Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD02-02805
StatusFinaled
Name ESP FUTURE LTD
Site Address 770 W AMITY RD
Project NameLake City International
Customer Number 
ePlanReviewNo
Description
A permit to install a new 1440 sq. ft. one story modular office building with footing, and concrete sidewalk with landings at doors. Other work inlcudes site improvements any paving and landscaping. Work per approved plans and attachments, DRH02-00106 Unit B State Tag Number 6915cc PA# 11164cc
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes11/15/200211/15/20028/10/2004 DONE
First Notice 9/29/20039/29/2003 DONE
Permanent occupancy  9/29/2003 DONE
Perm. Occ. Cert. #9821 issued 9-29-03 to Lake City International.
Permanent Occupancy 9/26/20039/26/2003 DONE
Details
PubWorks Occupancy Approval9/24/20039/24/20039/24/2003 DONE
Drainage project complete, signed permanent occupancy 9/24/03. R.Rokovitz
BLD-Final8/22/20038/22/20038/22/2003APASS
DetailsJim Storey
final ok
Temporary occupancy  8/22/2003 DONE
Temp. Occ. Cert. #4987 issued 8-22-03 to Lake City International by Barbara.
Code Occupancy Approval8/22/20038/21/20038/21/2003APASS
DetailsWm. Michael Meloy
Compliance met. 8/22/2003 10:01:39 AM
FIRE-Final Inspection8/21/20038/21/20038/21/2003PPASS
DetailsRick Jackson
ext 11- rob; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Final8/19/20038/20/20038/20/2003AFAIL
DetailsJim Storey
rob; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie need occ.card bsigned off. 8/20/2003 10:28:50 AM
FIRE-Final Inspection8/20/20038/20/20038/20/2003PFAIL
DetailsRick Jackson
###-#### ext 11 rob needs fire extinguisher - left correction notice at reception 8/20/2003 4:14:32 PM
BLD-Aging Inspection7/30/20037/30/20037/30/2003 PASS
DetailsJim Storey
wip 7/30/2003 7:46:43 AM
BLD-Foundation5/29/20035/30/20035/30/2003APASS
DetailsJim Storey
###-####
BLD-Footing5/20/20035/21/20035/21/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/20/2003 at 11:34:55 AM. Contact: ###-####. unable to locate site. 5/21/2003 4:50:20 PM
Issue PAID IN FULL permit  4/28/2003  
Inspection Record Card- Bld  4/11/2003  
Print Occupancy Form  4/11/2003  
Routing - PLAN CHECK4/7/2003 4/10/2003 PASS
PLANS/APPL TAKEN TO FRONT DESK  4/10/2003 DONE
Plan assigned to (MLO)11/20/2002 4/10/2003 PASS
DetailsMike Otto
4/10/2003 15:08:08 MLO - activity updated through activity BLDA022 from case BLD02-02805.
Plan resubmittals received  4/9/2003 DONE
state tag numbers
Routing - PLAN CHECK3/21/2003 4/1/2003 PEND
Project now has two trailers not connected requires separate permits, architect notified. MLO
Plan resubmittals received  3/21/2003 DONE
Received two copies of revised sheets A-0, S-1, S-2, A-2, A-2.1, A-3, A-4, SITE PLAN, ESC PLAN, FLOOR PLAN SHEET 1, 2, SITE PLAN 1 OF 9, and one copy of cover letter routed to Mike O. kmm
Application received  12/23/2002  
Routing - PLANNING Land Div12/23/2002 12/23/2002 PASS
Parcel issued building permit by City of Boise #1027556 in 1988. No further land divisions since 1988.
Routing - PLANNING12/11/2002 12/12/2002 PASS
Approved per DRH02-106 and as noted on plans and per attached landscape plan.
Routing - PLAN CHECK12/12/2002 12/12/2002 NR
Plan resubmittals received  12/11/2002 DONE
Received two coies of revised sheets ESC Plan and Landscape plan. Routed to Mike O. kmm
Routing - PLAN CHECK12/9/2002 12/10/2002 FAIL
corrections not done new letter sent to applicant. MLO
Plan resubmittals requested  12/10/2002 DONE
acceptable plans for review.
Plan resubmittals received  12/9/2002 DONE
Received two copies of resubmittal sheets "1 OF 9", engineering sheets F-MULTI and D-1, and cover letter with comments. Routed to Mike Otto.
Plan Review Completed(1st rev)  12/9/2002 FAIL
Routing - FIRE12/4/2002 12/9/2002 PASS
Routing - PLAN CHECK12/3/2002 12/4/2002 FAIL
Plans unacceptable for review. Plan submittal requirements sent to applicant
Routing - PLUMBING12/2/2002 12/3/2002 PASS
See plumbing plan review #2380

Routing - PLANNING11/26/2002 12/2/2002 FAIL
Plans do not comply with DRH02-106 conditions of approval #1a and #1b.
Routing - Erosion and Sediment11/25/2002 11/26/2002 PASS
ESC apprived with conditions attached to plans. Responsible Person Waiver not approved.
Routing - PUBLIC WORKS11/20/2002 11/25/2002 PASS
Additional plans submitted  11/22/2002 DONE
Received one copy of 8 1/2" x 11" sheet showing stair detail. Kathy informed applicant that larger size (minimum 18" x 24") might be required. Routed to Mike Otto.
Routing - PLANNING Land Div11/20/2002 11/20/2002 FAIL
Need proof of legal land division. Left message for Mike Musgrave on Nov. 20, 2003.
Plans ACCEPTED BY PLAN TECH  11/20/2002 DONE
1. Applicant informed that stair details are required.
2. Full site plan not submitted with all building locations, dimensions, and property lines.
3. Building Code Data not on the front of the plans.
4.ESC narrative incomplete.
5. Accept plans as is per John Menard
Pending Assignment by JCM11/20/2002 11/20/2002 DONE
DetailsJohn Menard
11/20/2002 10:18:22 JCM - activity updated through activity BLDA174 from case BLD02-02805.
Application received  11/15/2002  
Recd Pcfee & Taken To Pln CK  11/15/2002 DONE