BLD-Final | 9/15/2003 | 9/16/2003 | 9/16/2003 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/15/2003 at 7:27:42 PM. Contact: ###-####.
|
DOC - Permit Finaled | 9/16/2003 | 9/16/2003 | 9/16/2003 | A | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 9/16/2003 9:35:17 AM
|
BLD-Energy code compliance | 5/6/2003 | 5/6/2003 | 5/6/2003 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/6/2003 at 9:09:11 AM. Contact: ###-####. ok to cover 5/6/2003 4:16:00 PM
|
BLD-Framing/Rough-in | 5/2/2003 | 5/5/2003 | 5/5/2003 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/2/2003 at 1:09:27 PM. Contact: ###-####. wrong insulation 5/5/2003 10:26:40 AM
|
CHANGE STATUS TO (ISS) | | | 4/29/2003 | | DONE |
|
|
|
ALREADY ISSUED
|
BLD-Framing/Rough-in | 4/25/2003 | 4/28/2003 | 4/28/2003 | A | FAIL |
Dave Hannah
|
|
|
MARV ###-#### needs elec r/i ok to insulate aftyer elec r/i 4/28/2003 10:57:25 AM
|
BLD-Grading Inspection | 4/15/2003 | 4/15/2003 | 4/15/2003 | | DONE |
Rita DeYoung
|
|
|
Geotechnical engineer has approved the pier subgrade. However, the northernmost hole must have 3 to 4 inches of loose sand removed prior to placement of the concrete.
|
BLD-Footing | 4/15/2003 | 4/15/2003 | 4/15/2003 | P | PASS |
Dave Hannah
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 4/9/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/8/2003 | | DONE |
|
|
|
|
Telephone Call | | | 4/8/2003 | | |
|
|
|
|
Routing - Erosion and Sediment | 4/7/2003 | | 4/7/2003 | | PASS |
|
|
|
ESC waiver approved with conditions attached to plans.
|
Print Pending Permit.LaserJet4 | | | 4/7/2003 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2003 | | DONE |
|
|
|
|
Application received | | | 4/2/2003 | | |
|
|
|
|