First Notice | | 5/23/2003 | 5/23/2003 | | DONE |
|
|
|
|
First Notice | | 5/23/2003 | 5/23/2003 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 5/23/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9658 issued to Enterprise Rent-A-Car.
|
Permanent Occupancy | | 5/22/2003 | 5/22/2003 | | DONE |
|
|
|
|
BLD-Final | 5/22/2003 | 5/22/2003 | 5/22/2003 | P | PASS |
Russ Owen
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Barbara MooreOk perm oc. 5/23/2003 10:44:57 AM
|
FIRE-Final Inspection | 5/13/2003 | 5/14/2003 | 5/14/2003 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled 5/14/2003 10:56:03 AM
|
BLD-Final | 5/13/2003 | 5/14/2003 | 5/14/2003 | P | PART |
Russ Owen
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Barbara MooreOk temp oc told contractor to go obtain temp from office, a perm oc would be ok pending fire/life safety approval. 5/14/2003 2:45:42 PM
|
Temporary occupancy | | | 5/14/2003 | | DONE |
|
|
|
Temp. Occ. Cert. #4953 issued 5-14-03 to Enterprise Rent-A-Car.
|
BLD-Final | 5/8/2003 | 5/12/2003 | 5/12/2003 | P | NR |
Russ Owen
|
|
|
###-#### called builder told him to recall when fire/life safety signes. 5/12/2003 4:50:56 PM
|
FIRE-Final Inspection | 5/8/2003 | 5/12/2003 | 5/12/2003 | A | FAIL |
Troy Cobbley
|
|
|
###-#### Paint curbing for the fire lane per review note #3 and drawing G101. Provide "Door to remain unlocked during business hours" at the main entry/exit. Remove manual flush bosts from the main entry/exit. See IFC 1003.3.1.8.1. Remove thumbturn from the west door. Provide one additinal emergency light at the west door in the corridor. Test other emergency light in the same corridor. 5/12/2003 8:59:24 AM
|
BLD-Framing/Rough-in | 5/2/2003 | 5/5/2003 | 5/5/2003 | P | PART |
Russ Owen
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Darla Downs > Ok except for the will leave a tile out. 5/5/2003 2:14:17 PM
|
BLD-Framing/Rough-in | 4/18/2003 | 4/21/2003 | 4/21/2003 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 4/18/2003 at 3:04:13 PM. Contact: ###-####.Posted a 2nd c/n for the curb neede new detail or have engineer ok as built . Note: contractor stated it was a over kill design and I told him that was not for him to decide, again contractor very angry. At this time beams above are exposed and under side also exposed. 4/21/2003 10:41:05 AM
|
BLD-Framing/Rough-in | 4/14/2003 | 4/15/2003 | 4/15/2003 | A | PART |
Russ Owen
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Annette Moorewalls ok pendingenginners report on hvac penetration. 4/15/2003 5:07:11 PM
|
BLD-Framing/Rough-in | 4/10/2003 | 4/11/2003 | 4/11/2003 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 4/10/2003 at 12:51:41 PM. Contact: ###-####.Walls ok but roof detail for ahu not per engineers details, posted c/n. 4/11/2003 4:27:36 PM
|
BLD-Conference | 4/9/2003 | 4/10/2003 | 4/10/2003 | A | PART |
Russ Owen
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoungContractor said architect tod him a 2 hr area separation wall existed. Plan reveiw indicated this was not needed, and I have now written a c/n for architect clairification, also may need draft stop. 4/10/2003 10:22:57 AM
|
Inspection Record Card- Bld | | | 3/31/2003 | | |
|
|
|
|
Print Occupancy Form | | | 3/31/2003 | | |
|
|
|
|
Telephone call | | | 3/31/2003 | | DONE |
|
|
|
LEFT MESS FOR WILL CHRISTIAN THAT PERMIT IS READY
|
Issue PAID IN FULL permit | | | 3/31/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 3/24/2003 | | 3/28/2003 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 2/18/2003 | | 3/28/2003 | | PASS |
|
|
|
3/28/2003 16:11:04 RMH - activity updated through activity BLDA022 from case BLD03-00251.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/26/2003 | | DONE |
|
|
|
Received two copies of resubmittal sheets A101 and RME electrical, (2) structural calculations, and cover letter. Routed to Ron Hill.
|
Routing - FIRE | 3/18/2003 | | 3/21/2003 | | PASS |
|
|
|
Plans not complete; approved subject to CONDITIONS to be field verified.
|
Case Summary (BLD) | | | 3/18/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/5/2003 | | 3/18/2003 | | FAIL |
|
|
|
Plans failed in building department review, Faxed and mailed requirements to the Will Christian of CTA, on 3/18/03, Routed plans to the fire department Same day.
|
Routing - PLUMBING | 3/4/2003 | | 3/5/2003 | | PASS |
|
|
|
1. will require thermal expansion protection.
|
Routing - PLANNING | 2/25/2003 | | 3/4/2003 | | PASS |
|
|
|
ok
|
Routing - PUBLIC WORKS | 2/21/2003 | | 2/25/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/13/2003 | | DONE |
|
|
|
|
Application received | | | 2/12/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/12/2003 | | DONE |
|
|
|
|
Fee Review-notes | 2/12/2003 | 2/12/2003 | | | |
|
|
|
|
Routing Off Site -Energy | 2/14/2003 | | | | |
|
|
|
sent to outside energy. dkl
|