Letter of compliance | | | 8/19/2003 | | DONE |
|
|
|
Letter of Compliance #22986 issued 8-18-03 by Barbara
|
BLD-Final | 8/13/2003 | 8/14/2003 | 8/14/2003 | P | PASS |
Tom Arcoraci
|
|
|
brian ; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Final | 8/13/2003 | 8/13/2003 | 8/13/2003 | P | FAIL |
Tom Arcoraci
|
|
|
Phone #: ###-#### Internet Inspection Request from: Linda Hartwell cn issued handrail ht no elec final 8/13/2003 1:59:00 PM
|
BLD-Framing/Rough-in | 5/8/2003 | 5/9/2003 | 5/9/2003 | A | PASS |
Jim Storey
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Energy code compliance | 5/8/2003 | 5/9/2003 | 5/9/2003 | P | PASS |
Jim Storey
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Energy code compliance | 5/6/2003 | 5/8/2003 | 5/8/2003 | P | CANC |
Jim Storey
|
|
|
###-####
|
BLD-Framing/Rough-in | 5/7/2003 | 5/8/2003 | 5/8/2003 | A | NR |
Jim Storey
|
|
|
c/n not done. 5/8/2003 8:48:47 AM
|
BLD-Framing/Rough-in | 5/8/2003 | 5/8/2003 | 5/8/2003 | P | PART |
Jim Storey
|
|
|
BRIAN ###-#### -RE-INSP fire blk ok truss bracing not done. 5/8/2003 1:45:49 PM
|
BLD-Framing/Rough-in | 5/6/2003 | 5/7/2003 | 5/7/2003 | P | PART |
Jim Storey
|
|
|
###-#### ###-#### foire blk 2 nd floor mech chase/ truss bracing. 5/7/2003 5:13:28 PM
|
BLD-Framing/Rough-in | 5/6/2003 | 5/6/2003 | 5/6/2003 | P | PART |
Tom Arcoraci
|
|
|
bryan; Phone #: ###-#### Internet Inspection Request from: Annette Moore ok to side only 5/6/2003 4:14:06 PM
|
BLD-Framing/Rough-in | 4/28/2003 | 4/28/2003 | 4/28/2003 | P | NR |
Dave Hannah
|
|
|
bryan shear; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Foundation | 4/2/2003 | 4/3/2003 | 4/3/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/2/2003 at 3:10:21 PM. Contact: ###-####.
|
BLD-Footing | 4/2/2003 | 4/2/2003 | 4/2/2003 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/2/2003 at 6:46:44 AM. Contact: ###-####.checked set backs all ok 4/2/2003 11:59:26 AM
|
Issue PAID IN FULL permit | | | 3/26/2003 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 3/24/2003 | 3/24/2003 | 3/24/2003 | | PASS |
Dan Overy
|
|
|
3/24/2003 10:32:52 DJO - activity updated through activity BLDA022 from case BLD03-00397.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/24/2003 | | DONE |
|
|
|
|
Plan Review Report | | | 3/24/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/24/2003 | | |
|
|
|
|
Telephone call | | | 3/24/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Plans ACCEPTED BY PLAN CHECK | | | 3/24/2003 | | |
|
|
|
|
Routing - PUBLIC WORKS | 3/10/2003 | | 3/11/2003 | | PASS |
|
|
|
|
Routing - PLANNING | 3/10/2003 | | 3/10/2003 | | PASS |
|
|
|
Rcvd. updated site plan. AKT
|
Application received | | | 3/5/2003 | | |
|
|
|
|
Routing - PLANNING | 3/5/2003 | | 3/5/2003 | | FAIL |
|
|
|
Spoke w/Designer: Vehicular back up area is inadequate. Flip site. AKT
|
Pending Assignment by DJO | 3/5/2003 | | | | |
Dan Overy
|
|
|
|
Routing - PLAN CHECK | 3/12/2003 | | | | |
|
|
|
|