Permit Information
Permit NumberBLD02-03039
StatusFinaled
Name ARAMARK - IN-FLIGHT KITCHEN
Site Address 2761 W APOLLO WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
(ARAMARK - IN-FLIGHT KITCHEN) This building is NOT fire sprinklered. To remodel a 4,980 square foot tenant space on the main floor of an existing 8,767 square foot building. This tenant space will be used as an "in-flight kitchen" to serve the Boise Airport Terminal. Work is to include altering two restrooms to be accessible to the disabled, attaching two relocated canopies (or construct new), constructing a cooler/freezer addition, installing a grease duct, enlarging doors in masonry walls, constructing exerior wall infills, and installing a suspended ceiling system all per approved drawings, engineering, and plan review conditions on file. The structural design for the pre-manufactured cooler/freezer unit is a deferred submittal item.**CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 8/25/20038/25/2003 DONE
First Notice 8/25/20038/25/2003 DONE
Permanent occupancy UNPAID FEE  8/25/2003 DONE
Perm. Occ. Cert. #9775 issued 8-25-03 to the Aramark In-Flight Kitchen.
Permanent Occupancy 8/22/20038/22/2003 DONE
Details
BLD-Final8/18/20038/18/20038/18/2003ADONE
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/18/2003 at 7:13:51 AM. Contact: ###-####. final ok unpon plm and ele final aprovals. 8/18/2003 10:04:08 AM
Temporary occupancy  7/23/2003 DONE
Temp. Occ. Cert. #4974 issued 7-23-03 to Aramark - In Flight Kitchen.
BLD-Final7/18/20037/18/20037/18/2003PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/18/2003 at 7:59:13 AM. Contact: ###-####.manual flush bolds not allowed. 7/18/2003 4:02:30 PM
FIRE-Final Inspection7/17/20037/17/20037/17/2003PPASS
DetailsRick Jackson
JOHN; Phone #: ###-#### Internet Inspection Request from: Dixie Fellows
FIRE-Alarm Testing7/16/20037/16/20037/16/2003ACANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 7/16/2003 at 7:26:48 AM. Contact: ###-####. will be rescheduled 7/16/2003 12:03:00 PM
BLD-Other7/11/20037/14/20037/14/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/11/2003 at 8:19:33 AM. Contact: ###-####.need to insp. duct wrap at final and main door hardware. 7/14/2003 9:03:00 AM
BLD-Aging Inspection6/17/20036/17/20036/17/2003 PASS
DetailsJim Storey
wip 6/17/2003 11:30:55 AM
Telephone call  5/1/2003 DONE
Called the architect (David Turner) and told him that the structural design for the outside cooler/freezer was approved. I told him, though, that compliant landings were required on both sides of cooler/freezer doors (i.e. no ramp allowed at the door). He said he would take actions to resolve the issue.
Additional plans submitted  4/16/2003 PASS
Received deferred submittal for structual design for the outside cooler/freezer. Design approved May 1, 2003.
BLD-Wall cover4/11/20034/14/20034/14/2003APART
DetailsJim Storey
JOHN; Phone #: ###-#### Internet Inspection Request from: Darla Downs exterior walls and all but hood area ok for cover. 4/14/2003 10:06:47 AM
BLD-Footing4/11/20034/11/20034/11/2003APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/11/2003 at 5:19:04 AM. Contact: ###-####.ft ok 4/11/2003 8:40:55 AM
BLD-Footing4/10/20034/10/20034/10/2003PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/10/2003 at 7:11:05 AM. Contact: ###-####.
PLANS/APPL TAKEN TO FRONT DESK  2/4/2003 PASS
Print Occupancy Form  2/4/2003 DONE
Telephone call  2/4/2003 DONE
permit ready
Routing - PLAN CHECK1/17/2003 2/4/2003 PASS
Plan assigned to (CJW)12/24/2002 2/4/2003 PASS
DetailsCarl Westfall
2/4/2003 11:21:22 CJW - activity updated through activity BLDA022 from case BLD02-03039.
Plan resubmittals received  2/3/2003 DONE
Received two copies of revised sheets S101of 3, S102 of 3 S201 of 3, two copies of struct. calculations and one copy of response letter. Routed to Carl W. kmm
Plan Review Completed(1st rev)  1/17/2003 DONE
Routing - FIRE1/16/2003 1/17/2003 PASS
Routing - PLAN CHECK1/8/2003 1/16/2003  
Failed first UBC review. UBC plan review started January 10, 2003 and finished January 16, 2003. A response from the architect was required. See the conditions list.
Routing - Erosion and Sediment1/3/2003 1/8/2003 PASS
ESC waiver approved with conditions attached to plans.
Routing - PLUMBING1/2/2003 1/3/2003 PASS
1. 3 inch floor sink fs-1 and 3 inch floor drain fd-1 need 2 inch vent 2. need premise backflow protection 3. ice machines (2) may need backflow protection
Routing - PLANNING12/30/2002 1/2/2003 PASS
Approved.
Routing - PUBLIC WORKS12/24/2002 12/30/2002 PASS
Application received  12/20/2002  
Issue & PRINT to be Invoiced  12/20/2002 DONE
Plans ACCEPTED BY PLAN TECH  12/20/2002 PASS

CHANGE ISSUED DATE  12/20/2002