
|
|
|
2/13/2003 10:51:32 JCB - activity updated through activity BLDA022 from case BLD02-02663.
|
Routing - PLAN CHECK | 2/3/2003 | | 2/13/2003 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2003 | | PASS |
|
|
|
|
Print Occupancy Form | | | 2/13/2003 | | DONE |
|
|
|
|
Telephone call | | | 2/13/2003 | | DONE |
|
|
|
permit ready
|
Plan resubmittals requested | | | 2/3/2003 | | |
|
|
|
Plan addendums required for further review.
|
Telephone Call | | | 2/3/2003 | | |
|
|
|
Called architect representative, Mark, and let him know of some issues that were either not addressed or that were not adequately addressed. He said he would address the issues and provide some addendum pages.
|
Plan resubmittals received | | | 1/29/2003 | | DONE |
|
|
|
Received two copies of revised sheets T-1, D-1, A-1, A-2, A-3.0, A-3.1, A-4, A-9, M-1, M-2, M-3, P-1, P-2, P-3, DC-1, E-1, E-2, E-3. Routed to Jason B. kmm
|
Plan Review Completed(1st rev) | | | 11/25/2002 | | FAIL |
|
|
|
|
Routing - FIRE | 11/21/2002 | | 11/25/2002 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 11/21/2002 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 11/5/2002 | | 11/21/2002 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review. Plans routed to Fire Dept. for review.
|
Routing - PUBLIC WORKS | 11/4/2002 | | 11/5/2002 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/30/2002 | | DONE |
|
|
|
Plans not fully dimensioned
|
Application received | | | 10/30/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/30/2002 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/25/2002 | | 2/3/2002 | | FAIL |
|
|
|
Not all issues from original plan review report were addressed or addressed adequately. Called architect representative, Mark, and let him know of deficient issues. He said he would address and provide addendum pages.
|