BLD-Final | 7/17/2003 | 7/17/2003 | 7/17/2003 | A | PASS |
Dave Hannah
|
|
|
c.c isued by jim storey 7/17/2003 9:52:04 AM
|
DOC - Permit Finaled | 7/17/2003 | 7/17/2003 | 7/17/2003 | A | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 7/17/2003 9:52:06 AM
|
BLD-Final | 7/15/2003 | 7/15/2003 | 7/15/2003 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/15/2003 at 6:29:32 AM. house is all locked up no access 7/15/2003 1:50:31 PM
|
DOC - Permit Finaled | 7/15/2003 | 7/15/2003 | 7/15/2003 | A | PASS |
Jim Storey
|
|
|
Finaled by inspector at 7/15/2003 11:15:34 AM
|
BLD-Final | 7/7/2003 | 7/7/2003 | 7/7/2003 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 7/7/2003 at 8:51:41 AM. C/N posted......N Mill Spur R Canopy follow around...... 7/7/2003 4:59:58 PM
|
BLD-Wall cover | 4/9/2003 | 4/10/2003 | 4/10/2003 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/9/2003 at 5:07:20 PM. ok to cover around fire place 4/10/2003 9:24:12 AM
|
BLD-Wall cover | 4/8/2003 | 4/8/2003 | 4/8/2003 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/8/2003 at 8:31:10 AM. fire blocking around fire place not finished 4/8/2003 3:37:49 PM
|
BLD-Wall cover | 4/7/2003 | 4/7/2003 | 4/7/2003 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/7/2003 at 6:39:31 AM. fire place venting was changed needs to be furred out and fire blocked 4/7/2003 10:14:30 AM
|
BLD-Energy code compliance | 4/7/2003 | 4/7/2003 | 4/7/2003 | P | PART |
Dave Hannah
|
|
|
ok to start sheetrock all but for around fire place
|
Telephone call | | | 4/4/2003 | | DONE |
|
|
|
per bill with brighton throw away plans/already has a set
|
BLD-Framing/Rough-in | 4/3/2003 | 4/3/2003 | 4/3/2003 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/3/2003 at 10:00:41 AM.
|
BLD-Framing/Rough-in | 3/24/2003 | 3/24/2003 | 3/24/2003 | P | PART |
Dave Hannah
|
|
|
dan; Phone #: ###-#### Internet Inspection Request from: Annette Moore shear ok to cover ext 3/24/2003 2:18:14 PM
|
BLD-Foundation | 2/25/2003 | 2/26/2003 | 2/26/2003 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/25/2003 at 5:05:16 PM. Contact: ###-####.
|
BLD-Footing | 2/25/2003 | 2/25/2003 | 2/25/2003 | P | PART |
Dave Hannah
|
|
|
randy ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie work in progress 10% complete 2/25/2003 4:55:37 PM
|
Case Summary (BLD) | | | 2/24/2003 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/18/2003 | | DONE |
|
|
|
|
Telephone call | | | 2/12/2003 | | DONE |
|
|
|
CALLED 2-12-03 3:09 LEFT MESSAGE TO PICK PLANS, UP OR POSSIBLY BE VOIDED OUT IN TWO WEEKS...DARLA
|
Plan assigned to (DJO) | 11/26/2002 | 11/26/2002 | 11/27/2002 | | PASS |
Dan Overy
|
|
|
11/27/2002 11:16:37 DJO - activity updated through activity BLDA022 from case BLD02-02795.
|
Plan Reviewer's activity | | | 11/27/2002 | | DONE |
|
|
|
received truss type package from brighton, ok to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/27/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/27/2002 | | DONE |
|
|
|
|
Telephone call | | | 11/27/2002 | | DONE |
|
|
|
permit ready and fees due
|
Plans ACCEPTED BY PLAN CHECK | | | 11/26/2002 | | |
|
|
|
|
Case Summary (BLD) | | | 11/26/2002 | | PEND |
|
|
|
|
Plan Review Report | | | 11/26/2002 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 11/26/2002 | | PEND |
|
|
|
need additional information on roof framing.
|
Routing - PLANNING | 11/15/2002 | | 11/19/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 11/19/2002 | | 11/19/2002 | | PASS |
|
|
|
|
Application received | | | 11/15/2002 | | |
|
|
|
|
Pending Assignment by DJO | 11/15/2002 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 11/19/2002 | | | | |
|
|
|
|