Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD02-02899
StatusFinaled
Name STATEWIDE CONSTRUCTION INC
Site Address 4987 E SAGEWOOD DR
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a three bedroom, two and half bathroom 2604 sq. ft. single story single family dwelling with a 1507 sq. ft. UNFINISHED basement, a attached 847 sq. ft. three car garage, a 224 sq. ft. covered back porch and a 199 sq. ft. covered front porch. A SEPARATE PERMIT IS REQUIRED to finish the basement. Per approved plans, engineering and requirement list. ROOF HEIGHT per solar ordinance to be verified. PC#756 (SAM)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/23/20037/24/20037/24/2003AFAIL
DetailsSteven Webb
dwayne; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie C/N on site. 7/24/2003 8:57:20 AM
BLD-Final7/24/20037/24/20037/24/2003PPASS
DetailsSteven Webb
duane; Phone #: ###-#### Internet Inspection Request from: Annette Moore C. of C. #23359 issued. 7/24/2003 4:18:50 PM
DOC - Permit Finaled7/24/20037/24/20037/24/2003PPASS
DetailsSteven Webb
Finaled by inspector at 7/24/2003 4:18:56 PM
BLD-Final7/23/20037/23/20037/23/2003PFAIL
DetailsDave Hannah
duane; Phone #: ###-#### Internet Inspection Request from: Annette Moore needs elec final ,plumbing final,mec on fire place finaled need istulation manual on fire place, stairs in garage out of code, hand rail stairs back deck finash insulating basement 7/23/2003 2:58:38 PM
BLD-Wall cover4/23/20034/23/20034/23/2003PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/23/2003 at 9:51:09 AM. Contact: ###-####. ALLC/N ITEMS COMPLETED INSULATION OK TO COVER 4/23/2003 2:43:24 PM
BLD-Framing/Rough-in4/21/20034/21/20034/21/2003PFAIL
DetailsDave Hannah
###-#### c/n on site ok to insulate 4/21/2003 2:44:42 PM
BLD-Energy code compliance4/21/20034/21/20034/21/2003PPART
DetailsDave Hannah
seal package ok 4/21/2003 2:45:04 PM
BLD-Framing/Rough-in4/14/20034/15/20034/15/2003AFAIL
DetailsDave Hannah
###-#### needs truss engineering on site 4/15/2003 10:56:35 AM
BLD-Framing/Rough-in4/15/20034/15/20034/15/2003PNR
DetailsDave Hannah
###-####
BLD-Framing/Rough-in3/31/20033/31/20033/31/2003PPART
DetailsDave Hannah
DUANE SHEAR NAIL; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok to cover ext need engineering on back wall 3/31/2003 4:35:48 PM
BLD-Footing2/18/20032/19/20032/19/2003APART
DetailsDave Hannah
JIM; Phone #: ###-#### Internet Inspection Request from: Darla Downs the rest of to house footin g ok to pour 2/18/2003 2:16:01 PM
BLD-Foundation2/19/20032/19/20032/19/2003PPASS
DetailsDave Hannah
jim; Phone #: ###-#### Internet Inspection Request from: Annette Moore
BLD-Foundation1/28/20031/28/20031/28/2003PPASS
DetailsDave Hannah
WALL \\###-#### basement walls ok to pour 1/28/2003 4:54:35 PM
BLD-Footing1/22/20031/22/20031/22/2003PPASS
DetailsDave Hannah
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
Issue PAID IN FULL permit  1/13/2003 DONE
Case Summary (BLD)  1/8/2003  
Plan Review Report  1/8/2003  
Plan Reviewer's activity  1/8/2003 PEND
Only one set of plans are being approved due to red-lining and no extra site plan.
PLANS/APPL TAKEN TO FRONT DESK  1/8/2003 DONE
Inspection Record Card- Bld  1/8/2003 DONE
Print Occupancy Form  1/8/2003 DONE
Telephone call  1/8/2003 DONE
permit ready and fees due
Routing - PLAN CHECK12/27/2002 1/8/2003 DONE
Plan assigned to (SAM)1/3/2003 1/8/2003 PASS
DetailsSteve Munroe
1/8/2003 14:07:35 SAM - activity updated through activity BLDA022 from case BLD02-02899.
Plan Reviewer's activity  1/7/2003 PEND
1/7/03 15:25 I called and talked to Tim Johnson, the engineer. He said he will call me tomorrow. I have questions on wall line 4 and locations of all beam, headers and footings.
Plan Reviewer's activity  1/6/2003 PEND
1/6/02 09:00 I called and talked to Robin, the architect. She was in a meeting and will call me back. I need lateral calculations from the engineer.
Plan Reviewer's activity  1/6/2003 PEND
1/6/03 I called and left a message on Brian's phone, leting him know that I need the engineering calculations for the lateral bracing on this residence. Plans are on hold till I recieve the calculations.
Pending Assignment by DJO11/27/2002 1/3/2003 DONE
DetailsDan Overy
1/3/2003 15:47:40 SAM - activity updated through activity BLDA183 from case BLD02-02899.
Routing - PUBLIC WORKS12/26/2002 12/26/2002 PASS
Routing - PLANNING12/23/2002 12/26/2002 PASS
Pass per designer roof change. Plans found folded & left of third station. Missing eng. specs.
Routing - PLANNING12/17/2002 12/20/2002 FAIL
Plans resubmitted per solar restrictions--roof still too high. AKT
Routing - PLANNING11/27/2002 12/2/2002 FAIL
Subject to solar setbacks per solar lot on plat. Left msg. w/ Brian 12/2.
Application received  11/27/2002 PEND