BLD-Final | 11/20/2003 | 11/21/2003 | 11/21/2003 | P | PASS |
Jim Storey
|
|
|
Steve; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes l/c isued on site. 11/21/2003 1:56:56 PM
|
DOC - Permit Finaled | 11/21/2003 | 11/21/2003 | 11/21/2003 | P | PASS |
Jim Storey
|
|
|
Finaled by inspector at 11/21/2003 1:56:58 PM
|
BLD-Aging Inspection | 9/22/2003 | 9/22/2003 | 9/22/2003 | | NR |
Jim Storey
|
|
|
wip. 9/22/2003 8:34:39 AM
|
BLD-Aging Inspection | 7/21/2003 | 7/21/2003 | 7/21/2003 | | PASS |
Jim Storey
|
|
|
waiting for coridor wall protection at trench line. wip 7/21/2003 8:30:38 AM
|
BLD-Footing | 5/15/2003 | 5/19/2003 | 5/19/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/15/2003 at 1:04:45 PM. Contact: ###-####. red iron in place appears to be per plan pending special insp reports. 5/19/2003 8:58:57 AM
|
BLD-Footing | 5/16/2003 | 5/19/2003 | 5/19/2003 | A | PART |
Jim Storey
|
|
|
|
BLD-Footing | 5/15/2003 | 5/16/2003 | 5/16/2003 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/15/2003 at 1:04:03 PM. Contact: ###-####. out of time. 5/16/2003 4:55:15 PM
|
BLD-Footing | 5/8/2003 | 5/9/2003 | 5/9/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/8/2003 at 4:34:05 PM. Contact: ###-####.
|
BLD-Footing | 5/1/2003 | 5/6/2003 | 5/6/2003 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/1/2003 at 11:54:01 AM. Contact: ###-####.
|
BLD-Footing | 5/1/2003 | 5/5/2003 | 5/5/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/1/2003 at 11:53:11 AM. Contact: ###-####. wip covered with special insp. 5/5/2003 8:32:21 AM
|
BLD-Footing | 5/1/2003 | 5/2/2003 | 5/2/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/1/2003 at 11:52:22 AM. Contact: ###-####.wall ok. 5/2/2003 9:46:40 AM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2003 | | PASS |
|
|
|
|
Telephone call | | | 4/29/2003 | | DONE |
|
|
|
emailed permit ready
|
Inspection Record Card- Bld | | | 4/29/2003 | | DONE |
|
|
|
|
Issue & PRINT to be Invoiced | | | 4/29/2003 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 4/2/2003 | | 4/29/2003 | | PASS |
John Menard
|
|
|
4/29/2003 14:18:04 JCM - activity updated through activity BLDA022 from case BLD03-00682.
|
Routing - PLAN CHECK | 4/7/2003 | | 4/29/2003 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/21/2003 | | 4/29/2003 | | PASS |
|
|
|
Sent resubmittal to outside engineer. Spoke with consulting engineer and was advised that the resubmittals had been approved as submitted and a letter would follow. JCM
|
Additional plans submitted | | | 4/25/2003 | | DONE |
|
|
|
Letter of transmittal received three sets of L2.0.1, A2.2.1,A2.3.1, A5.0, M4.3.1 and taken to John M.
|
Plan resubmittals received | | | 4/18/2003 | | DONE |
|
|
|
3 sets of resubmittal sheets S3.0 along with cover letter received and forwarded to John M.
|
Plan resubmittals requested | | | 4/16/2003 | | |
|
|
|
Faxed Paul Marcolina a copy of the review comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 4/2/2003 | | 4/16/2003 | | FAIL |
|
|
|
contacted pdq for outside engineering. kmm Received a comment list from the consulting structural engineer requesting revisions. JCM
|
Plan Reviewer's activity | | | 4/11/2003 | | PASS |
|
|
|
Plans approved as submitted for the structural frame phase of this project. JCM
|
Plans ACCEPTED BY PLAN TECH | | | 4/8/2003 | | DONE |
|
|
|
Waiver letter received routed one copy to John M one to Jim R and one in file. kmm
|
Routing - PLANNING | 4/7/2003 | | 4/7/2003 | | PASS |
|
|
|
Approve per CZC03-36
|
Routing - Erosion and Sediment | 4/4/2003 | | 4/4/2003 | | PASS |
|
|
|
Per Jim Rogers no charge for ESC waiver letter. Micron work is under a General NPDES permit issued by EPA. All work on site must have BMP's as required by the General NPDES permit and Boise City attached to plans. An ESC permit is required by Boise City.
|
Routing - PUBLIC WORKS | 4/2/2003 | | 4/4/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/2/2003 | | DONE |
|
|
|
Waiting for waiver letter.
No outside energy review. kmm
|
Routing - PLANNING Land Div | 4/2/2003 | | 4/2/2003 | | PASS |
|
|
|
Approved, site is over 5 acres in size.
|
Plan routing begun/NEW & ADDTN | | | 4/2/2003 | | DONE |
|
|
|
|
Application received | | | 4/1/2003 | | |
|
|
|
|
Fee Review-notes | 4/1/2003 | 4/1/2003 | | | |
|
|
|
additional value from elect. permit so gave an additional 202,757.00 value
|