Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD03-00691
StatusExpired
Name CORNEL LARSON
Site Address 8740 W FAIRVIEW AVE
Project NameFairview Tech Center
Customer Number 
ePlanReviewNo
Description
Fairview Tech Center * Parking Lot * To excavate, grade, pave a parking lot and revise existing parking lot to accommodate existing building remodel, per engineered plans on file as approved by the Public Works department. Install curbing, striping as noted on the plans. No buildings to be demolished, installed or constructed under this permit. CUP02-00148, CAR02-00062, ESC03-00244 PC#165-03
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval1/19/20051/19/20051/19/2005 DONE
No final inspection, drive-by shows complete 1/19/05 R.Rokovitz
DOC - Permit Expired5/11/20045/11/20045/11/2004APASS
DetailsJim Sly
Expired by inspector at 5/11/2004 9:08:50 AM
BLD-Aging Inspection5/10/20045/10/20045/10/2004 DONE
DetailsJim Sly
EXP. 5/11/2004 9:08:34 AM
Telephone call  6/5/2003 DONE
LEFT MESS THAT PERMIT IS READY
Inspection Record Card- Bld  6/5/2003 DONE
Issue PAID IN FULL permit  6/5/2003 DONE
Print Pending Permit.LaserJet4  6/4/2003 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/4/2003 DONE
Plan assigned to (KMM)4/23/2003 6/4/2003 PASS
DetailsKathy Miller
6/4/2003 13:19:25 KMM - activity updated through activity BLDA022 from case BLD03-00691.
Routing - PLANNING5/23/2003 6/4/2003 PASS
Passed for compliance with CUP02-148 (KLG).
Passed for compliance with DRH02-251 (MGS).
Routing - PLAN CHECK6/4/2003 6/4/2003 DONE
Plan resubmittals received  5/29/2003 DONE
transmittal letter, 4 copies of SP-1 put two copies with grading plan kmm
Routing - PUBLIC WORKS5/22/2003 5/23/2003 PASS
DetailsBrandi Dominguez
Routing - PLANNING Land Div5/21/2003 5/21/2003 PASS
Recorded new deed on May 7, 2003.
Routing - PLAN CHECK5/20/2003 5/21/2003  
Plans in hold box. kmm
Routing - PUBLIC WORKS5/19/2003 5/20/2003 FAIL
Requires Drainage plan Review per Brian M. kmm
Routing - PLAN CHECK4/23/2003 5/19/2003  
Plans in hold box. kmm
Routing - FIRE4/23/2003 4/23/2003 PASS
plans approved per telcon discussion with architect clarifying all items on the previous review.
Routing - PLAN CHECK4/23/2003 4/23/2003  
Plans in hold box. kmm
Routing - FIRE4/16/2003 4/22/2003 FAIL
Insufficient information to confirm FD access. Review comments faxed to Larson Architects for response.
Routing - PLANNING4/9/2003 4/14/2003 FAIL
Karen Gallagher failed plans as 3 conditions of CUP02-148 have not been meet. Modifications needed to parking lot dimensions for southern row of parking. Need access easement. Need parcels combined. 4-14-03. Design Review (M. Santoyo) will review upon conditional use issues being met.
Routing - PLANNING Land Div4/14/2003 4/14/2003 FAIL
Fail. Need to record deed with new metes and bounds descriptionn that consolidates parcels as per ROS 2404. Need to obtain new tax parcel # after parcels are consolidated.
Routing - Erosion and Sediment4/8/2003 4/9/2003 PASS
ESC03-00244 issued on 3/13/03
Routing - PUBLIC WORKS4/2/2003 4/7/2003 FAIL
Requires drainage plans review.
Application received  4/2/2003  
Plans ACCEPTED BY PLAN TECH  4/2/2003 DONE
Plan routing begun/NEW & ADDTN  4/2/2003 DONE
Parking lot