Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD03-00300
StatusFinaled
Name VANITY
Site Address 350 N MILWAUKEE ST Unit: 2007
Project NameBTS - #2007
Customer Number 
ePlanReviewNo
Description
(VANITY)(BOISE TOWNE SQUARE-SPACE 2007) To remodel a 2,235 sq.ft. retail space for new tenant on the upper level per approved plans. Work to include, construction of new storefront system, installation of new suspended ceiling system, construction of interior partitions to create dressing rooms, storage area and accessible restroom. Miscelaneous related interior finishes. NOTE: This buidling is fully fire sprinklerd and contains a smoke evacutation system, any alterations to the fire sprinkler system shall be per NFPA # as regulated by the fire depatment. The smoke evacutation system shall remain as installed under the 1985 UBC. (PC#070-03) rmh
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 6/25/20036/25/2003 DONE
Permanent occupancy  6/25/2003 DONE
Perm. Occ. Cert. #9706 issued 6-25-03 to Vanity on the upper level of Boise Towne Square.
Temporary occupancy  6/24/2003 DONE
Temp. Occ. Cert. #4964 issued 6-24-03 to Vanity on the upper level of Boise Towne Square.
FIRE-Final Inspection6/16/20036/16/20036/16/2003PPASS
DetailsTroy Cobbley
OK for perm occupancy 6/16/2003 4:06:46 PM
FIRE-Final Inspection6/5/20036/6/20036/6/2003APART
DetailsRick Jackson
mitch; Phone #: ###-#### Internet Inspection Request from: Barbara Moore fire on temp per Sam Rogers as the duct detector for AHU shutdown will be installed next week 6/6/2003 11:53:17 AM
BLD-Final6/5/20036/6/20036/6/2003PPART
DetailsJim Storey
mitch; Phone #: ###-#### Internet Inspection Request from: Barbara Moore temp ok final ok pending fire insp. sign off. 6/6/2003 4:22:39 PM
FIRE-Final Inspection6/5/20036/5/20036/5/2003PFAIL
DetailsTroy Cobbley
###-#### Provide current inspection tags for the two fire extinguishers, provide the correct listed eschouceon on the sprinkler pendant outside of the entrance, replace the two painted sprinkler pendants just inside of the entrance, provide missing eschouceon for the pendant in the restroom, provide approved doorhardware on the dressing room doors and door 100, provide verification that the existing hvac unit does not require a duct smoke detector or provide and test, provide testing for the smoke evac system 6/5/2003 2:47:37 PM
FIRE-Final Inspection6/3/20036/4/20036/4/2003PCANC
DetailsTroy Cobbley
###-####
I spoke to the contractor and he stated that he needed to cancel the inspection due to duct smoke detector problems 6/4/2003 2:49:42 PM
BLD-Framing/Rough-in6/2/20036/3/20036/3/2003APART
DetailsRuss Owen
mitch grid; Phone #: ###-#### Internet Inspection Request from: Barbara MooreoK BUT REST ROOM NEEDS MORE WIRES, WILL LEAVE OPEN FOR A LATER INSPECTION. 6/5/2003 10:14:24 AM
BLD-Framing/Rough-in5/29/20035/30/20035/30/2003APASS
DetailsRuss Owen
MITCH; Phone #: ###-#### Internet Inspection Request from: Marsha SmylieOk for cover at front area. 5/30/2003 12:59:46 PM
BLD-Framing/Rough-in5/23/20035/27/20035/27/2003APART
DetailsRuss Owen
mitch; Phone #: ###-#### Internet Inspection Request from: Barbara Moorepending detail from architect for entry.contractor on site notified said detail would be coming.and he will call for re-insp asap. 5/27/2003 11:58:09 AM
BLD-Framing/Rough-in5/9/20035/12/20035/12/2003PPART
DetailsRuss Owen
mitch; Phone #: ###-#### Internet Inspection Request from: Annette MooreRear area ok rest room needs a new detail from architect should be ok as is. front not built and will need details as duct in way. 5/12/2003 1:47:52 PM
Inspection Record Card- Bld  4/23/2003 DONE
Print Occupancy Form  4/23/2003 DONE
Telephone call  4/23/2003 DONE
permit ready and fees due
Issue PAID IN FULL permit  4/23/2003 DONE
Routing - PLAN CHECK3/17/2003 4/22/2003 DONE
PLANS/APPL TAKEN TO FRONT DESK  4/22/2003 DONE
Plan assigned to (R_H)2/21/2003 4/22/2003 PASS
Details
4/22/2003 16:08:18 RMH - activity updated through activity BLDA022 from case BLD03-00300.
Plan resubmittals received  4/21/2003 DONE
received three plans of E-1 and letter from Richard Burns Associates,Britt Makela Group, 2 page Lighting Wattage Worksheet, Energy code compliance Ashrae 90.1 -1989 (AT6024T) tech lighting.
Plan resubmittals received  4/8/2003 DONE
Received three sets of resubmittal sheets A2.1, A2.2, and cover letter. Routed to Ron Hill.
Routing - FIRE3/11/2003 3/14/2003 PASS
Routing - PLAN CHECK2/24/2003 3/11/2003 FAIL
Faxed requirements to architect and tenant on 3/11/03, Routed plans to the fire department. Failed in building and energy reviews.
Routing - PUBLIC WORKS2/21/2003 2/24/2003 PASS
Application received  2/19/2003  
Recd Pcfee & Taken To Pln CK  2/19/2003 DONE
Plans ACCEPTED BY PLAN TECH  2/19/2003 DONE
Fee Review-notes8/14/20038/14/2003   
Fee Review-notes2/19/20032/19/2003   
Routing Off Site -Energy2/21/2003    
called ron oltman for outside energy review.dkl