BLD-Conference | 1/12/2004 | 1/13/2004 | 1/13/2004 | A | DONE |
Tony Young
|
|
|
|
First Notice | | 1/12/2004 | 1/12/2004 | | DONE |
|
|
|
|
Permanent Occupancy | | 1/12/2004 | 1/12/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/12/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 9928 issued 1-12-04 to the Red Flag Medical Clinic.
|
PubWorks Occupancy Approval | 12/8/2003 | 12/8/2003 | 12/8/2003 | | DONE |
|
|
|
Drainage project complete, OK to sign permanent occupancy to C.Weisshaupt 12/08/03. R.Rokovitz
|
BLD-Final | 11/18/2003 | 11/18/2003 | 11/18/2003 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Kim Olson
ok for temp. only untill trades are signed off and signage etc. 11/18/2003 3:24:42 PM
|
Temporary occupancy | | | 11/18/2003 | | DONE |
|
|
|
Temp. Occ. Cert. # 5023 issued 11-18-03 to the Red Flag Medical Clinic.
|
BLD-Final | 11/14/2003 | 11/17/2003 | 11/17/2003 | A | CANC |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Kim Olson
|
BLD-Final | 11/13/2003 | 11/14/2003 | 11/14/2003 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Kim Olson
|
FIRE-Final Inspection | 11/13/2003 | 11/14/2003 | 11/14/2003 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled 11/14/2003 9:58:41 AM
|
BLD-Final | 11/13/2003 | 11/14/2003 | 11/13/2003 | A | CANC |
Tony Young
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Inspection cancelled from web by: Kim Olson
|
BLD-Final | 11/12/2003 | 11/13/2003 | 11/13/2003 | A | NR |
Jim Storey
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
FIRE-Final Inspection | 11/12/2003 | 11/13/2003 | 11/13/2003 | A | FAIL |
Troy Cobbley
|
|
|
Mike; Phone #: ###-#### Provide approved plan notes for inspection, tag fire extinguishers, repair the exit signs, test duct smoke detectors 11/13/2003 9:54:16 AM
|
Inspection Record Card- Bld | | | 11/4/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/4/2003 | | DONE |
|
|
|
|
BLD-Wall cover | 9/23/2003 | 9/24/2003 | 9/24/2003 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Kim Olson
|
BLD-Framing/Rough-in | 9/15/2003 | 9/16/2003 | 9/16/2003 | A | PART |
Steven Webb
|
|
|
Phone #: ###-#### Internet Inspection Request from: Kim Olson C/N posted--ok to insulate. 9/16/2003 10:58:52 AM
|
BLD-Foundation | 7/11/2003 | 7/11/2003 | 7/11/2003 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Kim Olson
|
BLD-Footing | 7/10/2003 | 7/10/2003 | 7/10/2003 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/10/2003 at 9:31:48 AM. Contact: ###-####.
|
(F) Reprint permit | | | 6/30/2003 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/27/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/28/2003 | | DONE |
|
|
|
|
Telephone call | | | 5/28/2003 | | DONE |
|
|
|
permit ready and need ACHD
|
Routing Off Site - STRUCTURAL | 5/19/2003 | | 5/27/2003 | | PASS |
|
|
|
Contacted PDQ to take revised plans of 5/16/03 to outside engineering. kmm
|
Plan resubmittals received | | | 5/27/2003 | | DONE |
|
|
|
Received one copy of revised sheets 2,4&5. Routed to Mike O. kmm
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2003 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 3/7/2003 | | 5/27/2003 | | PASS |
Mike Otto
|
|
|
5/27/2003 14:15:20 MLO - activity updated through activity BLDA022 from case BLD03-00442.
|
Routing - FIRE | 5/6/2003 | | 5/16/2003 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 5/16/2003 | | DONE |
|
|
|
Received three copies of revised sheets 2,4, 5 and two sets of addendum #2 calculations. Routed to Mike O. kmm
|
Routing Off Site - STRUCTURAL | 5/8/2003 | | 5/8/2003 | | FAIL |
|
|
|
corrections incomplete architect notified. MLO
|
Plan resubmittals requested | | | 5/8/2003 | | DONE |
|
|
|
need design and calcs for girder saddle
|
Routing Off Site - STRUCTURAL | 4/28/2003 | | 5/6/2003 | | FAIL |
|
|
|
Resubmittals sent to outside engineer. corrections faxed and mailed to architect
|
Plan resubmittals requested | | | 5/6/2003 | | DONE |
|
|
|
structural corrections
|
Plan resubmittals received | | | 5/6/2003 | | DONE |
|
|
|
received three sets of sheets 1,2, 3, 5, and a extra copy of sheet 1 and taken to Mike Otto.
|
Plan resubmittals received | | | 4/24/2003 | | DONE |
|
|
|
Received United Water letter for available flow. Routed to fire and put one in file. kmm
|
Routing - FIRE | 4/17/2003 | | 4/23/2003 | | FAIL |
|
|
|
proposed new hydrant location is acceptable. Still need to submit hydrant flow info from UW.
|
Plan resubmittals received | | | 4/22/2003 | | DONE |
|
|
|
received a transmittal letter form Rodney Baldwin and two prints of GD-1
|
Plan resubmittals received | | | 4/18/2003 | | DONE |
|
|
|
Received one copy of each page 1 2 3 4 5
|
Plan resubmittals received | | | 4/18/2003 | | DONE |
|
|
|
Received 1 set of resubmittal sheets 1, 2, 3, 4 and 5 and forwarded to Mike O.
|
Routing - PLAN CHECK | 4/17/2003 | | 4/17/2003 | | PASS |
|
|
|
|
Routing Off Site -Energy | 4/17/2003 | | 4/17/2003 | | PASS |
|
|
|
corrections completed
|
Plan resubmittals received | | | 4/16/2003 | | DONE |
|
|
|
received two sets of pages 1, 2, 4 4/17/2003 resubs short set for structural review. Architect contacted.
|
Plan resubmittals received | | | 4/15/2003 | | DONE |
|
|
|
Received two copies of revised sheets E, 3, 5, addendum calculations and product specification commercial thermostat. Routed to Mike O.
|
Routing - FIRE | 3/28/2003 | | 4/3/2003 | | FAIL |
|
|
|
Review comments faxed to architect.
|
Routing Off Site - STRUCTURAL | 3/7/2003 | | 3/28/2003 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside eng. kmm Corrections mailed to architect
|
Routing - PLAN CHECK | 3/19/2003 | | 3/28/2003 | | FAIL |
|
|
|
corrections faxed and mailed to architect
|
Plan resubmittals requested | | | 3/28/2003 | | DONE |
|
|
|
IBC and IEEC corrections
|
Routing - PLUMBING | 3/13/2003 | | 3/19/2003 | | PASS |
|
|
|
add a waste connection in the dark room, additional cross connection protection may be required, verify thermol expantion sizing.
|
Routing Off Site -Energy | 3/7/2003 | | 3/17/2003 | | FAIL |
|
|
|
plans sent to Eric Makela for review. Corrections faxed to applicant by Makela on 3-17-2003.
|
Routing - Erosion and Sediment | 3/12/2003 | | 3/13/2003 | | PASS |
|
|
|
ESC approved with attached conditions.
|
Routing - PLANNING | 3/13/2003 | | 3/13/2003 | | PASS |
|
|
|
Approved per DRH02-00220.
|
Routing - PUBLIC WORKS | 3/7/2003 | | 3/12/2003 | | PASS |
|
|
|
|
Application received | | | 3/7/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/7/2003 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/7/2003 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/7/2003 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 3/7/2003 | | 3/7/2003 | | PASS |
|
|
|
Approved as per ROS 3700. Allowed one time lot split of Lot 11 of Berridge Subdivision.
|
Fee Review-notes | 3/7/2003 | 3/7/2003 | | | |
|
|
|
|