BLD-Final | 4/9/2004 | 4/9/2004 | 4/9/2004 | A | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 4/9/2004 at 7:01:35 AM. MATT CALLED TO CANS INSPECTION THIS MORNING & TO PUT IT IN FOR THIS AFTERNOON
|
BLD-Final | 4/9/2004 | 4/9/2004 | 4/9/2004 | P | PART |
Tony Young
|
|
|
MATT; Phone #: ###-#### Internet Inspection Request from: Darla Downs
ok for occupancy now but need to see actual railing on stair s when they get in, along w/ other items,,, owner said they are not moving in for a month or so 4/9/2004 3:33:20 PM
|
BLD-Grading Inspection | 4/9/2004 | 4/9/2004 | 4/9/2004 | | BND |
Rita DeYoung
|
|
|
The grading and drainage is conditionally approved. A $2000.00 bond has been submitted to ensure that the roof drain system is installed properly and the grading that was extended across the property line is removed and the adjacent lot restored.
|
BLD-Final | 4/8/2004 | 4/8/2004 | 4/8/2004 | P | NR |
Tony Young
|
|
|
MATT; Phone #: ###-#### Internet Inspection Request from: Darla Downs
need trades and hillside prior to inspection 4/8/2004 4:43:22 PM
|
BLD-Conference | 3/26/2004 | 3/29/2004 | 3/29/2004 | A | PART |
Tony Young
|
|
|
matt- ###-####
conf on stairs and procedure 3/29/2004 1:41:35 PM
|
BLD-Conference | 3/25/2004 | 3/26/2004 | 3/26/2004 | A | CANC |
Troy James
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Energy code compliance | 9/26/2003 | 9/29/2003 | 9/29/2003 | A | CANC |
Tony Young
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Framing/Rough-in | 9/26/2003 | 9/29/2003 | 9/29/2003 | A | CANC |
Tony Young
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Framing/Rough-in | 9/29/2003 | 9/29/2003 | 9/29/2003 | P | PART |
Tony Young
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Darla Downs
stairs not right yet, will verify at final 9/29/2003 2:49:01 PM
|
BLD-Energy code compliance | 9/29/2003 | 9/29/2003 | 9/29/2003 | P | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 9/24/2003 | 9/25/2003 | 9/25/2003 | A | FAIL |
Tony Young
|
|
|
Matt brown phone # ###-####
c/n posted,,, ok to insulate 9/25/2003 11:17:24 AM
|
BLD-Framing/Rough-in | 9/24/2003 | 9/24/2003 | 9/24/2003 | P | NR |
Tony Young
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Framing/Rough-in | 9/18/2003 | 9/18/2003 | 9/18/2003 | P | FAIL |
Tony Young
|
|
|
MATHEW; Phone #: ###-#### Internet Inspection Request from: Marc Lileks
conf. only on framing,,, will work on verbal corrections and recall, no insulation 9/18/2003 3:12:53 PM
|
BLD-Framing/Rough-in | 9/17/2003 | 9/17/2003 | 9/17/2003 | P | PART |
Tony Young
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Darla Downs
ext shear ok 9/17/2003 3:45:40 PM
|
BLD-Framing/Rough-in | 9/15/2003 | 9/16/2003 | 9/16/2003 | A | CANC |
Jim Sly
|
|
|
matt shear wall; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Footing | 6/26/2003 | 6/27/2003 | 6/27/2003 | A | PASS |
Dave Hannah
|
|
|
fred; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Foundation | 5/20/2003 | 5/20/2003 | 5/20/2003 | P | PART |
Tony Young
|
|
|
clint late afternoon; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
wip 5/21/2003 10:59:29 AM
|
BLD-Footing | 5/14/2003 | 5/15/2003 | 5/15/2003 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/14/2003 at 1:01:52 PM. Contact: ###-####.
soil ok per T.R. 5/15/2003 2:26:20 PM
|
Issue PAID IN FULL permit | | | 5/6/2003 | | DONE |
|
|
|
|
Telephone call | | | 4/8/2003 | | DONE |
|
|
|
left mess for matt brown that permit is ready
|
Plan assigned to (DJO) | 3/20/2003 | 3/20/2003 | 3/20/2003 | | PASS |
Dan Overy
|
|
|
3/20/2003 11:00:37 DJO - activity updated through activity BLDA022 from case BLD03-00364.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/20/2003 | | DONE |
|
|
|
|
Plan Review Report | | | 3/20/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2003 | | |
|
|
|
|
Print Occupancy Form | | | 3/20/2003 | | DONE |
|
|
|
|
Telephone call | | | 3/20/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Plans ACCEPTED BY PLAN CHECK | | | 3/20/2003 | | |
|
|
|
|
Routing - Erosion and Sediment | 3/4/2003 | | 3/4/2003 | | PASS |
|
|
|
ESC approved with attached conditions.
|
Routing - PLANNING | 3/3/2003 | | 3/4/2003 | | PASS |
|
|
|
|
Routing - FIRE | 3/4/2003 | | 3/4/2003 | | DONE |
|
|
|
No fire sprinklers required (Arrowhead Canyon)
|
Routing - PUBLIC WORKS GRADING | 2/28/2003 | | 3/3/2003 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3
|
Routing - PUBLIC WORKS | 3/3/2003 | | 3/3/2003 | | PASS |
|
|
|
NORTHWEST BOISE SEWER DISTRICT
|
Application received | | | 2/28/2003 | | |
|
|
|
|
Pending Assignment by DJO | 2/28/2003 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 3/4/2003 | | | | |
|
|
|
|