Case Summary (BLD) | | | 12/6/2004 | | |
|
|
|
|
BLD-Final | 5/30/2003 | 6/2/2003 | 6/2/2003 | A | DONE |
Tom Arcoraci
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
First Notice | | 6/2/2003 | 6/2/2003 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 6/2/2003 | | DONE |
|
|
|
Perm. Occ. cert. #9670 issued 6-2-03 to Chico's.
|
BLD-Conference | 5/30/2003 | 5/30/2003 | 5/30/2003 | P | PASS |
Carl Dependahl
|
|
|
RA grills back-ordered...ok 5/30/2003 4:44:36 PM
|
BLD-Final | 5/30/2003 | 5/30/2003 | 5/30/2003 | P | PASS |
Carl Dependahl
|
|
|
ok for c/o fees owing okay per Linda
|
Permanent Occupancy | | 5/30/2003 | 5/30/2003 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/29/2003 | 5/30/2003 | 5/30/2003 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled. The contractor said that he had an agreement with Carl about the thumbturn on the front door. I notified Carl Dependahl 5/30/2003 3:37:59 PM
|
BLD-Framing/Rough-in | 5/28/2003 | 5/28/2003 | 5/28/2003 | P | PART |
Carl Dependahl
|
|
|
joe ceiling grid; Phone #: ###-#### Internet Inspection Request from: Barbara Moore...grid at storeroom ok... 5/28/2003 1:59:22 PM
|
BLD-Conference | 5/21/2003 | 5/21/2003 | 5/21/2003 | P | FAIL |
Carl Dependahl
|
|
|
###-####, c/n...need min 4" step or ramp 5/21/2003 4:04:13 PM
|
BLD-Framing/Rough-in | 5/13/2003 | 5/13/2003 | 5/13/2003 | P | PART |
Carl Dependahl
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Barbara Moore...walls patched &penetrations ok, lid ok pend elec. & hvac 5/13/2003 4:19:45 PM
|
BLD-Framing/Rough-in | 5/9/2003 | 5/9/2003 | 5/9/2003 | P | PART |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore; need patch demising wall, add blocking at restroom walls, etc. storefront not in yet. need IECC for elec, & hvac. 5/9/2003 11:57:49 AM 5/9/2003 4:53:02 PM
|
Inspection Record Card- Bld | | | 5/7/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/7/2003 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/7/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2003 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 3/12/2003 | | 5/6/2003 | | PASS |
Carl Westfall
|
|
|
5/6/2003 11:03:26 CJW - activity updated through activity BLDA022 from case BLD03-00467.
|
Routing - PLAN CHECK | 4/24/2003 | | 5/6/2003 | | PASS |
|
|
|
Drawings approved after 2nd resubmittal review.
|
Plan resubmittals received | | | 5/5/2003 | | DONE |
|
|
|
Received three copies of revised sheets C-1, C-2, A-1, A-2, A-4. Routed to Carl W. kmm
|
Telephone call | | | 5/1/2003 | | DONE |
|
|
|
Called David Levy, Architect, and discussed the review of his resubmittal. He was e-mailed a list of 4 items that still need to be addressed.
|
Plan resubmittals received | | | 4/30/2003 | | DONE |
|
|
|
received transmittal letter, letter from Steve Szumlanski of Chico's, copy of a fax cover sheet from Britt Makela Group, Plan Review report. Three sets of cover sheets, C2, A1, A1.1, A1.1a, A2, A2.1, A2.1a, A4, A4a, A4.1, A5, A5a, M2, E2, E3, E4, E5, EN1, EN2, S1,.
|
Routing - Erosion and Sediment | 4/22/2003 | | 4/23/2003 | | DONE |
|
|
|
If any comments please call Rita at ###-####---ESC waiver for plan approved with attached conditions. ESC permit is required. RP required to be in charge.
|
Plan Review Completed(1st rev) | | | 4/22/2003 | | DONE |
|
|
|
|
Routing - FIRE | 4/16/2003 | | 4/22/2003 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 3/18/2003 | | 4/16/2003 | | |
|
|
|
Failed first UBC review. UBC plan review started April 11, 2003 and finished April 16, 2003. A response was required from the architect. See the plan review report.
|
Received Certificate of Value | | | 3/26/2003 | | DONE |
|
|
|
Received demo cert. of value. put with plans, file and Carl W. kmm
|
Received Certificate of Value | | | 3/26/2003 | | DONE |
|
|
|
Received revised cert. of value to reflect demo permit. put with plans and file. kmm
|
Routing - PLANNING | 3/17/2003 | | 3/18/2003 | | PASS |
|
|
|
Approved per DRH03-00025.
|
Routing - PUBLIC WORKS | 3/13/2003 | | 3/17/2003 | | PASS |
|
|
|
|
Application received | | | 3/10/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/10/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/10/2003 | | DONE |
|
|
|
Received three sets of plans, will have to ask for a fourth set if outside eng. is requested.
|
Fee Review-notes | 3/10/2003 | 3/10/2003 | | | |
|
|
|
|
Routing Off Site -Energy | 3/13/2003 | | | | |
|
|
|
Contacted Eric M for energy review. kmm
|