First Notice | | 9/10/2003 | 9/10/2003 | | DONE |
|
|
|
|
BLD-Final | 9/8/2003 | 9/9/2003 | 9/9/2003 | A | PASS |
Jim Storey
|
|
|
KIM; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
Permanent Occupancy | | 9/9/2003 | 9/9/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/9/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9794 issued 9-9-03 to the Hong Kong Spa.
|
Code Occupancy Approval | | | 8/21/2003 | | PASS |
|
|
|
compliance met.
|
BLD-Final | 8/20/2003 | 8/20/2003 | 8/20/2003 | P | NR |
Russ Owen
|
|
|
kim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
Code Occupancy Approval | | | 8/20/2003 | | FAIL |
|
|
|
Inspection noted landscaping not completed in the small garden at the rear entrance. I spoke with "Kim" and a price of $200 was approved for a bond.
|
FIRE-Final Inspection | 8/19/2003 | 8/19/2003 | 8/19/2003 | P | PASS |
Rick Jackson
|
|
|
mark; Phone #: ###-#### Internet Inspection Request from: Barbara Moore door hardware wasn't correct but he had the right hardware and was going to install it by the time for the strcutural inspector 8/19/2003 3:28:38 PM
|
BLD-Conference | 7/21/2003 | 7/21/2003 | 7/21/2003 | P | PART |
Jim Storey
|
|
|
TOM WILL CALL YOU TO SCHEDULE A TIME; Phone #: ###-#### Internet Inspection Request from: Dixie Fellows arch to submit elavations to justify 1:12 ramp. 7/21/2003 2:42:37 PM
|
BLD-Conference | 7/9/2003 | 7/9/2003 | 7/9/2003 | P | PASS |
Jim Storey
|
|
|
GRAIG; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
Inspection Record Card- Bld | | | 6/18/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/18/2003 | | DONE |
|
|
|
|
Telephone call | | | 6/18/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Issue PAID IN FULL permit | | | 6/18/2003 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/17/2003 | | 6/17/2003 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/17/2003 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 4/28/2003 | | 6/17/2003 | | PASS |
Jason Blais
|
|
|
6/17/2003 13:06:42 JCB - activity updated through activity BLDA022 from case BLD03-00890.
|
Routing - PLANNING | 4/30/2003 | | 6/17/2003 | | PASS |
|
|
|
The net square footage bring the main floor to just below 1000 sq. ft. requiring 4 paking spaces one of which will be provided off-site at Wendy's
|
Routing - PLANNING | 6/12/2003 | | 6/17/2003 | | PASS |
|
|
|
Susan Riggs.
|
Routing - PLAN CHECK | 6/4/2003 | | 6/12/2003 | | PEND |
|
|
|
Plan approval dependent on approval by Planning. Route plans to Susan Riggs.
|
Routing - PLAN CHECK | 6/3/2003 | | 6/4/2003 | | PEND |
|
|
|
Building code issues addressed. Permit issuance pending approval by Planning for parking issue/agreement.
|
Telephone call | | | 6/4/2003 | | |
|
|
|
Called architect Barbara Beier and let her know a few items that will be red-lined on plan and that permit can be issued when Planning approves the parking issue/agreement.
|
Routing - FIRE | 5/23/2003 | | 6/3/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/3/2003 | | DONE |
|
|
|
Received two copies of revised sheets 1of 6, 2of 6, 4 of 6, 6 of 6. One copy of response letter, and one copy of revised TI application, cover sheet involved party sheet and registered design professional in responsible charge. Routed to Jason B. kmm
|
Plan resubmittals requested | | | 5/23/2003 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 5/2/2003 | | 5/23/2003 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
|
Telephone call | | | 5/22/2003 | | |
|
|
|
Called architect Barbara Beier and went over some code issues that will need to be addressed on this project.
|
Routing - PLUMBING | 5/1/2003 | | 5/2/2003 | | PASS |
|
|
|
bathroom remodel in existing, no plan required, additional cross connection protection may be required.
|
Routing - PUBLIC WORKS | 4/29/2003 | | 4/30/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/28/2003 | | DONE |
|
|
|
Tom would like a interior Demo permit prior to the building permit, also this came in with the value at 25,000.00 and I told him to break out the Demo portion hope thats ok.
|
Application received | | | 4/23/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/23/2003 | | |
|
|
|
|
Fee Review-notes | 4/25/2003 | 4/25/2003 | | | |
|
|
|
|