DOC - Permit Finaled | 3/3/2005 | 3/3/2005 | 3/3/2005 | A | PASS |
Jim Storey
|
|
|
Finaled by inspector at 3/3/2005 9:10:34 AM
|
BLD-Aging Inspection | 9/29/2004 | 9/29/2004 | 9/29/2004 | | NR |
Jim Storey
|
|
|
pending scope reduction responce to planreview/insp. 9/29/2004 8:30:22 AM
|
BLD-Aging Inspection | 7/26/2004 | 7/26/2004 | 7/26/2004 | | NR |
Jim Storey
|
|
|
wip 7/26/2004 11:28:53 AM
|
Plan Reviewer's activity | | | 6/2/2004 | | DONE |
|
|
|
At micron's request, I have modified the permit to reduce the area of the proposed project to 23,600 square feet from the original permitted area of 30,000 square feet. Micron has decided not to complete the 6400 square foot area originally approved under this permit. I given a copy of the request letter and a revised copy of the certificate of value to Linda Hartwell. JCM
|
BLD-Aging Inspection | 5/17/2004 | 5/17/2004 | 5/17/2004 | | PASS |
Jim Storey
|
|
|
wip 5/17/2004 8:41:59 AM
|
BLD-Aging Inspection | 3/16/2004 | 3/16/2004 | 3/16/2004 | | PART |
Jim Storey
|
|
|
wip 3/16/2004 8:01:31 AM
|
BLD-Aging Inspection | 1/15/2004 | 1/15/2004 | 1/15/2004 | | PART |
Jim Storey
|
|
|
called ernie pending responce. 1/15/2004 10:27:24 AM
|
BLD-Conference | 10/7/2003 | 10/8/2003 | 10/8/2003 | P | PASS |
Jim Storey
|
|
|
ernie; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Final | 8/21/2003 | 8/27/2003 | 8/27/2003 | A | NR |
Jim Storey
|
|
|
ERNIE; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Conference | 7/23/2003 | 7/24/2003 | 7/24/2003 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/23/2003 at 2:21:22 PM. Contact: ###-####.
|
BLD-Conference | 7/24/2003 | 7/24/2003 | 7/24/2003 | P | PART |
Jim Storey
|
|
|
floor ceilling fire stopping ok ceilling ok exsting shaft and south coridor wall pending fire stop. 7/24/2003 3:22:09 PM
|
FIRE-Final Inspection | 6/18/2003 | 6/19/2003 | 6/19/2003 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 6/18/2003 at 7:54:05 AM. Contact: ###-####. phase A of this project okay pending structural okay 6/19/2003 10:28:31 AM
|
FIRE-Final Inspection | 6/16/2003 | 6/16/2003 | 6/16/2003 | P | FAIL |
Rick Jackson
|
|
|
ERNIE; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Final | 6/5/2003 | 6/6/2003 | 6/6/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/5/2003 at 11:01:34 AM. Contact: ###-####. need plm permit/ 6/6/2003 9:43:16 AM
|
BLD-Final | 5/21/2003 | 5/21/2003 | 5/21/2003 | P | PART |
Jim Storey
|
|
|
ERNIE ###-#### Internet Inspection Request from: Darla Downs wip. 5/21/2003 3:20:18 PM
|
FIRE-Sprinkler Rough-in | 5/12/2003 | 5/13/2003 | 5/13/2003 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 5/12/2003 at 7:58:35 PM. Contact: ###-####. this permit was called in by mistake 5/14/2003 7:07:15 AM
|
BLD-Framing/Rough-in | 5/5/2003 | 5/6/2003 | 5/6/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/5/2003 at 12:46:28 PM. Contact: ###-####.wip 5/6/2003 2:53:02 PM
|
Issue & PRINT to be Invoiced | | | 3/18/2003 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 2/6/2003 | 2/6/2003 | 3/17/2003 | | PASS |
John Menard
|
|
|
3/17/2003 11:37:37 JCM - activity updated through activity BLDA022 from case BLD03-00175.
|
Routing - PLAN CHECK | 3/3/2003 | | 3/17/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2003 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 3/17/2003 | | |
|
|
|
|
Print Occupancy Form | | | 3/17/2003 | | |
|
|
|
|
Print Occupancy Form | | | 3/17/2003 | | DONE |
|
|
|
|
Telephone call | | | 3/17/2003 | | DONE |
|
|
|
E-MAILED PAUL
|
Plan Reviewer's activity | | | 3/17/2003 | | PASS |
|
|
|
Reviewed and approved resubmittal information with redlined notes and attached comment list. JCM
|
Plan resubmittals received | | | 3/14/2003 | | |
|
|
|
|
BLD-Conference | 3/4/2003 | 3/5/2003 | 3/5/2003 | P | PASS |
Jim Storey
|
|
|
ERNIE ###-#### ERNIE ###-#### reviewed duct transpher fire stopping assemblie as to how to apply assembley. ok 3/5/2003 3:26:43 PM
|
Plan Review Completed(1st rev) | | | 3/3/2003 | | FAIL |
|
|
|
|
Routing - FIRE | 2/26/2003 | | 3/3/2003 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 2/26/2003 | | |
|
|
|
E-mailed the design professional in charge a copy of the plan review comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 2/11/2003 | | 2/24/2003 | | FAIL |
|
|
|
|
Routing - PLUMBING | 2/10/2003 | | 2/10/2003 | | PASS |
|
|
|
additional cross connection protection may be required on the potable water to the production area
|
Routing - PUBLIC WORKS | 2/6/2003 | | 2/10/2003 | | PASS |
|
|
|
|
Application received | | | 2/6/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/6/2003 | | |
|
|
|
1. Called and left message for Paul Marcolina that one more set of plans are required for TI's due to outside energy review. Need energy compliance information per John Menard.
|
Fee Review-notes | 2/6/2003 | 2/6/2003 | | | |
|
|
|
|