Permit Information
Permit NumberBLD03-00715
StatusExpired
Name CORNEL LARSON
Site Address 2201 E PARKCENTER BLVD
Project NameGold's Gym @ Parkcenter
Customer Number 
ePlanReviewNo
Description
Gold's Gym * grading permit * To grub, clean, excavate, grade, import and compact site earth materials in preparation for the future construction of the Gold's Gym at Park Center. To install curb, gutter and paving in accordance with the grading and drainage plans approved by the public works department. Related site utilities included in this permit. No building demoliton, installation or construction is allowed under this permit. DRH03-0005 CUP02-00154 PC#171-03
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval4/6/20044/6/20044/6/2004 DONE
Drainage project complete, signed permanent occupancy 4/06/04. R.Rokovitz
DOC-Permit Expired10/28/200310/28/200310/28/2003 FAIL
DetailsJim Storey
Permit expired by limitations.
BLD-Aging Inspection8/26/20038/26/20038/26/2003 PASS
DetailsJim Storey
wip 8/26/2003 8:19:31 AM
Plan resubmittals received  6/3/2003 DONE
Received parcel information. Routed to Dave Abo. kmm
Override - Parcel Holds  5/27/2003  
Issue PAID IN FULL permit  5/27/2003  
Telephone call  5/16/2003  
LEFT MESS THAT PERMIT READY
Plan assigned to (KMM)4/3/2003 5/15/2003 PASS
DetailsKathy Miller
5/15/2003 09:21:42 KMM - activity updated through activity BLDA022 from case BLD03-00715.
Routing - PUBLIC WORKS5/14/2003 5/15/2003 PASS
Brian took the three extra sets out of permit set. kmm
PLANS/APPL TAKEN TO FRONT DESK  5/15/2003 DONE
Override - Parcel Holds  5/15/2003  
Print Pending Permit.LaserJet4  5/15/2003 DONE
Routing - PLAN CHECK5/15/2003 5/15/2003 DONE
Routing - FIRE5/1/2003 5/13/2003 PASS
resubmittal acceptable. review comments faxed to architect.
Plan resubmittals received  5/9/2003 DONE
Received two copies of revised E1.1 Put with plans. kmm
Routing - PLAN CHECK4/23/2003 5/1/2003  
Plans in hold box. kmm
Plan resubmittals received  4/30/2003  
Received two copies of revised sheets O, SP-1, P-1.1. One copy of plan review comments for Sam R., request for fire flow information, letter to United Water, vicinity map with wter line and United Water available flow information. Put with plans. kmm
Routing - FIRE4/15/2003 4/22/2003 FAIL
Plan resubmittal required. Review comments discussed with and faxed to Cornel Larson.
Routing - PLUMBING4/11/2003 4/15/2003 PASS
Routing - PLANNING4/11/2003 4/11/2003 PASS
Approved per conditions of approval of CUP02-154 pending Design Review approval.
Routing - PUBLIC WORKS4/4/2003 4/10/2003 FAIL
Requires drainage plan revisions. per Brian Murphy
Requires Street Light Plan. Street lighting plans submitted to I.E.S. Standard. per Hank Alarcon
Routing - Erosion and Sediment4/10/2003 4/10/2003 PASS
ESC approved with conditions attached to plans. Listed Responsible Person is not certified by Boise City. Please supply RP name and CON number to Jim Rogers @ ###-#### prior to the start of construction.
Routing - PLANNING Land Div4/4/2003 4/4/2003 PASS
For grading only. Do not issue building permit for building until Record of Survey to adjust property line process is completed. See Parcel Tag.
Plan routing begun/NEW & ADDTN  4/4/2003  
Application received  4/3/2003  
Plans ACCEPTED BY PLAN TECH  4/3/2003 DONE