Case Summary (BLD) | | | 7/2/2013 | | DONE |
|
|
|
|
Fee Review-notes | 3/7/2003 | 3/7/2003 | 4/30/2007 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/12/2003 | | 4/30/2007 | | PASS |
|
|
|
Failed first UBC review. UBC plan review started April 7, 2003 and finished April 10, 2003. A response from the architect was required. See the plan review report.
|
Third Notice BLD | 4/9/2007 | 4/9/2007 | 4/13/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 3/30/2007 | 3/30/2007 | 4/9/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 3/20/2007 | 3/30/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/20/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11486 issued 3-20-07 to Holland & Hart in the U.S. Bank Bldg.
|
Print Occupancy Form | | | 3/13/2007 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/9/2007 | | DONE |
|
|
|
|
BLD-Aging Inspection | 9/16/2004 | 9/16/2004 | 9/16/2004 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Expired | 9/16/2004 | 9/16/2004 | 9/16/2004 | A | PASS |
Dave Hannah
|
|
|
Expired by inspector at 9/16/2004 8:06:49 AM
|
BLD-Final | 7/2/2004 | 7/6/2004 | 7/6/2004 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/2/2004 at 8:15:55 AM. Contact: ###-####. ok for perm occ 7/6/2004 10:24:15 AM
|
Permanent Occupancy | | 7/6/2004 | 7/6/2004 | | DONE |
|
|
|
|
BLD-Final | 4/22/2004 | 4/23/2004 | 4/23/2004 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/22/2004 at 3:08:20 PM. Contact: ###-####. ok for temp occ 4/23/2004 4:49:09 PM
|
FIRE-Final Inspection | 4/22/2004 | 4/22/2004 | 4/22/2004 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 4/22/2004 at 8:37:18 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/16/2004 | 3/17/2004 | 3/17/2004 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/16/2004 at 11:32:42 AM. Contact: ###-####. lid in confunce room ok to rock 3/17/2004 9:50:58 AM
|
BLD-Conference | 3/4/2004 | 3/5/2004 | 3/5/2004 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/4/2004 at 1:35:46 PM. Contact: ###-####.
|
BLD-Conference | 3/5/2004 | 3/5/2004 | 3/5/2004 | P | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/4/2004 at 1:35:46 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/1/2004 | 3/2/2004 | 3/2/2004 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/1/2004 at 8:57:13 AM. Contact: ###-####.steel stud partion walls north half 3/2/2004 10:53:49 AM
|
BLD-Framing/Rough-in | 2/12/2004 | 2/12/2004 | 2/12/2004 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/12/2004 at 8:48:10 AM. ok to cover bath room walls 2/12/2004 4:58:28 PM
|
BLD-Final | 1/6/2004 | 1/7/2004 | 1/7/2004 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/6/2004 at 3:40:58 PM. Contact: ###-####. ok to occ phase one 1/8/2004 7:33:52 AM
|
BLD-Final | 12/31/2003 | 1/5/2004 | 1/5/2004 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/31/2003 at 2:50:20 PM. Contact: ###-####. needs fire cualking shaft walls 1/5/2004 11:43:34 AM
|
FIRE-Final Inspection | 12/19/2003 | 12/22/2003 | 12/22/2003 | P | PART |
Rick Jackson
|
|
|
phased project - okay to occupy the south half of 14th floor; second exit to be maintained 12/22/2003 4:15:08 PM
|
BLD-Framing/Rough-in | 12/16/2003 | 12/17/2003 | 12/17/2003 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/16/2003 at 11:57:53 AM. Contact: ###-####. out of time reschedled for pm 12/17/2003 11:21:20 AM
|
BLD-Framing/Rough-in | 12/17/2003 | 12/17/2003 | 12/17/2003 | P | PART |
Dave Hannah
|
|
|
walls are kicked with 45s but need arc to ok ceiling grid desegn 12/17/2003 2:09:14 PM
|
BLD-Framing/Rough-in | 11/24/2003 | 11/25/2003 | 11/25/2003 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/24/2003 at 2:49:19 PM. Contact: ###-####. ok to cover after elec r/i 11/25/2003 11:30:21 AM
|
Plan Reviewer's activity | | | 9/9/2003 | | DONE |
|
|
|
Reviewed and approved the resubmitted drawings for compliance with the "Letter of Understanding" signed by the building owners and the City of Boise.
|
Plan resubmittals received | | | 7/15/2003 | | DONE |
|
|
|
letter of transmittal, Project letter, with, three copies of A1.0,A2.0,A3.0, A4.1, A6.0, A7.0, A8.0, A9.1, A11.0, and taken to Carl.
|
BLD-Conference | 4/30/2003 | 5/1/2003 | 5/1/2003 | A | PART |
Carl Dependahl
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Barbara Moore...w/ Jason B...no cisca-2 spec available (which is referenced in 1621 IBC.) re suspended ceilings. 5/1/2003 2:54:33 PM
|
BLD-Conference | 5/1/2003 | 5/1/2003 | 5/1/2003 | A | CANC |
Carl Dependahl
|
|
|
Chris
|
BLD-Conference | 5/1/2003 | 5/1/2003 | 5/1/2003 | P | PASS |
Carl Dependahl
|
|
|
Chris, Install grid per " seismic C " specs...floating. 5/1/2003 2:56:26 PM
|
Issue PAID IN FULL permit | | | 4/24/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 4/17/2003 | | 4/18/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/18/2003 | | PASS |
|
|
|
|
Print Occupancy Form | | | 4/18/2003 | | DONE |
|
|
|
|
Telephone call | | | 4/18/2003 | | DONE |
|
|
|
permit ready
|
Plan assigned to (CJW) | 3/7/2003 | | 4/18/2003 | | PASS |
Carl Westfall
|
|
|
4/18/2003 10:06:22 CJW - activity updated through activity BLDA022 from case BLD03-00436.
|
Routing - FIRE | 4/11/2003 | | 4/17/2003 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 4/17/2003 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 3/7/2003 | | 3/12/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/7/2003 | | |
|
|
|
|
Application received | | | 3/7/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/7/2003 | | |
|
|
|
|