Case Summary (BLD) | | | 12/10/2014 | | DONE |
|
|
|
|
Fee Review-notes | 8/20/2003 | 8/20/2003 | 8/20/2003 | | DONE |
|
|
|
|
First Notice | | 7/31/2003 | 7/31/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/31/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9747 issued 7-31-03 to Berryhill & Company.
|
BLD-Aging Inspection | 7/29/2003 | 7/29/2003 | 7/29/2003 | | PASS |
Jim Storey
|
|
|
final ok 7/29/2003 8:04:36 AM
|
Permanent Occupancy | | 5/28/2003 | 5/28/2003 | | DONE |
|
|
|
|
BLD-Final | 5/27/2003 | 5/28/2003 | 5/28/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/27/2003 at 4:10:13 PM. Contact: ###-####. final ok sign offs archived. 5/28/2003 10:19:30 AM
|
Temporary occupancy | | | 5/28/2003 | | DONE |
|
|
|
Temp. Occ. Cert. #4956 issued 5-28-03 to Berryhill & Company in Broadway Park complex.
|
FIRE-Final Inspection | 5/23/2003 | 5/27/2003 | 5/27/2003 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety is OK. Door hardware was not installed yet but what the contractor showed me in the boxes would be OK 5/27/2003 9:47:18 AM
|
BLD-Final | 5/23/2003 | 5/27/2003 | 5/27/2003 | P | FAIL |
Jim Storey
|
|
|
shannon; Phone #: ###-#### Internet Inspection Request from: Darla Downs NEED PLM/ HEALTH DEPT./ PANIC HARDWARE ON BACK DOOR. 5/27/2003 2:45:31 PM
|
FIRE-Final Inspection | 5/23/2003 | 5/23/2003 | 5/23/2003 | P | NR |
Rick Jackson
|
|
|
shannon; Phone #: ###-#### Internet Inspection Request from: Barbara Moore met with the GC as they weren't ready for a final; exit signs need to be tested; exit doors to the east and west to be openable from the inside without special knowledge; hang extinguisher at east exit; kitchen area was exsisting and now work was performed in this area; will need to mount the K class extinguisher 5/23/2003 3:14:01 PM
|
BLD-Framing/Rough-in | 5/14/2003 | 5/15/2003 | 5/15/2003 | A | FAIL |
Jim Storey
|
|
|
###-#### ###-#### need fuseable link at fire damper/ need min 44 inch width for hallway. 5/15/2003 4:02:24 PM
|
Plan assigned to (JCB) | 4/17/2003 | | 5/14/2003 | | PASS |
Jason Blais
|
|
|
5/14/2003 10:27:27 JCB - activity updated through activity BLDA022 from case BLD03-00776.
|
Routing - PLAN CHECK | 5/14/2003 | | 5/14/2003 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/14/2003 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 5/14/2003 | | |
|
|
|
|
Print Occupancy Form | | | 5/14/2003 | | |
|
|
|
|
Override - Parcel Holds | | | 5/14/2003 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/14/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/24/2003 | | 5/13/2003 | | PEND |
|
|
|
Plan review sent to architect. No response required. Plans to route to Fire Dept. for review. When approved by Fire Dept. permit can be issued.
|
Routing - FIRE | 5/13/2003 | | 5/13/2003 | | PASS |
|
|
|
Comments faxed to architect.
|
Telephone call | | | 5/12/2003 | | |
|
|
|
Called architect to let him know an alternate approval would be accepted by the Building Director for the existing kitchen/adjacent tenant common wall where no work is occurring as only one hour rated, but the new A-2 expansion area must have a 2-hour fire barrier wall separation where common to adjacent tenants. The alternate approval also includes an additional exit from the A-2 for a total of three exits. Any new restaurant tenant that would occupy the space in the future would be required to upgrade the kitchen common wall to the adjacent tenant to a 2-hour rating.
|
Plan resubmittals received | | | 5/8/2003 | | |
|
|
|
Plan resubmittals provided.
|
Telephone call | | | 5/8/2003 | | |
|
|
|
Called architect concerning new code requirement of 2-hour fire barrier walls. Architect indicated an alternate approval request would be provided.
|
Telephone call | | | 5/7/2003 | | |
|
|
|
Called architect concerning some code issues needing to be addressed.
|
Routing - PLUMBING | 4/22/2003 | | 4/24/2003 | | PASS |
|
|
|
1. water heater may need pan w/drain to approved location 2. may need thermal expansion protection
|
Routing - PUBLIC WORKS | 4/17/2003 | | 4/22/2003 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 4/15/2003 | | 4/16/2003 | | PASS |
|
|
|
Contacted Cory Nelson at ###-#### to take plans out to CDH for review. kmm\\ approved by CDH Bob Mayer
|
Plans ACCEPTED BY PLAN TECH | | | 4/16/2003 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/14/2003 | | FAIL |
|
|
|
no CDH signature have call into Bob Mayer
|
Telephone call | | | 4/11/2003 | | DONE |
|
|
|
Contacted Bob Mayer at ###-####, left message for him to give us a call regarding signature for this project. kmm
|
Application received | | | 4/11/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/11/2003 | | DONE |
|
|
|
|
Fee Review-notes | 4/11/2003 | 4/11/2003 | | | |
|
|
|
we need fire values included in the total value. they are noted as n/a
|