Case Summary (BLD) | | | 9/18/2014 | | DONE |
|
|
|
|
BLD-Aging Inspection | 1/16/2004 | 1/16/2004 | 1/16/2004 | | PASS |
Tom Arcoraci
|
|
|
|
CHANGE STATUS TO (FNL) | | | 1/16/2004 | | |
|
|
|
|
Case Summary (BLD) | | | 11/25/2003 | | DONE |
|
|
|
|
Letter of compliance | | | 8/13/2003 | | DONE |
|
|
|
Letter of Compliance #22982 issued 8-13-03.
|
FIRE-Final Inspection | 8/12/2003 | 8/12/2003 | 8/12/2003 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 8/12/2003 at 6:50:02 AM. Contact: ###-####.
|
BLD-Final | 8/12/2003 | 8/12/2003 | 8/12/2003 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/12/2003 at 6:51:35 AM. Contact: ###-####. ok for perm 8/12/2003 3:19:43 PM
|
FIRE-Final Inspection | 7/30/2003 | 7/31/2003 | 7/31/2003 | A | FAIL |
Troy Cobbley
|
|
|
Remove thumbturn from the main exit, provide ADA compliant door hardware on the 7/31/2003 12:43:44 PM
|
BLD-Final | 7/30/2003 | 7/31/2003 | 7/31/2003 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/30/2003 at 3:17:46 PM. Contact: ###-####. ok pending fire 7/31/2003 2:37:46 PM
|
FIRE-Final Inspection | 7/31/2003 | 7/31/2003 | 7/31/2003 | P | FAIL |
Troy Cobbley
|
|
|
Remove thumbturn from the main exit, provide ADA compliant door hardware on the pocket doors, provide "Door to remain unlocked" sticker at the main exit, provide suite numbers, provide automatic shutdown on the hvac system per IMC 606, provide remote alarm/trouble indicators per IMC 606.4.1 #2 and repair the emergency light
|
Code Occupancy Approval | | | 7/31/2003 | | PASS |
|
|
|
ALL IN AS REQUIRED FINAL SIGNED OFF.
|
BLD-Other | 7/25/2003 | 7/25/2003 | 7/25/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/25/2003 at 6:55:33 AM. Contact: ###-####. grid ok 7/25/2003 9:17:18 AM
|
Print Occupancy Form | | | 7/24/2003 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 6/4/2003 | 6/5/2003 | 6/5/2003 | A | PASS |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Energy code compliance | 6/4/2003 | 6/5/2003 | 6/5/2003 | A | PASS |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Framing/Rough-in | 5/30/2003 | 6/2/2003 | 6/2/2003 | A | FAIL |
Russ Owen
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Barbara Mooreposted a c/n. 6/2/2003 11:30:16 AM
|
BLD-Wall cover | 5/21/2003 | 5/22/2003 | 5/22/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/21/2003 at 4:02:10 PM. Contact: ###-####. ok to side 5/22/2003 11:07:00 AM
|
BLD-Other | 5/19/2003 | 5/20/2003 | 5/20/2003 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/19/2003 at 4:28:46 PM. Contact: ###-####. paraphet ok and cs strap on roof installed 5/20/2003 9:32:17 AM
|
BLD-Foundation | 4/25/2003 | 4/25/2003 | 4/25/2003 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/25/2003 at 8:04:33 AM. Contact: ###-####.
|
BLD-Footing | 4/24/2003 | 4/24/2003 | 4/24/2003 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 4/24/2003 at 7:23:29 AM. Contact: ###-####. Needs up rights in and tied in place told contractor i would set him up with a pm inspection . also noted with him that it is now 11:15 and he should have called in for a pm inspection. 4/24/2003 11:38:14 AM
|
BLD-Footing | 4/24/2003 | 4/24/2003 | 4/24/2003 | P | PASS |
Russ Owen
|
|
|
ok last part of footing. 4/24/2003 2:06:16 PM
|
BLD-Foundation | 4/21/2003 | 4/22/2003 | 4/22/2003 | A | PASS |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Footing | 4/17/2003 | 4/18/2003 | 4/18/2003 | A | PASS |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ground installed in footing
4/18/2003 10:58:21 AM
|
(F) Reprint permit | | | 4/16/2003 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/15/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/9/2003 | | DONE |
|
|
|
|
Telephone call | | | 4/9/2003 | | DONE |
|
|
|
permit ready and need ACHD
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2003 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 2/18/2003 | | 4/8/2003 | | PASS |
Mike Otto
|
|
|
4/8/2003 14:54:56 MLO - activity updated through activity BLDA022 from case BLD03-00273.
|
Routing Off Site -Energy | 3/31/2003 | | 4/4/2003 | | PASS |
|
|
|
resubs sent to Ron Oltman
|
Routing - PLANNING Land Div | 4/3/2003 | | 4/3/2003 | | PASS |
|
|
|
Approved. Parcel was part of an original parcel recorded February 12, 1956, deed #171 387.
|
Routing Off Site - STRUCTURAL | 3/21/2003 | | 4/2/2003 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/31/2003 | | 4/1/2003 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 3/31/2003 | | 3/31/2003 | | FAIL |
|
|
|
Need deed recorded prior to 1965 to verify legal land division. Call Oscar at Larry Knopp Architects on March 31, 2003. Said he would call Title Company.
|
Routing - PLAN CHECK | 3/21/2003 | | 3/28/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 3/21/2003 | | DONE |
|
|
|
xtra set for engineering review. MLO
|
Plan resubmittals received | | | 3/21/2003 | | DONE |
|
|
|
Received two copies of HVAC calculations, struct. engineers letter dated 3/19/03, additional copy of sheets A0, A4 and A9, previously provided only two copies and three copies of sheet A6. routed to Mike O. kmm
|
Plan resubmittals received | | | 3/18/2003 | | DONE |
|
|
|
Received two copies of revised sheets A0, A4, A6 & A9, and two copies of truss drawings and calcs. One response letter and design criteria. Routed to Mike O. kmm
|
Routing - PLAN CHECK | 3/18/2003 | | 3/18/2003 | | FAIL |
|
|
|
corrections faxed and mailed to architect
|
Routing - FIRE | 3/10/2003 | | 3/13/2003 | | PASS |
|
|
|
no corrections required
|
Routing Off Site - STRUCTURAL | 2/18/2003 | | 3/7/2003 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside eng. kmm
|
Routing Off Site -Energy | 2/18/2003 | | 3/7/2003 | | FAIL |
|
|
|
Plans to go to Ron O. for outside energy review. kmm
|
Routing - PLUMBING | 2/25/2003 | | 2/25/2003 | | PASS |
|
|
|
|
Routing - PLANNING | 2/21/2003 | | 2/25/2003 | | PASS |
|
|
|
Approved per DRH02-194.
|
Routing - Erosion and Sediment | 2/21/2003 | | 2/21/2003 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 2/18/2003 | | 2/21/2003 | | FAIL |
|
|
|
Requires Drainage plan.
|
Plans ACCEPTED BY PLAN TECH | | | 2/18/2003 | | DONE |
|
|
|
Separate permit will route with these plans for the TI for Chad Ward Real Estate.
|
Routing - PLANNING Land Div | 2/18/2003 | | 2/18/2003 | | FAIL |
|
|
|
Need to provide copy of recorded deed prior to October 30, 1965 to document legal land division. Called Larry Knopp's office on February 18, 2003. Required by Condition of Approval #1.d in DRH02-194 approved on November 14, 2002. Existing ROS 0977 divided parcel on October 31, 1986.
|
Plan routing begun/NEW & ADDTN | | | 2/18/2003 | | DONE |
|
|
|
|
Application received | | | 2/14/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/14/2003 | | DONE |
|
|
|
|
Fee Review-notes | 2/14/2003 | 2/14/2003 | | | |
|
|
|
|