First Notice | | 8/27/2003 | 8/27/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/27/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9778 issued 8-27-03 to K J Beauty in the Village Shopping Center.
|
Permanent Occupancy | | 8/26/2003 | 8/26/2003 | | DONE |
|
|
|
|
BLD-Final | 8/25/2003 | 8/26/2003 | 8/26/2003 | A | PASS |
Jim Sly
|
|
|
k.j. beauty; Phone #: ###-#### Internet Inspection Request from: Marc Lileks OK for Perm Occ. :) Architect resubmital drawings of ADA front counters appr and installed ....the rest OK per plan. 8/26/2003 4:39:16 PM
|
BLD-Conference | 7/22/2003 | 7/23/2003 | 7/23/2003 | A | PASS |
Jim Sly
|
|
|
CARLA; Phone #: ###-#### Internet Inspection Request from: Dixie Fellows C/N....Last and final extension for perm Occ status....provide and complete prev corr notice.....Gave 30 days. 7/23/2003 12:17:17 PM
|
Temporary occupancy | | | 3/28/2003 | | DONE |
|
|
|
Temp. Occ. Cert. #4939 issued 3-28-03 to K J Beauty.
|
BLD-Final | 3/26/2003 | 3/27/2003 | 3/27/2003 | A | FAIL |
Russ Owen
|
|
|
CARLA; Phone #: ###-#### Internet Inspection Request from: Darla Downs. Ok for a temp oc, left a correction on site will need the architect to address some items and or plan review. 3/27/2003 11:58:46 AM
|
FIRE-Final Inspection | 3/20/2003 | 3/20/2003 | 3/20/2003 | P | PASS |
Rick Jackson
|
|
|
CARLA ###-#### FOR BEAUTY all items from previous inspection corrected 3/20/2003 4:33:26 PM
|
FIRE-Final Inspection | 3/18/2003 | 3/19/2003 | 3/19/2003 | A | FAIL |
Troy Cobbley
|
|
|
CARLA; Phone #: ###-#### Provide annual inspection for the fire extinguisher in the spa, provide emergency light in the spa and repair the exit sign in the corridor outside of the spa 3/19/2003 8:51:33 AM
|
FIRE-Final Inspection | 3/11/2003 | 3/12/2003 | 3/12/2003 | A | FAIL |
Troy Cobbley
|
|
|
robert; Phone #: ###-#### Replace the painted sprinkler pendant in storage room 109 or remove it. Repair the exit/emergency light in the spa corridor. Add emergency light in the spa. Provide atleast three more fire extinguishers. Retag the existing fire extinguisher. Verify current inspection on the fire sprinkler system. Remove thumbturns on the rear exit doors. Remove the dead bolts on the main entry/exit. Replace the door hardware on restrooms 107, 113, 114 and the closet next to 113. 3/12/2003 10:36:57 AM
|
BLD-Other | 3/11/2003 | 3/11/2003 | 3/11/2003 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/11/2003 at 8:22:39 AM. Contact: ###-####. Talked to owner....Need all Req. signatures. 3/11/2003 2:16:42 PM
|
Issue PAID IN FULL permit | | | 3/7/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/5/2003 | | 3/6/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2003 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 3/6/2003 | | |
|
|
|
|
Print Occupancy Form | | | 3/6/2003 | | |
|
|
|
|
Telephone call | | | 3/6/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Plan assigned to (CJW) | 2/18/2003 | | 3/6/2003 | | PASS |
Carl Westfall
|
|
|
3/6/2003 08:31:09 CJW - activity updated through activity BLDA022 from case BLD03-00260.
|
Routing - FIRE | 3/3/2003 | | 3/5/2003 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 3/5/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/25/2003 | | 3/3/2003 | | PASS |
|
|
|
UBC plan review started February 28, 2003 and finished March 3, 2003. The drawings were approved with conditions. See the plan review report.
|
Routing - PUBLIC WORKS | 2/21/2003 | | 2/25/2003 | | PASS |
|
|
|
|
Application received | | | 2/13/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/13/2003 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/13/2003 | | DONE |
|
|
|
NO ENERGY REVIEW per Marlene & Carl.
|
Fee Review-notes | 2/13/2003 | 2/13/2003 | | | |
|
|
|
|