(ALLIANCE TITLE) Remodel for a new 7,980 sq.ft. office tenant that will occupy the entire building per approved plans on file. Work to include new interior walls, new interior doors and sidelights, new suspended ceiling, new draft stops, interior finish, sinks, counters/cabinets, mechanical work, plumbing work, and electrical work. Entrance vestibule, restrooms, and mechanical room exist from previous permits. All other areas will be new and were previously demolished under BLD03-00368, an interior demo permit. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is NOT fire sprinklered. (PC#0163-03) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD7/7/20067/7/20067/7/2006 DONE
First Notice has not been responded to.
First Notice6/5/20066/5/20067/7/2006 DONE
DetailsMike Jordan
BLD-Aging Inspection6/5/20066/5/20066/5/2006 DONE
DetailsMike Jordan
job has been finaled.
DOC - Permit Finaled6/5/20066/5/20066/5/2006PPASS
DetailsMike Jordan
BLD-Aging Inspection4/3/20064/3/20064/3/2006 CANC
DetailsMike Jordan
DOC - Permit Finaled4/3/20064/3/20064/3/2006ADONE
DetailsMike Jordan
BLD-Final6/9/20036/10/20036/10/2003APASS
DetailsJim Sly
phil; Phone #: ###-#### Internet Inspection Request from: Barbara Moore OK for Perm Occ. 6/10/2003 11:59:43 AM
BLD-Final5/27/20035/28/20035/28/2003APART
DetailsRuss Owen
gil; Phone #: ###-#### Internet Inspection Request from: Annette Moore. Ok temp oc pending ele perm and c/n for lever hardware at breakroom sink,pull out ele boxes for reach ranges and have water cooler on site. 5/28/2003 12:52:13 PM
FIRE-Final Inspection5/27/20035/27/20035/27/2003PPASS
DetailsTroy Cobbley
gil; Phone #: ###-#### Life safety finaled 5/27/2003 3:05:24 PM
FIRE-Final Inspection5/22/20035/23/20035/23/2003AFAIL
DetailsTroy Cobbley
gil; Phone #: ###-#### Duct detectors did not shut down the hvac units and the remote alarm led's did not operate 5/23/2003 9:46:50 AM
BLD-Final5/22/20035/23/20035/23/2003PCANC
DetailsRuss Owen
gil; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in5/8/20035/9/20035/9/2003APASS
DetailsRuss Owen
gil celing grid ; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Conference4/30/20035/1/20035/1/2003APART
DetailsRuss Owen
GIL; Phone #: ###-#### Internet Inspection Request from: Darla Downs. Went over accessibility issues . 5/1/2003 3:13:34 PM
BLD-Framing/Rough-in4/22/20034/23/20034/23/2003AFAIL
DetailsRuss Owen
gil; Phone #: ###-#### Internet Inspection Request from: Darla Downs. needs ele insp and mec also lower support at draft stop. c/n. 4/23/2003 12:06:00 PM
Routing - PLAN CHECK4/18/2003 4/21/2003 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  4/21/2003 PASS
Inspection Record Card- Bld  4/21/2003  
Print Occupancy Form  4/21/2003  
Telephone call  4/21/2003 DONE
LEFT MESS FOR BOB ROSS THAT PERMIT IS READY
Issue PAID IN FULL permit  4/21/2003 DONE
Plan assigned to (JCB)4/3/2003 4/21/2003 PASS
DetailsJason Blais
4/21/2003 14:08:44 JCB - activity updated through activity BLDA022 from case BLD03-00673.
Routing - FIRE4/14/2003 4/18/2003 PASS
Plan resubmittals received  4/16/2003 DONE
Received 3 sets of A-1 and A-2 and a letter of Transmittal along with a momo from BRS.rounted to Jason
Plan resubmittals requested  4/14/2003  
Plan resubmittals and written response required for further review.
Routing - PLAN CHECK4/7/2003 4/14/2003 FAIL
Plan review report sent and faxed to architect and contractor on 4/11/03. Plan resubmittals and written response required for further review. Plans routed to Fire Dept. for review.
Routing - PUBLIC WORKS4/3/2003 4/7/2003 PASS
Plans ACCEPTED BY PLAN TECH  4/1/2003 DONE
Application received  3/31/2003  
Recd Pcfee & Taken To Pln CK  3/31/2003 DONE
Fee Review-notes3/31/20033/31/2003