Permanent occupancy UNPAID FEE | | | 4/11/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9616 issued to Commercial Tire on 4-11-03 aml
|
Permanent Occupancy | | 4/10/2003 | 4/10/2003 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/10/2003 | 4/10/2003 | 4/10/2003 | P | PASS |
Rick Jackson
|
|
|
JERRY; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Final | 4/10/2003 | 4/10/2003 | 4/10/2003 | P | PASS |
Steven Webb
|
|
|
JERRY; Phone #: ###-#### Internet Inspection Request from: Darla Downs Received MTI special inspection report on anchor bolts "pull test". 4/10/2003 1:38:38 PM
|
BLD-Framing/Rough-in | 2/25/2003 | 2/26/2003 | 2/26/2003 | A | PASS |
Tom Arcoraci
|
|
|
JERRY; Phone #: ###-#### Internet Inspection Request from: Marsha S ok to cover pending mti on bolts per plan
2/26/2003 9:00:09 AM 2/26/2003 9:15:03 AM
|
BLD-Concrete | 1/21/2003 | 1/22/2003 | 1/22/2003 | A | PART |
Carl Dependahl
|
|
|
###-#### call first to meet there...col pads ok 1/22/2003 1:56:58 PM
|
BLD-Foundation | 1/22/2003 | 1/22/2003 | 1/22/2003 | P | PART |
Carl Dependahl
|
|
|
masonry...1st lift cols...steel ok 1/22/2003 2:55:30 PM
|
BLD-Footing | 1/14/2003 | 1/15/2003 | 1/15/2003 | A | NR |
Carl Dependahl
|
|
|
jerry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...complete forms. 1/15/2003 12:59:53 PM
|
BLD-Footing | 1/14/2003 | 1/15/2003 | 1/15/2003 | A | NR |
Carl Dependahl
|
|
|
jerry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Footing | 1/15/2003 | 1/15/2003 | 1/15/2003 | P | PART |
Carl Dependahl
|
|
|
jerry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...ftg ok 1/15/2003 2:47:32 PM
|
BLD-Conference | 1/10/2003 | 1/10/2003 | 1/10/2003 | P | PASS |
Carl Dependahl
|
|
|
need to expose fnd to determine req's for request, call when ready 1/13/2003 8:39:05 AM
|
Issue PAID IN FULL permit | | | 12/31/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/23/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/23/2002 | | DONE |
|
|
|
|
Telephone call | | | 12/23/2002 | | DONE |
|
|
|
permit ready and fees due
|
Plan assigned to (R_H) | 11/14/2002 | | 12/20/2002 | | PASS |
|
|
|
12/20/2002 15:32:08 RMH - activity updated through activity BLDA022 from case BLD02-02760.
|
Routing - PLAN CHECK | 12/11/2002 | | 12/20/2002 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/20/2002 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2002 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/19/2002 | | DONE |
|
|
|
Received three sets of resubmittal sheets A3.00, A3.01, with cover letter. Routed to Ron Hill.
|
Routing - FIRE | 12/5/2002 | | 12/10/2002 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 12/10/2002 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 11/20/2002 | | 12/5/2002 | | FAIL |
|
|
|
Faxed and mailed requirements to the architect, Routed plans to the fire department 12/05/02.
|
Case Summary (BLD) | | | 12/5/2002 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 11/19/2002 | | 11/19/2002 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PLANNING | 11/18/2002 | | 11/19/2002 | | PASS |
|
|
|
Approved per CZC02-172.
|
Routing - PUBLIC WORKS | 11/14/2002 | | 11/18/2002 | | PASS |
|
|
|
|
Additional plans submitted | | | 11/13/2002 | | DONE |
|
|
|
Received two copies of EC-1. Attached to plans.
|
Plans ACCEPTED BY PLAN TECH | | | 11/12/2002 | | DONE |
|
|
|
|
First Notice | 11/8/2002 | 11/8/2002 | 11/8/2002 | | DONE |
|
|
|
|
Application received | | | 11/8/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/8/2002 | | DONE |
|
|
|
|