Case Summary (BLD) | | | 6/9/2014 | | DONE |
|
|
|
|
Fee Review-notes | 12/30/2002 | 12/30/2002 | 8/10/2004 | | DONE |
|
|
|
|
First Notice | | 4/7/2004 | 4/7/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/7/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10078 issued 4-6-04 to Liberty Lake Apts.
|
Permanent Occupancy | | 4/6/2004 | 4/6/2004 | | DONE |
|
|
|
|
BLD-Final | 4/6/2004 | 4/6/2004 | 4/6/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/6/2004 at 10:54:50 AM. Contact: ###-####. OK FOR PERM OCC 4/6/2004 1:19:19 PM
|
Temporary occupancy | | | 4/1/2004 | | PASS |
|
|
|
FINAL SIGNED OFF & RELEASE OF BOND
|
BLD-Final | 3/11/2004 | 3/12/2004 | 3/12/2004 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/11/2004 at 3:24:05 PM. Contact: ###-####. ok for perm when others sign perm 3/12/2004 9:29:49 AM
|
FIRE-Final Inspection | 3/2/2004 | 3/2/2004 | 3/2/2004 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 3/2/2004 11:47:02 AM
|
BLD-Conference | 2/20/2004 | 2/20/2004 | 2/20/2004 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/20/2004 at 7:30:17 AM. Contact: ###-####. hand rail ok 2/20/2004 10:05:28 AM
|
BLD-Energy code compliance | 1/12/2004 | 1/12/2004 | 1/12/2004 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/12/2004 at 7:24:42 AM. Contact: ###-####. ok to cover 1/12/2004 8:48:30 AM
|
BLD-Framing/Rough-in | 1/8/2004 | 1/9/2004 | 1/9/2004 | A | PART |
Tom Arcoraci
|
|
|
1st floor need ok to insulate. 1/8/2004 2:14:05 PM ok to insul 1 st floor re check floor ceiling pents at drops 1/9/2004 9:21:15 AM
|
BLD-Framing/Rough-in | 1/8/2004 | 1/8/2004 | 1/8/2004 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 1/8/2004 at 11:23:32 AM. Contact: ###-####. called contractor told him that attic needs inspection will need to meet with a ladder. 1/8/2004 2:16:05 PM
|
BLD-Energy code compliance | 12/31/2003 | 12/31/2003 | 12/31/2003 | P | PART |
Tom Arcoraci
|
|
|
Odie ok to cover 2nd floor need to check 2 hr wall pents at attic 12/31/2003 3:11:05 PM
|
BLD-Conference | 11/20/2003 | 11/21/2003 | 11/21/2003 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/20/2003 at 8:34:17 PM. Contact: ###-####. NEED TO FINISH FIRE CAULKING IN DROPS 11/21/2003 2:55:32 PM
|
BLD-Energy code compliance | 11/6/2003 | 11/7/2003 | 11/7/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/6/2003 at 4:46:58 PM. Contact: ###-####.
|
BLD-Energy code compliance | 11/4/2003 | 11/5/2003 | 11/5/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/4/2003 at 1:01:04 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/3/2003 | 11/3/2003 | 11/3/2003 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/3/2003 at 10:35:22 AM. Contact: ###-####.
|
FIRE-Conference | 10/23/2003 | 10/24/2003 | 10/24/2003 | A | DONE |
Troy Cobbley
|
|
|
I spoke with Mike with Steed Construction about the placement of fire extinguishers. They need to be placed at each of the exit/entrances for a total of 6 extinguishers for each apartment block 10/24/2003 12:07:42 PM
|
BLD-Conference | 10/21/2003 | 10/22/2003 | 10/22/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/21/2003 at 5:12:41 PM. Contact: ###-####. wip ok 10/22/2003 1:17:09 PM
|
BLD-Conference | 10/20/2003 | 10/21/2003 | 10/21/2003 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/20/2003 at 6:02:02 PM. Contact: ###-####.
|
BLD-Conference | 10/14/2003 | 10/14/2003 | 10/14/2003 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/14/2003 at 7:43:42 AM. Contact: ###-####. ok to side 10/14/2003 2:06:04 PM
|
BLD-Conference | 10/7/2003 | 10/8/2003 | 10/8/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/7/2003 at 5:44:23 PM. Contact: ###-####. 2 hr wall needs fix 10/8/2003 9:34:38 AM
|
BLD-Footing | 9/30/2003 | 10/1/2003 | 10/1/2003 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/30/2003 at 3:01:29 PM. Contact: ###-####.
|
BLD-Conference | 9/30/2003 | 10/1/2003 | 10/1/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/30/2003 at 3:02:06 PM. Contact: ###-####.
|
FIRE-Conference | 9/29/2003 | 9/30/2003 | 9/30/2003 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 9/29/2003 at 1:00:07 PM. Contact: ###-####. Met with GC and electrician about smoke detectors; install in locations as shown on plans but they will be located close to the kitchen requiring silencing option; need 177 cd in ADA rooms 9/30/2003 12:35:54 PM
|
BLD-Conference | 9/17/2003 | 9/18/2003 | 9/18/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/17/2003 at 5:45:59 PM. Contact: ###-####. needs arch detail for floor 9/18/2003 10:36:02 AM
|
BLD-Conference | 9/10/2003 | 9/11/2003 | 9/11/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/10/2003 at 1:13:25 PM. Contact: ###-####.
|
BLD-Conference | 9/2/2003 | 9/3/2003 | 9/3/2003 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 9/2/2003 at 11:19:12 AM. Contact: ###-####. out of time. 9/2/2003 6:04:04 PM
|
BLD-Framing/Rough-in | 9/3/2003 | 9/3/2003 | 9/3/2003 | P | FAIL |
Russ Owen
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Conference | 9/2/2003 | 9/3/2003 | 9/3/2003 | P | FAIL |
Russ Owen
|
|
|
2 hr wall at floor line not per plan met with contractor. build per plan or architect to supply new detail. 9/2/2003 10:14:13 PM
|
BLD-Foundation | 7/30/2003 | 7/30/2003 | 7/30/2003 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/30/2003 at 8:26:55 AM. Contact: ###-####. spec insp on site 7/30/2003 4:05:05 PM
|
BLD-Footing | 7/23/2003 | 7/23/2003 | 7/23/2003 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/23/2003 at 7:15:30 AM. Contact: ###-####. pending strata 7/23/2003 9:00:06 AM
|
Issue PAID IN FULL permit | | | 6/27/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/18/2003 | | DONE |
|
|
|
|
Telephone call | | | 6/18/2003 | | DONE |
|
|
|
permit ready
|
Plan assigned to (M_P) | 12/31/2002 | 12/31/2002 | 6/17/2003 | | PASS |
Mike Phillips
|
|
|
6/17/2003 14:33:45 M_P - activity updated through activity BLDA022 from case BLD02-03075.
|
Routing - PLANNING | 6/16/2003 | | 6/17/2003 | | PASS |
|
|
|
Approved per DRH02-140 and Modification.
|
Routing - PLAN CHECK | 6/17/2003 | | 6/17/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/17/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/17/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/17/2003 | | DONE |
|
|
|
|
Routing - FIRE | 6/11/2003 | | 6/13/2003 | | PASS |
|
|
|
Comments revised to reflect plan modifications.
|
Print permit w/o conditions | | | 6/11/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 5/8/2003 | | 6/11/2003 | | PEND |
|
|
|
Routing to fire.
|
Plan resubmittals received | | | 5/29/2003 | | DONE |
|
|
|
Response letter, transmittal letter from JUB, transmittal from Ikemire Arch, Revised certificates of value for bld02-03075,02-03076,3077, 2 copies of S2-6, S1-6, S6-6, S2-6, (2 of A2, A3, A4, A5, A6, A7, A8, A9, and taken to Mike P.
|
Routing - PLANNING | 5/1/2003 | | 5/7/2003 | | PEND |
|
|
|
Pending a Design Review modification application for site-landscape design. Met with Mark (with Steed Construction) on May 6 and discussed this issue with him.
|
Routing - PLAN CHECK | 4/4/2003 | | 5/1/2003 | | FAIL |
|
|
|
Third review failed. Need additional information submitted for review prior to issuing permit.
|
Routing - PLANNING | 4/1/2003 | | 4/4/2003 | | FAIL |
|
|
|
K. Gallagher - approved resubmitted plans.
M. Santoyo - Landscape plan changed from original approval. The applicant is required to submit a staff level Design Review modification application to address the changes, as well as the removal of approved trees per DRH02-140, condition of approval #21.
|
Routing - PLAN CHECK | 3/14/2003 | | 4/1/2003 | | |
|
|
|
|
Plan resubmittals received | | | 4/1/2003 | | DONE |
|
|
|
Received two copies of revised sheets, EL1, S2 of 6, S4 of 6, S5 of 6, Three copies of A2, two of A5, A7, A9, A10, A11, A11A. One response letter from JUB engineering, and one response letter from IKEMIRE Architects. Routed to Mike P. kmm
|
Routing - PLAN CHECK | 3/5/2003 | | 3/14/2003 | | FAIL |
|
|
|
Second review failed sent correction report to architect requesting additional informaiton to be submitted for further review prior to issuing permit.
|
Routing - PLANNING | 3/3/2003 | | 3/4/2003 | | FAIL |
|
|
|
Failed again - sent letter to developer, architect, and builder. kg
|
Routing - PLAN CHECK | 2/21/2003 | | 3/3/2003 | | |
|
|
|
|
Plan resubmittals received | | | 2/28/2003 | | DONE |
|
|
|
Received two sets of resubmittal sheets "Landscape Plans". Routed to Mike Phillips.
|
Plan resubmittals received | | | 2/28/2003 | | DONE |
|
|
|
Received two sets of resubmittal sheets A1, A3, A4, A5, A6, A6A, A7, A8, A9, A10, A11, A11A, A12, S1, S2, S3, S4, S5, with cover/comment letter and transmittal. Routed to Mike Phillips.
|
Routing - PLAN CHECK | 2/14/2003 | | 2/21/2003 | | |
|
|
|
|
Routing - FIRE | 2/21/2003 | | 2/21/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/21/2003 | | 2/21/2003 | | |
|
|
|
|
Routing - FIRE | 2/21/2003 | | 2/21/2003 | | |
|
|
|
|
Routing - PUBLIC WORKS | 2/13/2003 | | 2/14/2003 | | PASS |
|
|
|
|
Routing - FIRE | 2/11/2003 | | 2/13/2003 | | FAIL |
|
|
|
water supply quote
|
Routing - PLAN CHECK | 1/27/2003 | | 2/11/2003 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional informaiton for further review, prior to issuing permit.
|
Print permit w/o conditions | | | 2/11/2003 | | |
|
|
|
|
Routing - PLUMBING | 1/24/2003 | | 1/27/2003 | | PASS |
|
|
|
1. Idaho code requires a base of stack cleanout on all dwv stacks. 2. Water heater T&P drains must terminate to outside of the bldg 6-24 inches above ground. 3. The double check valves for each building need to be 11/2 inch not 11/4 inch per fixture schedule. 4. Each apartment needs a water shutoff valve in addition to the water heater shutoff valve. 5. ET-1 needs to be sized for the building thermal expansion.
|
Routing - PLANNING | 1/14/2003 | | 1/24/2003 | | FAIL |
|
|
|
Karen Gallagher - Failed. Not in compliance with CUP02-75. 1-16-03.
Marty Santoyo - Not in compliance with DRH02-140. 1-23-03.
|
Routing Off Site - STRUCTURAL | 1/2/2003 | | 1/21/2003 | | PASS |
|
|
|
contacted PDQ to take plans to outside eng. kmm
Approved no further review required by outside engineering firm.
|
Routing - Erosion and Sediment | 1/13/2003 | | 1/14/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 12/31/2002 | | 1/13/2003 | | FAIL |
|
|
|
Requires Drainage plan and geotech revision. Per Brian M. kmm
|
Routing - PLANNING Land Div | 12/31/2002 | | 12/31/2002 | | PASS |
|
|
|
Approved by ROS 5887.
|
Plans ACCEPTED BY PLAN TECH | | | 12/31/2002 | | DONE |
|
|
|
Received (3) sets of plans, (3) extra sets of Grading/Drainage plans, (2) Geotech Reports, (2) sets of storm water O&M, (2) sets of drainage calculations, (2) sets of ESC plans with narrative, (3) sets of structural calculations, and (1) New commercial permit application with ESC permit application.
|
Application received | | | 12/30/2002 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/30/2002 | | DONE |
|
|
|
|