Case Summary (BLD) | | | 9/3/2014 | | DONE |
|
|
|
|
Permanent Occupancy | | 9/10/2003 | 9/10/2003 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/9/2003 | 9/10/2003 | 9/10/2003 | A | PASS |
Rick Jackson
|
|
|
DENNIS; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Other | 9/9/2003 | 9/10/2003 | 9/10/2003 | A | PASS |
Jim Sly
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Darla Downs OK for Perm Occ. :) 9/10/2003 9:07:01 AM
|
First Notice | | 9/10/2003 | 9/10/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/10/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9795 issued 9-10-03 to the Sonic Drive-In.
|
FIRE-Final Inspection | 9/8/2003 | 9/9/2003 | 9/9/2003 | A | FAIL |
Troy Cobbley
|
|
|
The incorrect remote alarm/trouble indicators have been installed 9/9/2003 3:32:11 PM
|
BLD-Final | 9/8/2003 | 9/9/2003 | 9/9/2003 | P | NR |
Jim Sly
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Annette Moore 9/9/2003 2:00:12 PM
|
FIRE-Final Inspection | 9/8/2003 | 9/8/2003 | 9/8/2003 | P | NR |
Troy Cobbley
|
|
|
per the general contractor the remote leds for the duct smoke detectors did not arrive 9/8/2003 3:47:01 PM
|
FIRE-Final Inspection | 9/2/2003 | 9/3/2003 | 9/3/2003 | A | FAIL |
Troy Cobbley
|
|
|
The remote alarm/trouble leds that were to be provided do not annunciate a trouble condition. I spoke with the electrical contractor about the correct model to use. 9/3/2003 1:12:07 PM
|
FIRE-Final Inspection | 8/28/2003 | 8/29/2003 | 8/29/2003 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Millers permission until the remote alarm/trouble indicators get installed. The air balance report is OK 8/29/2003 11:39:01 AM
|
BLD-Final | 8/28/2003 | 8/29/2003 | 8/29/2003 | P | PART |
Jim Sly
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Barbara Moore OK for Temp Occ. C/N Need all req signatures within 90 days of this notice. :) 8/29/2003 5:08:23 PM
|
FIRE-Final Inspection | 8/27/2003 | 8/28/2003 | 8/28/2003 | A | FAIL |
Troy Cobbley
|
|
|
###-#### dennis Provide air balance report for hoods, remove thumbturns from restroom doors, test duct smoke detectors and repair exit signs 8/28/2003 11:09:54 AM
|
PubWorks Occupancy Approval | 8/28/2003 | 8/28/2003 | 8/28/2003 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 8/28/03. R.Rokovitz
|
BLD-Energy code compliance | 8/5/2003 | 8/6/2003 | 8/6/2003 | A | PASS |
Jim Sly
|
|
|
danny ###-####
|
BLD-Other | 7/23/2003 | 7/23/2003 | 7/23/2003 | P | PASS |
Jim Sly
|
|
|
###-#### danny sheeting inspection OK to cover Ext. 7/23/2003 4:18:25 PM
|
BLD-Framing/Rough-in | 7/23/2003 | 7/23/2003 | 7/23/2003 | P | NR |
Jim Sly
|
|
|
###-#### danny Need HVAC and Plumb R/I's 7/23/2003 4:18:57 PM
|
BLD-Footing | 6/17/2003 | 6/18/2003 | 6/18/2003 | A | FAIL |
Jim Sly
|
|
|
lazaro; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Special insp Req. (3000 psi) Or need stamped letter from Eng of record changing psi to 2500........ 6/18/2003 12:29:05 PM
|
BLD-Footing | 6/18/2003 | 6/18/2003 | 6/18/2003 | P | NR |
Jim Sly
|
|
|
lazara; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
(F) Reprint permit | | | 6/6/2003 | | |
|
|
|
|
Routing - PLANNING | 6/5/2003 | | 6/5/2003 | | PASS |
|
|
|
Approved per civil drawings date 6/4/03 and landscape plan in the design review file (DRH03-56) dated May 21, 2003 except as modified by the fax dated 6/4/03 from BRS. A copy of the fax and approval letter are attached to the building permit documents. The appropriate landscape plan is in the DR file. No landscape plan was submitted for the building permit plans. The drawings have been passed back to Karen Gallagher for her approval.
|
Routing - PLANNING | 6/5/2003 | | 6/5/2003 | | PASS |
|
|
|
Gutter panel to extend below Light Fixture in canopy. Light Fixture type per fax attached to Sheet CA1. Only one light pole on site at cross access driveway near Ustick Road per Bill Strite. Passed on these items, plans have been passed. 6-5-03 kg
|
Routing - PLAN CHECK | 6/5/2003 | | 6/5/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2003 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/5/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/5/2003 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/5/2003 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 3/12/2003 | | 6/5/2003 | | PASS |
John Menard
|
|
|
6/5/2003 15:30:07 JCM - activity updated through activity BLDA022 from case BLD03-00475.
|
Routing - PLANNING | 5/30/2003 | | 6/4/2003 | | PEND |
|
|
|
Sarah S. to review for DRH compliance. KG still needs revised sheet CA1 detail 7 regarding lighting.
DR is waiting for an updated landscape plan. Currently there is not a landscape plan in the building set. The applicant still needs to show the reconfigured swale at the northeast corner of the site. The civil drawings in the building permit set have been marked to reflect that that sidewalk along the north property line is to be deleted per CUP02-130 and DRH03-56. Skip (###-####) has been notified of these requirements.
|
Routing Off Site -Energy | 5/28/2003 | | 6/3/2003 | | PASS |
|
|
|
Contacted Eric M for energy review of resubmitted plans of 5/21/03. kmm Received fax from consulting energy reviewer approving the resubmitted energy information. JCM
|
Plan resubmittals received | | | 6/2/2003 | | DONE |
|
|
|
Received four copies of energy compliance sheets EC1 & EC2. Routed to John M. kmm
|
Routing - FIRE | 5/28/2003 | | 5/30/2003 | | PASS |
Bill Alexander
|
|
|
|
Telephone call | | | 5/28/2003 | | DONE |
|
|
|
Contacted Don Dishon at ###-#### requesting energy compliance to be incorporated in to the plans. Have asked for three copies. kmm
|
Plan Reviewer's activity | | | 5/28/2003 | | PASS |
|
|
|
Reviewed and approved resubmittals with attached comment list and redlined notes. JCM
|
Routing - PLAN CHECK | 5/8/2003 | | 5/28/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/22/2003 | | DONE |
|
|
|
received two copies of response comments for energy code review, along wtih three sets of A6, P1, P2, K2, and taken to John M.
|
Routing - PUBLIC WORKS | 4/30/2003 | | 5/7/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 4/30/2003 | | DONE |
|
|
|
received two sets of C1.0, C1.1, C1.2, C1.3, C1.4 and taken to John M.
|
Plan Review Completed(1st rev) | | | 4/8/2003 | | DONE |
|
|
|
|
Routing - FIRE | 4/2/2003 | | 4/8/2003 | | FAIL |
Bill Alexander
|
|
|
Need hydrant and fire flows IFC 508
|
Plan resubmittals requested | | | 4/2/2003 | | |
|
|
|
Mailed the applicant, Skip Hofferber, a copy of the plan review comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 3/26/2003 | | 4/2/2003 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/13/2003 | | 3/28/2003 | | PASS |
|
|
|
contacted PDQ to take plans to outside eng. kmm Received a fax from the consulting structural engineer approving the structural portion of this project. JCM
|
Routing - PLUMBING | 3/26/2003 | | 3/26/2003 | | PASS |
|
|
|
use boise city approved grease interceptor detail, attached, C1.0 shows a 1'' water service, increase to 1 1/4'' per plumbing plans, all vents must be 10' away from fresh air intake, additional cross connection protection may be required, thermol expantion protection required.
|
Routing - PLANNING | 3/21/2003 | | 3/25/2003 | | FAIL |
|
|
|
Handful of conditions from CUP not met. Sent fax to Danny Goodman and paged Skip.
|
Routing - Erosion and Sediment | 3/20/2003 | | 3/21/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 3/13/2003 | | 3/20/2003 | | FAIL |
|
|
|
Requires drainage plan revision per Brian Murphy.
|
Routing - PLANNING Land Div | 3/19/2003 | | 3/19/2003 | | PASS |
|
|
|
Parcel was first land split of pre-1965 parcel.
|
Routing Off Site -Energy | 3/12/2003 | | 3/19/2003 | | FAIL |
|
|
|
Contacted Eric M for energy review. kmm
|
Plans ACCEPTED BY PLAN TECH | | | 3/13/2003 | | DONE |
|
|
|
Calcs., received
|
Routing - PLANNING Land Div | 3/12/2003 | | 3/12/2003 | | FAIL |
|
|
|
Need pre-1965 deed to verify legal parcel. Called Clinton Yaka of Bill Strite on 3/12/03.
|
Plans ACCEPTED BY PLAN TECH | | | 3/12/2003 | | PEND |
|
|
|
Waiting for struct. calcs. kmm
|
Plan routing begun/NEW & ADDTN | | | 3/12/2003 | | DONE |
|
|
|
|
Application received | | | 3/11/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/11/2003 | | DONE |
|
|
|
|
Fee Review-notes | 3/11/2003 | 3/11/2003 | | | |
|
|
|
|