Case Summary (BLD) | | | 8/10/2006 | | DONE |
|
|
|
|
Permanent Occupancy | | 9/26/2003 | 9/26/2003 | | DONE |
|
|
|
|
First Notice | | 9/26/2003 | 9/26/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/26/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9814 issued 9-26-03 to the Boise Bagel Cafe in the Ram Bldg.
|
FIRE-Final Inspection | 8/21/2003 | 8/22/2003 | 8/22/2003 | A | PASS |
Rick Jackson
|
|
|
RICHARD; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Final | 8/21/2003 | 8/22/2003 | 8/22/2003 | P | PART |
Dave Hannah
|
|
|
RICHARD; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok for temp occ ok for perm occ after elec is perm occ 8/22/2003 4:02:53 PM
|
FIRE-Final Inspection | 8/21/2003 | 8/21/2003 | 8/21/2003 | P | FAIL |
Rick Jackson
|
|
|
richard; Phone #: ###-#### Internet Inspection Request from: Marc Lileks duct smoke detector not installed per IMC/IFC - needs audible trouble/alarm and installed on return 8/21/2003 2:42:17 PM
|
BLD-Framing/Rough-in | 6/24/2003 | 6/26/2003 | 6/26/2003 | P | PART |
Dave Hannah
|
|
|
jack; Phone #: ###-#### Internet Inspection Request from: Annette Moore ok to cover int walls after other trades sign off 6/25/2003 2:46:07 PM
|
Issue PAID IN FULL permit | | | 6/20/2003 | | DONE |
|
|
|
|
Telephone call | | | 6/16/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Routing - PLAN CHECK | 6/10/2003 | | 6/13/2003 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2003 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/13/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/13/2003 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 4/30/2003 | | 6/13/2003 | | PASS |
Jason Blais
|
|
|
6/13/2003 10:51:48 JCB - activity updated through activity BLDA022 from case BLD03-00900.
|
Routing - FIRE | 6/2/2003 | | 6/9/2003 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 6/9/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/6/2003 | | DONE |
|
|
|
Received response letter from Pat M., response letter from Kartchner Engineering, Zone design cooling load summary, four sets of A1.0,A1.1, A1.2, A3.1, A3.2, A3.3, P-1, E1.0, E2.0, and taken to jason
|
Plan resubmittals requested | | | 6/2/2003 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 5/2/2003 | | 6/2/2003 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
|
Routing - PUBLIC WORKS | 4/30/2003 | | 5/2/2003 | | PASS |
|
|
|
|
Routing - PLUMBING | 5/2/2003 | | 5/2/2003 | | PASS |
|
|
|
additional cross connection protection may be required, thermol expantion protection may need to be upgraded, provide shutoff valve for this space.
|
Plans ACCEPTED BY PLAN TECH | | | 4/29/2003 | | DONE |
|
|
|
|
Application received | | | 4/24/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/24/2003 | | DONE |
|
|
|
|
Fee Review-notes | 4/24/2003 | 4/24/2003 | | | |
|
|
|
|