BLD-Final | 5/1/2003 | 5/2/2003 | 5/2/2003 | A | PASS |
Jim Sly
|
|
|
JEFF; Phone #: ###-#### Internet Inspection Request from: Darla Downs C/C issued. 5/2/2003 9:34:46 AM
|
DOC - Permit Finaled | 5/2/2003 | 5/2/2003 | 5/2/2003 | A | PASS |
Jim Sly
|
|
|
Finaled by inspector at 5/2/2003 9:34:53 AM
|
BLD-Framing/Rough-in | 3/25/2003 | 3/26/2003 | 3/26/2003 | A | PASS |
Russ Owen
|
|
|
###-####. r-19 req in floor. 3/26/2003 10:01:37 AM
|
BLD-Foundation | 3/4/2003 | 3/6/2003 | 3/6/2003 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/4/2003 at 6:49:18 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/6/2003 | 3/6/2003 | 3/6/2003 | P | PART |
Jim Sly
|
|
|
JOSH; Phone #: ###-#### Internet Inspection Request from: Darla Downs Should have been found insp.....FOUNDATION PASS. 3/6/2003 12:48:31 PM
|
BLD-Footing | 3/4/2003 | 3/5/2003 | 3/5/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/4/2003 at 6:48:36 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 3/3/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/26/2003 | | DONE |
|
|
|
|
Telephone call | | | 2/26/2003 | | DONE |
|
|
|
permit ready and fee due
|
Pending Assignment by DJO | 2/13/2003 | | 2/25/2003 | | DONE |
Dan Overy
|
|
|
2/25/2003 13:52:41 PEP - activity updated through activity BLDA176 from case BLD03-00258.
|
Plan assigned to (PEP) | 2/25/2003 | | 2/25/2003 | | PASS |
Perry Paine
|
|
|
2/25/2003 16:47:09 PEP - activity updated through activity BLDA022 from case BLD03-00258.
|
Plan Review Report | | | 2/25/2003 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 2/25/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/25/2003 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 2/19/2003 | | 2/19/2003 | | PASS |
|
|
|
|
Routing - PLANNING | 2/13/2003 | | 2/19/2003 | | PASS |
|
|
|
2/18: Spoke w/Shannon. Plans awaiting 20 x 20 garage change. Updates submitted 2/18/03. AKT.
|
Application received | | | 2/13/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 2/19/2003 | | | | |
|
|
|
|