BLD-Final | 7/23/2003 | 7/24/2003 | 7/24/2003 | A | FAIL |
Steven Webb
|
|
|
dwayne; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie C/N on site. 7/24/2003 8:57:20 AM
|
BLD-Final | 7/24/2003 | 7/24/2003 | 7/24/2003 | P | PASS |
Steven Webb
|
|
|
duane; Phone #: ###-#### Internet Inspection Request from: Annette Moore C. of C. #23359 issued. 7/24/2003 4:18:50 PM
|
DOC - Permit Finaled | 7/24/2003 | 7/24/2003 | 7/24/2003 | P | PASS |
Steven Webb
|
|
|
Finaled by inspector at 7/24/2003 4:18:56 PM
|
BLD-Final | 7/23/2003 | 7/23/2003 | 7/23/2003 | P | FAIL |
Dave Hannah
|
|
|
duane; Phone #: ###-#### Internet Inspection Request from: Annette Moore needs elec final ,plumbing final,mec on fire place finaled need istulation manual on fire place, stairs in garage out of code, hand rail stairs back deck finash insulating basement 7/23/2003 2:58:38 PM
|
BLD-Wall cover | 4/23/2003 | 4/23/2003 | 4/23/2003 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/23/2003 at 9:51:09 AM. Contact: ###-####. ALLC/N ITEMS COMPLETED INSULATION OK TO COVER 4/23/2003 2:43:24 PM
|
BLD-Framing/Rough-in | 4/21/2003 | 4/21/2003 | 4/21/2003 | P | FAIL |
Dave Hannah
|
|
|
###-#### c/n on site ok to insulate 4/21/2003 2:44:42 PM
|
BLD-Energy code compliance | 4/21/2003 | 4/21/2003 | 4/21/2003 | P | PART |
Dave Hannah
|
|
|
seal package ok 4/21/2003 2:45:04 PM
|
BLD-Framing/Rough-in | 4/14/2003 | 4/15/2003 | 4/15/2003 | A | FAIL |
Dave Hannah
|
|
|
###-#### needs truss engineering on site 4/15/2003 10:56:35 AM
|
BLD-Framing/Rough-in | 4/15/2003 | 4/15/2003 | 4/15/2003 | P | NR |
Dave Hannah
|
|
|
###-####
|
BLD-Framing/Rough-in | 3/31/2003 | 3/31/2003 | 3/31/2003 | P | PART |
Dave Hannah
|
|
|
DUANE SHEAR NAIL; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok to cover ext need engineering on back wall 3/31/2003 4:35:48 PM
|
BLD-Footing | 2/18/2003 | 2/19/2003 | 2/19/2003 | A | PART |
Dave Hannah
|
|
|
JIM; Phone #: ###-#### Internet Inspection Request from: Darla Downs the rest of to house footin g ok to pour 2/18/2003 2:16:01 PM
|
BLD-Foundation | 2/19/2003 | 2/19/2003 | 2/19/2003 | P | PASS |
Dave Hannah
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Foundation | 1/28/2003 | 1/28/2003 | 1/28/2003 | P | PASS |
Dave Hannah
|
|
|
WALL \\###-#### basement walls ok to pour 1/28/2003 4:54:35 PM
|
BLD-Footing | 1/22/2003 | 1/22/2003 | 1/22/2003 | P | PASS |
Dave Hannah
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Issue PAID IN FULL permit | | | 1/13/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/8/2003 | | |
|
|
|
|
Plan Review Report | | | 1/8/2003 | | |
|
|
|
|
Plan Reviewer's activity | | | 1/8/2003 | | PEND |
|
|
|
Only one set of plans are being approved due to red-lining and no extra site plan.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/8/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/8/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/8/2003 | | DONE |
|
|
|
|
Telephone call | | | 1/8/2003 | | DONE |
|
|
|
permit ready and fees due
|
Routing - PLAN CHECK | 12/27/2002 | | 1/8/2003 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 1/3/2003 | | 1/8/2003 | | PASS |
Steve Munroe
|
|
|
1/8/2003 14:07:35 SAM - activity updated through activity BLDA022 from case BLD02-02899.
|
Plan Reviewer's activity | | | 1/7/2003 | | PEND |
|
|
|
1/7/03 15:25 I called and talked to Tim Johnson, the engineer. He said he will call me tomorrow. I have questions on wall line 4 and locations of all beam, headers and footings.
|
Plan Reviewer's activity | | | 1/6/2003 | | PEND |
|
|
|
1/6/02 09:00 I called and talked to Robin, the architect. She was in a meeting and will call me back. I need lateral calculations from the engineer.
|
Plan Reviewer's activity | | | 1/6/2003 | | PEND |
|
|
|
1/6/03 I called and left a message on Brian's phone, leting him know that I need the engineering calculations for the lateral bracing on this residence. Plans are on hold till I recieve the calculations.
|
Pending Assignment by DJO | 11/27/2002 | | 1/3/2003 | | DONE |
Dan Overy
|
|
|
1/3/2003 15:47:40 SAM - activity updated through activity BLDA183 from case BLD02-02899.
|
Routing - PUBLIC WORKS | 12/26/2002 | | 12/26/2002 | | PASS |
|
|
|
|
Routing - PLANNING | 12/23/2002 | | 12/26/2002 | | PASS |
|
|
|
Pass per designer roof change. Plans found folded & left of third station. Missing eng. specs.
|
Routing - PLANNING | 12/17/2002 | | 12/20/2002 | | FAIL |
|
|
|
Plans resubmitted per solar restrictions--roof still too high. AKT
|
Routing - PLANNING | 11/27/2002 | | 12/2/2002 | | FAIL |
|
|
|
Subject to solar setbacks per solar lot on plat. Left msg. w/ Brian 12/2.
|
Application received | | | 11/27/2002 | | PEND |
|
|
|
|