Permit Information
Permit NumberBLD03-00035
StatusFinaled
Name CSHQA
Site Address 13601 13613 W MCMILLAN RD
Project NameMcMillan's Corner
Customer Number 
ePlanReviewNo
Description
McMillan's Corner Retail Shops - To construct a 13,175 sq.ft. one story, TypeVB retail SHELL ONLY building within a shopping center per approved plans and attachments. CUP02-00108 PC#003-03 No Occupancy is allowed under this permit. Separate plans and permits must be provided for each tenant space.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  9/25/2009 DONE
Second Notice BLD5/25/20065/25/20065/25/2006 DONE
First Notice has not been responded to.
First Notice4/11/20064/11/20065/25/2006 DONE
DetailsJim Sly
BLD-Final4/11/20064/11/20064/11/2006PPASS
DetailsJim Sly
Prev Finaled
DOC - Permit Finaled4/11/20064/11/20064/11/2006PPASS
DetailsJim Sly
BLD-Final7/9/20037/10/20037/10/2003PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 7/9/2003 at 1:23:21 PM. Contact: ###-####.
FIRE-Final Inspection7/9/20037/10/20037/10/2003AFAIL
DetailsTroy Cobbley
duct smoke detectors in Block Buster do not shut down the hvac units 7/10/2003 8:53:11 AM
FIRE-Final Inspection7/10/20037/10/20037/10/2003PPASS
DetailsTroy Cobbley
fire life safety for the shell and core finaled 7/10/2003 2:41:30 PM
Letter of compliance  7/10/2003 DONE
Letter of Compliance #22958 issued 7-10-03.
FIRE-Conference7/8/20037/9/20037/9/2003ADONE
DetailsTroy Cobbley
Spoke with the contractor about curb painting for fire dept. access 7/9/2003 10:10:05 AM
BLD-Conference7/9/20037/9/20037/9/2003PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 7/9/2003 at 9:24:09 AM.
PubWorks Occupancy Approval  7/2/2003 DONE
Drainage project complete, signed permanent occupancy 7/2/03. R.Rokovitz
BLD-Framing/Rough-in6/24/20036/24/20036/24/2003PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/24/2003 at 8:20:34 AM. Contact: ###-####.
BLD-Framing/Rough-in6/17/20036/17/20036/17/2003APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/17/2003 at 6:43:12 AM. Contact: ###-####. All framing OK ....Still need firestopping 3hr wall. 6/17/2003 12:05:56 PM
BLD-Framing/Rough-in5/21/20035/21/20035/21/2003PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 5/21/2003 at 9:30:00 AM. Contact: ###-####. Ext Entrys and canopys OK pend special insp welding appr. 5/21/2003 3:21:45 PM
(F) Reprint permit  5/8/2003  
BLD-Concrete3/24/20033/25/20033/25/2003APART
DetailsJim Sly
tim; Phone #: ###-#### Internet Inspection Request from: Annette Moore Grouting CMU....MTI on site Stopped laying block...Rain. 3/25/2003 10:15:08 AM 3/25/2003 10:16:09 AM
BLD-Footing3/13/20033/14/20033/14/2003APART
DetailsJim Sly
tim; Phone #: ###-#### Internet Inspection Request from: Annette Moore Remainder of footing at North wall, and intermediate (N.S.) footing OK pending MTI insp and approvals. 3/14/2003 9:50:02 AM
BLD-Footing3/10/20033/12/20033/12/2003AFAIL
DetailsJim Sly
TIM; Phone #: ###-#### Internet Inspection Request from: Annette Moore C/N....Eng to OK fill at footings. 3/12/2003 10:15:05 AM
(F) Reprint permit  3/3/2003  
Routing - FIRE2/28/2003 2/28/2003 PASS
DetailsBill Alexander
Architect provided revised (clarification) of floor area.
PLANS/APPL TAKEN TO FRONT DESK  2/28/2003 DONE
Inspection Record Card- Bld  2/28/2003 DONE
Telephone call  2/28/2003 DONE
permit ready and fees due
Issue PAID IN FULL permit  2/28/2003 DONE
Plan assigned to (MLO)1/13/2003 2/28/2003 PASS
DetailsMike Otto
2/28/2003 13:36:51 MLO - activity updated through activity BLDA022 from case BLD03-00035.
Routing Off Site - STRUCTURAL2/21/2003 2/26/2003 PASS
Contacted PDQ to take revised plans of 2.19.03 to outside eng. kmm Received letter from consulting structural engineer indicating that all items had been adequately addressed. JCM
Routing - FIRE2/21/2003 2/25/2003 FAIL
DetailsBill Alexander
Lack required fire (hydrant) flows for construction Type/ft/2. Faxed copy of failed review to Mr. Jim March and returned plan to Plan Review.
Routing Off Site -Energy2/20/2003 2/21/2003 PASS
Routing - PLAN CHECK2/20/2003 2/21/2003 PASS
Routing - PUBLIC WORKS2/13/2003 2/20/2003 PASS
Route back to PW after first review.
Plan resubmittals received  2/19/2003  
Received three sets resubmittal sheets 1.5, 1.6, 1.7. Routed to Mike Otto.
Plan resubmittals received  2/19/2003 DONE
Received three sets of resubmittal sheets 1.0, 2.0A, 2.1, 2.2A, 3.0, 3.3, 3.5, 4.0, 5.0, 5.1, E1.0, (3) Structural calculations with cover letters, (1) Energy compliance information with letter. Routed to Mike Otto.
Plan Review Completed(1st rev)  2/13/2003 FAIL
Routing - FIRE2/11/2003 2/13/2003 FAIL
water quote
Routing Off Site - STRUCTURAL1/13/2003 2/11/2003 FAIL
contacted PDQ to take plans to outside eng. kmm Corrections sent to architect
Routing - PLAN CHECK2/7/2003 2/11/2003 FAIL
corrections mailed and faxed to architect
Plan resubmittals requested  2/11/2003 DONE
for UBC structural and non-structural and energy
Routing - PLUMBING2/4/2003 2/6/2003 PASS
verify floor drain will handle full discharge of 2" premise R.P., water to space A-6 needs isolation valve, extend 1 1/4" water line in space A-6 to last toilet branch, provide floor drains at premise R.P. and water heater in space A-6. additional cross connection protection may be required at the roof top units.
Routing - Erosion and Sediment1/27/2003 2/4/2003 PASS
ESC approved with conditions attached to plans.

Received narrative on 1/31/03
Plan resubmittals received  1/30/2003 DONE
Received three sets of ESC Narrative with transmittal addressesed to Jim rogers. Routed to Jim rogers.
Plan resubmittals received  1/28/2003 DONE
Received five copies of resubmittal sheets 1.5 with transmittal. Routed to Mike Otto.
Additional plans submitted  1/27/2003 DONE
Received one copy of Soils report with transmittal addressed to Brian Murphy. Routed to Mike Otto.
Routing - PLANNING1/24/2003 1/27/2003 PASS
Routing - PUBLIC WORKS1/15/2003 1/24/2003 FAIL
Requires drainage plan revision per Brian M. kmm
Routing Off Site -Energy1/13/2003 1/22/2003 FAIL
corrections faxed to craig slocum @ cshqa
Routing - PLANNING Land Div1/13/2003 1/15/2003 PASS
Lot 2, Block 2 of Lowell Plaza Subdivision.
Plans ACCEPTED BY PLAN TECH  1/13/2003 PASS


Plan routing begun/NEW & ADDTN  1/13/2003 DONE
Application received  1/9/2003  
Recd Pcfee & Taken To Pln CK  1/9/2003 DONE
Fee Review-notes1/9/20031/9/2003