First Notice | | 9/10/2003 | 9/10/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 8/18/2003 | 8/18/2003 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 8/18/2003 | | DONE |
|
|
|
Perm. Occ. cert. #9767 issued 8-18-03 to the Kane Square Four-Plexes.
|
FIRE-Final Inspection | 8/11/2003 | 8/12/2003 | 8/12/2003 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 8/13/2003 9:20:07 AM
|
Temporary occupancy | | | 8/7/2003 | | DONE |
|
|
|
Temp. Occ. Cert. #4983 issued 8-7-03 to the Signature Square Subdivision.
|
FIRE-Final Inspection | 8/4/2003 | 8/5/2003 | 8/5/2003 | P | PART |
Troy Cobbley
|
|
|
nick ###-#### A temporary occupancy was given with Dave Millers permission until either the contractor provides a listing for the smoke detector that states coverage or provides an additional smoke detectors 8/5/2003 4:22:31 PM
|
BLD-Final | 8/4/2003 | 8/5/2003 | 8/5/2003 | A | PART |
Tom Arcoraci
|
|
|
NICK; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok after others sign 8/5/2003 10:50:52 AM
|
Code Occupancy Approval | | | 8/5/2003 | | FAIL |
|
|
|
Inspection noted no landscaping and no bonding. Contractor showed me his set of plans that had "no" landscaping plans. I showed him our CUP02-00028 file with a set of landscaping plans.
|
BLD-Framing/Rough-in | 6/17/2003 | 6/18/2003 | 6/18/2003 | A | PASS |
Tom Arcoraci
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 6/13/2003 | 6/16/2003 | 6/16/2003 | A | PART |
Tom Arcoraci
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to insulate upper floor needs fire stopping on floor assemble 6/16/2003 10:25:14 AM
|
PubWorks Occupancy Approval | | | 5/15/2003 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 5/15/03. S.Landaluce
|
BLD-Framing/Rough-in | 5/9/2003 | 5/9/2003 | 5/9/2003 | P | PART |
Tom Arcoraci
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Annette Moore party wall 5/9/2003 3:18:46 PM
|
Issue PAID IN FULL permit | | | 5/6/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 4/30/2003 | | 5/5/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/5/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/5/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/5/2003 | | DONE |
|
|
|
|
Telephone call | | | 5/5/2003 | | |
|
|
|
|
Print Occupancy Form | | | 5/5/2003 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 3/11/2003 | | 5/5/2003 | | PASS |
Mike Phillips
|
|
|
5/5/2003 09:00:31 M_P - activity updated through activity BLDA022 from case BLD03-00439.
|
Routing Off Site - STRUCTURAL | 4/29/2003 | | 5/2/2003 | | DONE |
|
|
|
Contacted PDQ to take revised plans of 4/25/03 to outside engineering. kmm
|
Routing - PLAN CHECK | 4/18/2003 | | 4/30/2003 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Routing Off Site - STRUCTURAL | 4/10/2003 | | 4/30/2003 | | FAIL |
|
|
|
Plan resubmittals of 4/10/03. Contacted PDQ to take plans to outside eng. kmm
Additional information required for further review.
|
Plan resubmittals received | | | 4/25/2003 | | DONE |
|
|
|
Received three copies of revised sheets A2.0, A2.1, A3.0, A4.;0, A7.0, A7.1, A7.2, A8.0, A10.0, E2.0, M1.0, NRG and one copy of response letter. Routed to Mike P. kmm
|
Routing - PLANNING Land Div | 4/18/2003 | | 4/18/2003 | | PASS |
|
|
|
Lot 1 of Signature Square Subdivision.
|
Override - Parcel Holds | | | 4/17/2003 | | |
|
|
|
|
Print permit w/o conditions | | | 4/17/2003 | | |
|
|
|
|
Routing - FIRE | 4/17/2003 | | 4/17/2003 | | PASS |
Bill Alexander
|
|
|
"Non Build Aggreement" attached, must be cleared upon FD verification of required hydrants and acceptable vehicle access roadways in place. Personnally visited site 04/18/03 and it appears to be finished.
|
Routing - PLAN CHECK | 3/26/2003 | | 4/17/2003 | | FAIL |
|
|
|
Second review completed, sent correction report to designer requesting additional information be resubmitted for further review prior to issuing parmit.
|
Plan resubmittals received | | | 4/10/2003 | | DONE |
|
|
|
Received foru copies of revised sheets C, A0, 1,of 1, 1 of 3, 2 of 3, 3 of 3, A1.1, A2.0, A2.1, A3.0, A4.0, A5.0, A5.1, A6.0, A7.0, A7.1, A7.2, A8.0, A10.0, E2.0, M1.0, P1.0, P1.1, P2.0, NRG. Five copies of additional calcs. Put two copies of resubmittals and calcs with plans, one copy to outside engineering and one copy for energy review routed to Mike with his two copies. kmm
|
Plan Review Completed(1st rev) | | | 3/26/2003 | | DONE |
|
|
|
|
Routing - FIRE | 3/25/2003 | | 3/26/2003 | | FAIL |
Bill Alexander
|
|
|
Requires a full IBC review prior to acceptance. Need Fire Flows.
|
Routing Off Site - STRUCTURAL | 3/13/2003 | | 3/26/2003 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside eng. kmm
Additional information required for further review.
|
Routing - PLAN CHECK | | | 3/25/2003 | | FAIL |
|
|
|
Sent submittal letter to designer requesting plans be resubmitted and detailed to reflect the 2000 IBC requirements.
|
Routing Off Site -Energy | 3/20/2003 | | 3/21/2003 | | FAIL |
|
|
|
Contacted Ron O. for outside energy review. kmm
|
Routing - Erosion and Sediment | | | 3/19/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PLUMBING | 3/19/2003 | | 3/19/2003 | | PASS |
Lee Rice
|
|
|
see review attachment
|
Routing - PUBLIC WORKS | 3/12/2003 | | 3/19/2003 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/12/2003 | | |
|
|
|
|
Routing - PLANNING Land Div | 3/12/2003 | | 3/12/2003 | | FAIL |
|
|
|
Do not issue building permit until Kane Square Subdivision is recorded.
|
Plans ACCEPTED BY PLAN TECH | | | 3/11/2003 | | DONE |
|
|
|
|
Application received | | | 3/7/2003 | | |
|
|
|
|
Routing - PLANNING | | | | | PASS |
|
|
|
Approved per CUP02-28; Must meet required setbacks. 2 barbeque facilities and 2 picnic tables are to be installed in the open space before occupancy is approved.
|