PubWorks Occupancy Approval | 4/6/2004 | 4/6/2004 | 4/6/2004 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 4/06/04. R.Rokovitz
|
DOC-Permit Expired | 10/28/2003 | 10/28/2003 | 10/28/2003 | | FAIL |
Jim Storey
|
|
|
Permit expired by limitations.
|
BLD-Aging Inspection | 8/26/2003 | 8/26/2003 | 8/26/2003 | | PASS |
Jim Storey
|
|
|
wip 8/26/2003 8:19:31 AM
|
Plan resubmittals received | | | 6/3/2003 | | DONE |
|
|
|
Received parcel information. Routed to Dave Abo. kmm
|
Override - Parcel Holds | | | 5/27/2003 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/27/2003 | | |
|
|
|
|
Telephone call | | | 5/16/2003 | | |
|
|
|
LEFT MESS THAT PERMIT READY
|
Plan assigned to (KMM) | 4/3/2003 | | 5/15/2003 | | PASS |
Kathy Miller
|
|
|
5/15/2003 09:21:42 KMM - activity updated through activity BLDA022 from case BLD03-00715.
|
Routing - PUBLIC WORKS | 5/14/2003 | | 5/15/2003 | | PASS |
|
|
|
Brian took the three extra sets out of permit set. kmm
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/15/2003 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 5/15/2003 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/15/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/15/2003 | | 5/15/2003 | | DONE |
|
|
|
|
Routing - FIRE | 5/1/2003 | | 5/13/2003 | | PASS |
|
|
|
resubmittal acceptable. review comments faxed to architect.
|
Plan resubmittals received | | | 5/9/2003 | | DONE |
|
|
|
Received two copies of revised E1.1 Put with plans. kmm
|
Routing - PLAN CHECK | 4/23/2003 | | 5/1/2003 | | |
|
|
|
Plans in hold box. kmm
|
Plan resubmittals received | | | 4/30/2003 | | |
|
|
|
Received two copies of revised sheets O, SP-1, P-1.1. One copy of plan review comments for Sam R., request for fire flow information, letter to United Water, vicinity map with wter line and United Water available flow information. Put with plans. kmm
|
Routing - FIRE | 4/15/2003 | | 4/22/2003 | | FAIL |
|
|
|
Plan resubmittal required. Review comments discussed with and faxed to Cornel Larson.
|
Routing - PLUMBING | 4/11/2003 | | 4/15/2003 | | PASS |
|
|
|
|
Routing - PLANNING | 4/11/2003 | | 4/11/2003 | | PASS |
|
|
|
Approved per conditions of approval of CUP02-154 pending Design Review approval.
|
Routing - PUBLIC WORKS | 4/4/2003 | | 4/10/2003 | | FAIL |
|
|
|
Requires drainage plan revisions. per Brian Murphy
Requires Street Light Plan. Street lighting plans submitted to I.E.S. Standard. per Hank Alarcon
|
Routing - Erosion and Sediment | 4/10/2003 | | 4/10/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans. Listed Responsible Person is not certified by Boise City. Please supply RP name and CON number to Jim Rogers @ ###-#### prior to the start of construction.
|
Routing - PLANNING Land Div | 4/4/2003 | | 4/4/2003 | | PASS |
|
|
|
For grading only. Do not issue building permit for building until Record of Survey to adjust property line process is completed. See Parcel Tag.
|
Plan routing begun/NEW & ADDTN | | | 4/4/2003 | | |
|
|
|
|
Application received | | | 4/3/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/3/2003 | | DONE |
|
|
|
|