Permit Information
Permit NumberBLD02-02801
StatusFinaled
Name LITZINGER CONSTRUCTION CO
Site Address 9114 W CORY LN
Project NameCory Street Apartments
Customer Number 
ePlanReviewNo
Description
(Grading and Drainage)-To grub, clean, excavate, grade, import, and compact site earth materials in preparation for the future construction of the Cory Street Apartments. To install curb, gutter, and paving in accordance with the grading and drainage plans approved by the public works department. Related site utilities included in this permit. No demolition, installation, or building construction is allowed under this permit. Refer to BLD02-02313, BLD02-02314. DRH02-00107 CUP02-00073 PC#728-02
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection2/18/20032/18/20032/18/2003 PASS
DetailsJim Sly
DOC - Permit Finaled2/18/20032/18/20032/18/2003APASS
DetailsJim Sly
Finaled by inspector at 2/18/2003 8:34:15 AM
Routing - FIRE12/12/2002 12/12/2002 PASS
DetailsBill Alexander
Revised plans. (No Fire Protection Suystem Requirements) Revised access approved by Dave Miller attached.
Plan assigned to (M_P)11/15/200211/15/200211/19/2002 PASS
DetailsMike Phillips
11/19/2002 14:13:51 M_P - activity updated through activity BLDA022 from case BLD02-02801.
PLANS/APPL TAKEN TO FRONT DESK  11/19/2002 DONE
Print Pending Permit.LaserJet4  11/19/2002 DONE
Case Summary (BLD)  11/19/2002 DONE
Issue PAID IN FULL permit  11/19/2002 DONE
Routing - PLAN CHECK11/4/2002 11/19/2002 PASS
Issue grading permit per Marlene w/out plans.
Routing - FIRE11/18/2002 11/18/2002 PASS
DetailsBill Alexander
Application received  11/15/2002  
Plans ACCEPTED BY PLAN TECH  11/15/2002 DONE
Routing - PLUMBING11/1/2002 11/4/2002 PASS
Routing - PUBLIC WORKS10/30/2002 11/1/2002 PASS
Routing - PLANNING10/11/2002 10/28/2002 PASS
approved per DRH02-107
Routing - Erosion and Sediment10/7/2002 10/11/2002 PASS
ESC Plan approved with attached conditions.
Routing - PLANNING Land Div9/24/2002 9/26/2002 PASS
Received deed verifying split prior to annexation in 94, setbacks ok.