Permit Information
Permit NumberBLD02-02889
StatusFinaled
Name WESTERN POWER SPORTS (RACKING)
Site Address 601 W GOWEN RD
Project NameWESTERN POWER SPORTS-RACKING
Customer Number 
ePlanReviewNo
Description
(WESTERN POWER SPORTS)(RACKING) To install additional steel storage racking/shelving on mezzanine and around perimeter of warehouse main floor and to install another third catwalk level on top of existing multiple level racking system in an existing 106,964 sq. ft. building per approved plans on file. There will now be three levels of racking above the floor. (4 total tiers of rack storage including main floor.) Work to include steel storage racks and shelving installation per UBC Chapter 22, Division X and attached structural engineering, new stairway extensions with guardrails/handrails to new upper catwalk level, some new exit signs, removing a wood structure photo booth constructed without a permit on the mezzanine, fire sprinkler work, and electrical work. Stairs in existing portion of racking system were originally approved per UBC provisions of a "private stairway". Per Building Director alternate approval, new stairway extensions to the new upper catwalk level will also be allowed to meet "private stairway" provisions but restrict each catwalk level above the ground floor to 9 persons/employees maximum. (Less than 10 per level.) This is a Scope of Work Permit. Letter of Completion to be issued when done. NOTE: This building is fully fire sprinklered and has 60' on all sides for unlimited area provisions. (PC#784-02) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes12/13/200212/13/20028/10/2004 DONE
RECEIVED CHECK FOR $ 2,597.62 THAT HAS BEEN APPLIED TO FEE'S THEY STILL OWE $ 9.37 12-13-02 ///DLD ( WESTERN POWER SPORTS INC CHECK # 36847 )
BLD-Final12/8/200312/8/200312/8/2003PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/8/2003 at 11:16:03 AM. Contact: ###-####.
FIRE-Final Inspection12/8/200312/8/200312/8/2003PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/8/2003 at 11:16:50 AM. Contact: ###-####.
DOC - Permit Finaled12/8/200312/8/200312/8/2003PPASS
DetailsJim Storey
Finaled by inspector at 12/8/2003 3:27:24 PM
BLD-Aging Inspection10/21/200310/21/200310/21/2003 FAIL
DetailsJim Storey
pending action on fire insp. 10/21/2003 8:15:35 AM
BLD-Aging Inspection8/18/20038/18/20038/18/2003 PART
DetailsJim Storey
wip 8/18/2003 8:35:07 AM
BLD-Aging Inspection6/16/20036/16/20036/16/2003 PASS
DetailsJim Storey
spk wip 6/16/2003 1:41:00 PM
BLD-Final4/11/20034/14/20034/14/2003ANR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/11/2003 at 3:52:25 PM. Contact: ###-####. needs fire life safty and fire sprinkler sign off 4/14/2003 10:21:14 AM
Telephone call  4/7/2003 DONE
left mess that permit is ready
Inspection Record Card- Bld  4/7/2003  
Issue PAID IN FULL permit  4/7/2003 DONE
PAID UP FRONT
Routing - FIRE4/1/2003 4/4/2003 PASS
DetailsBill Alexander
Routing - PLAN CHECK4/4/2003 4/4/2003 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  4/4/2003 PASS
Plan assigned to (JCB)12/16/2002 4/4/2003 PASS
DetailsJason Blais
4/4/2003 15:34:18 JCB - activity updated through activity BLDA022 from case BLD02-02889.
Routing - PLAN CHECK3/19/2003 4/1/2003 PEND
Permit approval dependent on Fire Dept. approval. Plans routed to Fire Dept.
Plan resubmittals received  4/1/2003 DONE
Received two copies of revised sheet A2.3, one cover letter, one description of products and on lay out of storage area. Routed to Jason B. kmm
Plan resubmittals received  4/1/2003 DONE
Received four copies of revised sheet 1-4. Routed to Jason B. kmm
Routing - FIRE3/13/2003 3/19/2003 FAIL
DetailsBill Alexander
Need information for verification of meeting UFC Article 81. Faxed copy to Architect on record.
Plan Review Completed(1st rev)  3/19/2003 DONE
Routing - PLAN CHECK12/16/2002 3/13/2003 FAIL
Plan review report sent and faxed to architect. One issue to be addressed. Plans routed to Fire Dept. for review.
Plan resubmittals received  3/5/2003 DONE
Received two copies of revised sheets A2.1, A2.2, A2.3, A2.4. Routed to Jason B. kmm
Telephone Call  2/13/2003  
Called architect, Wes Steele, on status of project. He said more work had been done and that he was still waiting on structural engineering to be provided. Would resubmit as soon as engineering is received.
Telephone call  1/7/2003 DONE
Talked to Wes Steele concerning this permit. He was going to the site to get clarification on all new racking. New information will be provided for clarification.
Telephone call  1/6/2003 DONE
Left a message for architect, Wes Steele, and called Tenant, Mike Gulley, concerning more information needed to do full review on additional racking.
Plans ACCEPTED BY PLAN TECH  12/16/2002 DONE
Per Jason B. kmm
Application received  11/27/2002