(F) Reprint permit | | | 3/13/2007 | | |
|
|
|
|
First Notice | | 7/2/2003 | 7/2/2003 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 7/2/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9710 issued 7-2-03 to H.W. Investments, LLC.
|
BLD-Final | 6/30/2003 | 7/1/2003 | 7/1/2003 | A | PASS |
Carl Dependahl
|
|
|
TEMP OCC -DON; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...ok for c/o 7/1/2003 1:29:52 PM
|
Permanent Occupancy | | 7/1/2003 | 7/1/2003 | | DONE |
|
|
|
|
BLD-Conference | 6/27/2003 | 6/30/2003 | 6/30/2003 | P | PASS |
Carl Dependahl
|
|
|
Don; t/o req's... 6/30/2003 1:02:07 PM
|
BLD-Final | 6/30/2003 | 6/30/2003 | 6/30/2003 | P | PART |
Carl Dependahl
|
|
|
###-####; ok for t/o 90 days 6/30/2003 1:02:31 PM
|
BLD-Conference | 6/30/2003 | 6/30/2003 | 6/30/2003 | A | PASS |
Carl Dependahl
|
|
|
complete door hdwe
|
BLD-Final | 6/26/2003 | 6/27/2003 | 6/27/2003 | P | NR |
Carl Dependahl
|
|
|
DON; Phone #: ###-#### Internet Inspection Request from: Darla Downs...need plbg. 6/27/2003 6:35:37 PM
|
PubWorks Occupancy Approval | 6/25/2003 | 6/25/2003 | 6/25/2003 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 6/25/03. M.Strasser
|
FIRE-Final Inspection | 6/23/2003 | 6/24/2003 | 6/24/2003 | A | PASS |
Rick Jackson
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
Code Occupancy Approval | 6/23/2003 | 6/23/2003 | 6/23/2003 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met. 6/23/2003 1:16:49 PM
|
BLD-Footing | 6/9/2003 | 6/10/2003 | 6/10/2003 | P | CANC |
Carl Dependahl
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 6/4/2003 | 6/5/2003 | 6/5/2003 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 6/4/2003 at 1:40:49 PM. Contact: ###-####....ok to cover int walls pend plbg....discussed rails w/ bldr. 6/5/2003 3:03:10 PM
|
FIRE-Conference | 6/3/2003 | 6/3/2003 | 6/3/2003 | P | PART |
Rick Jackson
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Barbara Moore met with Don about door hardware - main exit will be the north exit and south door to be openable from the inside without special knowledge; extinguishers needed on both floors 6/3/2003 3:41:09 PM
|
Routing - PLAN CHECK | 5/30/2003 | | 6/2/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2003 | | PASS |
|
|
|
|
Print Occupancy Form | | | 6/2/2003 | | DONE |
|
|
|
|
Telephone call | | | 6/2/2003 | | DONE |
|
|
|
permit ready
|
Issue PAID IN FULL permit | | | 6/2/2003 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/10/2003 | | 6/2/2003 | | PASS |
Carl Westfall
|
|
|
6/2/2003 06:50:35 CJW - activity updated through activity BLDA022 from case BLD03-00742.
|
Routing - PLAN CHECK | 5/23/2003 | | 5/30/2003 | | PASS |
|
|
|
Forwarded back to Brian Murphy for approval.
|
Routing - PUBLIC WORKS | 5/30/2003 | | 5/30/2003 | | PASS |
|
|
|
Brian Murphy approved resubmitted drainage plans and returned to Plan Review.
|
Routing - PUBLIC WORKS | 5/22/2003 | | 5/23/2003 | | |
|
|
|
Modified drawings. Sent back to Brial Murphy to review new drainage pattern.
|
Routing - PLAN CHECK | 5/19/2003 | | 5/22/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/21/2003 | | DONE |
|
|
|
Received three copies of revised sheets C1.0, A1.0, A2.0. One copy of cover letter and one copy of response letter and one copy of stormwater management calculations. Routed to Carl W. kmm
|
Routing - FIRE | 5/9/2003 | | 5/19/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/23/2003 | | 5/9/2003 | | |
|
|
|
Failed first UBC review. UBC plan review started May 9, 2003 and finished the same day. A response from the designer was required. See the plan review report.
|
Routing - PUBLIC WORKS | 4/23/2003 | | 4/23/2003 | | PASS |
|
|
|
Went back later because of modified drawings.
|
Routing - PLAN CHECK | 4/16/2003 | | 4/23/2003 | | |
|
|
|
|
Routing - PLANNING | 4/15/2003 | | 4/16/2003 | | PASS |
|
|
|
Approved per DRH03-19.
|
Routing - PUBLIC WORKS | 4/10/2003 | | 4/15/2003 | | |
|
|
|
Failed first review. Requires a drainage plan.
|
Routing - Erosion and Sediment | 4/15/2003 | | 4/15/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Plan resubmittals received | | | 4/11/2003 | | DONE |
|
|
|
Received three copies of revised sheet A2.0. Put with plans. kmm
|
Routing - PLANNING Land Div | 4/10/2003 | | 4/10/2003 | | PASS |
|
|
|
Approved by ROS 5285.
|
Application received | | | 4/9/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/9/2003 | | |
|
|
|
Failed first submittal. Requires
1. Interior elevations
2. Dimensions
|