BLD-Final | 7/31/2003 | 7/31/2003 | 7/31/2003 | P | PASS |
Dave Hannah
|
|
|
Access garage 0852 enter; Phone #: ###-#### Internet Inspection Request from: josh strasser c.c # 23951 issued 7/31/2003 2:02:13 PM
|
BLD-Final | 7/30/2003 | 7/30/2003 | 7/30/2003 | P | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: josh strasser
|
BLD-Final | 7/29/2003 | 7/29/2003 | 7/29/2003 | P | FAIL |
Dave Hannah
|
|
|
needs plumbing final and fire place final 7/29/2003 2:29:00 PM
|
BLD-Final | 7/23/2003 | 7/24/2003 | 7/24/2003 | P | NH |
Steven Webb
|
|
|
Phone #: ###-#### Internet Inspection Request from: josh strasser No answer on telephone -- door locked. Re-schedule. 7/24/2003 1:58:45 PM
|
BLD-Framing/Rough-in | 5/29/2003 | 5/30/2003 | 5/30/2003 | A | PASS |
Jim Storey
|
|
|
josh dry wall shear nail; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 5/27/2003 | 5/28/2003 | 5/28/2003 | A | PASS |
Dave Hannah
|
|
|
JOSH; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Framing/Rough-in | 5/21/2003 | 5/22/2003 | 5/22/2003 | P | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: josh strasser c/n on site ok insulate 5/22/2003 4:40:41 PM
|
BLD-Framing/Rough-in | 5/16/2003 | 5/19/2003 | 5/19/2003 | A | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: josh strasser needs other trades r/i 5/19/2003 10:05:38 AM
|
BLD-Framing/Rough-in | 5/5/2003 | 5/6/2003 | 5/6/2003 | A | PART |
Dave Hannah
|
|
|
Shere wall inspection; Phone #: ###-#### Internet Inspection Request from: josh strasser ok to cover ext 5/6/2003 11:58:09 AM
|
BLD-Foundation | 3/27/2003 | 3/28/2003 | 3/28/2003 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/27/2003 at 5:53:23 PM. Contact: ###-####.work in progress checked setbacks all look ok but crew only about 20 complete 3/28/2003 9:56:56 AM
|
BLD-Footing | 3/27/2003 | 3/27/2003 | 3/27/2003 | P | PART |
Dave Hannah
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Annette Moore work in progress about 20% complete 3/27/2003 4:03:40 PM
|
Telephone call | | | 2/13/2003 | | DONE |
|
|
|
CALLED 2-13-03 TOLD JOSH NEED TO PICK UP PERMIT OR POSSIBLE THAT IT WILL BE VOIDED OUT IN A COUPLE OF WEEKS...DARLA 9:51 MIKE CALLED TO LET ME KNOW THAT HE WOULD PICK UP THE PERMITS 1 MONTH FROM THE 14TH OF FEB
|
Issue PAID IN FULL permit | | | 2/13/2003 | | |
|
|
|
|
Pending Assignment by DJO | 11/25/2002 | | 12/9/2002 | | DONE |
Dan Overy
|
|
|
12/9/2002 09:10:45 SAM - activity updated through activity BLDA183 from case BLD02-02877.
|
Routing - PLAN CHECK | 11/25/2002 | | 12/9/2002 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 12/9/2002 | | 12/9/2002 | | PASS |
Steve Munroe
|
|
|
12/9/2002 11:20:05 SAM - activity updated through activity BLDA022 from case BLD02-02877.
|
Case Summary (BLD) | | | 12/9/2002 | | |
|
|
|
|
Plan Review Report | | | 12/9/2002 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/9/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/9/2002 | | DONE |
|
|
|
|
Telephone call | | | 12/9/2002 | | DONE |
|
|
|
permit ready and fees due
|
Routing - PLANNING | 11/25/2002 | | 11/25/2002 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 11/25/2002 | | 11/25/2002 | | DONE |
|
|
|
|
Application received | | | 11/25/2002 | | |
|
|
|
|