Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD02-02670
StatusFinaled
Name TAHOE CONSTRUCTION
Site Address 5273 E ARROW JUNCTION DR
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a three bedroom, two and half bathroom 1824 sq. ft. two story single family dwelling (905 sq. ft. first floor/919 sq. ft. second floor) with a attached 542 sq. ft. two car garage, a 87 sq. ft. covered back porch and a 112 sq. ft. covered front porch. Per approved plans, engineering and requirement list. CUP98-116 and CUP01-103 per Angie Thomas with Planning and Zoning. PC#653 (SAM)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/29/20034/30/20034/30/2003PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/29/2003 at 4:43:56 PM. Contact: ###-####.c.c # 22908 issued 4/30/2003 4:04:59 PM
DOC - Permit Finaled4/30/20034/30/20034/30/2003PPASS
DetailsDave Hannah
Finaled by inspector at 4/30/2003 4:05:01 PM
BLD-Final2/26/20032/26/20032/26/2003PFAIL
DetailsDave Hannah
Scheduled by a contractor via Hello! on 2/26/2003 at 11:23:26 AM. Contact: ###-####. c/n on site 2/26/2003 2:59:38 PM
BLD-Energy code compliance1/7/20031/8/20031/8/2003APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 01/07/2003 at 18:39:18. Contact: ###-####. ok to cover 1/8/2003 9:11:17 AM
BLD-Framing/Rough-in12/30/200212/31/200212/31/2002APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/30/2002 at 16:10:58. Contact: ###-####.ok to insulate 12/31/2002 9:37:28 AM
BLD-Other12/16/200212/17/200212/17/2002APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/16/2002 at 11:18:37. Contact: ###-####.ok to cover ext 12/17/2002 9:59:27 AM
BLD-Footing11/14/200211/15/200211/15/2002APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/14/2002 at 16:04:52. Contact: ###-####.
BLD-Foundation11/14/200211/15/200211/15/2002APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/14/2002 at 16:05:25. Contact: ###-####. work in progress rebar is in forms 50% complete 11/15/2002 11:05:51 AM
BLD-Footing11/13/200211/14/200211/14/2002PPASS
DetailsDave Hannah
clint; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
Routing - PLAN CHECK11/4/2002 11/13/2002 DONE
Plan assigned to (SAM)11/12/2002 11/13/2002 PASS
DetailsSteve Munroe
11/13/2002 08:40:21 SAM - activity updated through activity BLDA022 from case BLD02-02670.
Case Summary (BLD)  11/13/2002  
Plan Review Report  11/13/2002  
PLANS/APPL TAKEN TO FRONT DESK  11/13/2002 DONE
Inspection Record Card- Bld  11/13/2002 DONE
Telephone call  11/13/2002 DONE
CALLED 11-13-02
Issue PAID IN FULL permit  11/13/2002 DONE
Pending Assignment by DJO10/31/2002 11/12/2002 DONE
DetailsDan Overy
11/12/2002 10:55:09 SAM - activity updated through activity BLDA183 from case BLD02-02670.
Routing - PLANNING10/31/2002 11/4/2002 PASS
Routing - PUBLIC WORKS11/4/2002 11/4/2002 PASS
Application received  10/31/2002