BLD-Final | 8/7/2003 | 8/7/2003 | 8/7/2003 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 8/7/2003 at 8:04:12 AM. Contact: ###-####....ok for l/c 8/7/2003 3:48:14 PM
|
DOC - Permit Finaled | 8/7/2003 | 8/7/2003 | 8/7/2003 | P | PASS |
Carl Dependahl
|
|
|
Finaled by inspector at 8/7/2003 3:48:17 PM
|
FIRE-Final Inspection | 8/6/2003 | 8/6/2003 | 8/6/2003 | P | PASS |
Rick Jackson
|
|
|
verfied damper operation - okay; penetrations fire stopped at walls and at new wall for new doors 8/6/2003 12:31:59 PM
|
BLD-Wall cover | 5/30/2003 | 5/30/2003 | 5/30/2003 | P | PART |
Carl Dependahl
|
|
|
dan; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 5/29/2003 | 5/29/2003 | 5/29/2003 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/29/2003 at 7:13:38 AM. Contact: ###-####. need to fire cualk and protect all opennings in walls and floors 5/29/2003 12:04:34 PM
|
BLD-Framing/Rough-in | 5/28/2003 | 5/28/2003 | 5/28/2003 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 5/28/2003 at 7:44:52 AM. Contact: ###-####.
|
Issue & PRINT to be Invoiced | | | 4/9/2003 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/9/2003 | | DONE |
|
|
|
|
Plan assigned to (MYS) | 2/21/2003 | 2/21/2003 | 4/7/2003 | | PASS |
Marlene Southard
|
|
|
4/7/2003 14:20:14 DRS - activity updated through activity BLDA022 from case BLD03-00315.
|
Routing - PUBLIC WORKS | 4/4/2003 | | 4/7/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/7/2003 | | 4/7/2003 | | PASS |
|
|
|
Plans to front desk for issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2003 | | PASS |
|
|
|
To permit desk to issue.
|
Inspection Record Card- Bld | | | 4/7/2003 | | |
|
|
|
|
Telephone call | | | 4/7/2003 | | DONE |
|
|
|
e-mailed curtis that permit is ready
|
Routing - FIRE | 3/31/2003 | | 4/4/2003 | | PASS |
|
|
|
resubmittal acceptable.
|
Routing - PLAN CHECK | 4/4/2003 | | 4/4/2003 | | PEND |
|
|
|
To public works for review. Given to BAD
|
Routing - PLAN CHECK | 3/18/2003 | | 3/31/2003 | | PEND |
|
|
|
3/31/03 - Inserted new architectural plan sheets A1, A2, & A3, received 3/28/03, & new lighting certificate. No further re-submittals required.Routing to fire code analyst for re-review.
|
Plan resubmittals received | | | 3/28/2003 | | DONE |
|
|
|
Received two sets of resubmittal sheets A!,A2,A3 with (2) Comment Letter and transmittal. Routed to Dan Stuart.
|
Routing - FIRE | 3/13/2003 | | 3/17/2003 | | FAIL |
|
|
|
comments faxed to architect.
|
Plan resubmittals requested | | | 3/13/2003 | | FAIL |
|
|
|
Corrections & clarifications required. Copy of plan review comments needing addressed faxed and mailed to architect. Routing plans to fire code analyst for review.
|
Routing - PLAN CHECK | 2/28/2003 | | 3/13/2003 | | FAIL |
|
|
|
Routed to Dan S. kmm
3/13/03 - Plan resubmittals & clarifications requested. Routed to fire code analyst for review.
|
Plan resubmittals received | | | 3/5/2003 | | DONE |
|
|
|
Received three copies of revised sheets A0, EN1.0, A1, A2, A3, M1, M2, M3, E1.0, E2.1, E3.1. Routed to Dan S. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 2/24/2003 | | FAIL |
|
|
|
Requires third set of plans for outside energy review. Energy code compliance must be incorporated into the plans before routing. Contacted Curtis/Gregg of these needs. Plans on my table. kmm
|
Application received | | | 2/21/2003 | | |
|
|
|
|