Permit Information
Permit NumberBLD03-00956
StatusExpired
Name ANDREW ERSTAD
Site Address 2582 N BOGUS BASIN RD
Project NameHighlands Station (Pad A)
Customer Number 
ePlanReviewNo
Description
Highlands Station (Pad A) Shell & Core - To construct a 3,952 sq. ft. one story Type VB, fully fire sprinklered retail/office shell building. Other work includes all site improvements, paving and landscaping per approved plans and attachments, DRH03-00001 CUP03-00002. No Occupancy is authorized by this permit. Separate plans and permits are required for any tenant improvements. Fire sprinklers used for area.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permit EXPIRED  6/30/2008 DONE
Per email request from Marlene. This permit expired, last update was 2004
Routing - PLANNING11/9/2004 11/10/2004 FAIL
Revisions needed to comply with CUP and CVA approved Nov. 8, 2004. Also need DRH review. kg
CHANGE STATUS TO (PND)  11/9/2004 DONE
resubs recd 11/9/2004 - cmc
Plan resubmittals received  11/9/2004 DONE
Received two copies of revised sheet a1.11. Routed to Karen G. kmm
Ready Permit EXTENDED  9/28/2004 DONE
per bruce chatterton granted a 90 day extention until december 27, 2004 letter dated sept 27, 2004/mls
Extend Permit 180 days 3/12/20043/12/2004 PASS
DetailsTom Arcoraci
per letter from jenifer ok to extend permit to september 27th 2004/mls
CHANGE STATUS TO (R)  3/12/2004 DONE
filed for extension need to put back into ready status/mls
Ready Permit EXTENDED  3/12/2004 DONE
per letter from jennifer extend permit to september 27th 2004/mls
Telephone call  2/26/2004 DONE
left mess for andy that permit is ready-will need to pickup by march 29th or will need to void
Telephone call  1/27/2004 DONE
Left message for Andy to follow up if he requested the extension yet//1/27/04 BAM
Telephone call  1/27/2004 DONE
Spoke with Andy, he has the letter requesting an extension written and will be bringing it in in the next day or so//1/27/04 BAM
Telephone call  1/7/2004 DONE
Spoke with Andy he is going to ask for an extension this week on this permit//1/7/04 3:06pm BAM
Telephone call  10/21/2003 DONE
Left message to remind that permit is ready , fees and that we need ACHD
Plan assigned to (MLO)4/30/2003 9/29/2003 PASS
DetailsMike Otto
9/29/2003 09:16:09 MLO - activity updated through activity BLDA022 from case BLD03-00956.
PLANS/APPL TAKEN TO FRONT DESK  9/29/2003 DONE
Inspection Record Card- Bld  9/29/2003 DONE
Permit Ready to Issue  9/29/2003 DONE
Telephone call  9/29/2003 DONE
Spoke with Bill told permit ready, fees & need ACHD
Routing - PUBLIC WORKS9/22/2003 9/26/2003 PASS
Routing Off Site - STRUCTURAL9/10/2003 9/10/2003 PASS
Keith Jones contacted about seepage bed and was considered in original design.
Routing - PUBLIC WORKS8/28/2003 9/2/2003 FAIL
Requires drainage plan. New Bld. A appears to almost be on existing seepage bed. All per Brian Murphy. kmm
Routing - PLAN CHECK9/2/2003 9/2/2003 NR
Plan resubmittals received  9/2/2003 DONE
Received four copies of revised sheets S1.0, S2.0, S3.0, S4.0 & S5.0. Two additional copies of structl. calculations. Routed to Mike O. kmm
Routing - FIRE8/20/2003 8/27/2003 PASS
Resubmittal acceptable.
Plan resubmittals requested  8/21/2003 DONE
additional structural comments
Routing Off Site - STRUCTURAL8/15/2003 8/21/2003 FAIL
corrections sent to architect
Routing - PLAN CHECK8/15/2003 8/20/2003 PASS
Plan resubmittals received  8/14/2003 DONE
Recieved two additional copies of sheets S1.0, S2.0, S3.0, S4.0 & S5.0 and three copies of revised sheets a2.11. Routed to Mike O. kmm
Plan resubmittals received  7/25/2003 DONE
Fax transmittal from Erstad Thornton Arch,.Two copies of response letter,two copies of structural review comment responses, two copies of a map, two copies of structural calculations, two copies of C1.5a, C1.5b, (4copies ofA1.11,) A3.11, A5.12, S1.0, S2.0, S3.0, S4.0, S5.0, S1.0, S2.0, S3.0, S4.0, S5.0, taken to Mike O.
Plan resubmittals requested  7/23/2003 DONE
for parapet as corrected in fax and door on existing building to 45 minute
Routing - PLAN CHECK7/22/2003 7/23/2003 FAIL
went over parapet and exterior door with Neil Daigle from architects office. MLO
Routing - PLANNING Land Div7/22/2003 7/22/2003 PASS
Approved by ROS 6173 recorded on May 22, 2003.
Routing - PLAN CHECK6/17/2003 6/17/2003 NR
Routing - FIRE6/12/2003 6/17/2003 FAIL
review comments discussed with and faxed to Andrew Erstad
Routing Off Site -Energy5/9/2003 6/16/2003 PASS
Plans routed to Ron O. for energy review. kmm
Routing - PLAN CHECK5/22/2003 6/12/2003  
Routing Off Site - STRUCTURAL4/30/2003 6/11/2003 FAIL
contacted PDQ to take plans to outside engineering. Corrections faxed to architect
Plan resubmittals requested  6/10/2003 DONE
Routing - PLAN CHECK5/22/2003 6/10/2003 FAIL
architect contacted by phone and mail
Routing - PLUMBING5/22/2003 5/22/2003 PASS
roof drain and overflow piping shall be four inch where piping is common to two drains installed at an eight of inch per foot
Routing - PLANNING5/14/2003 5/21/2003 PASS
Approved for CUP compliance, if Land Division ensures recorded property line adjustment. KG 5-15-03
Approved per DRH03-1 and as noted on plans (MGS).
Routing - Erosion and Sediment5/12/2003 5/13/2003 PASS
ESC approved with conditions attached to plans.
Routing - PUBLIC WORKS5/1/2003 5/12/2003 FAIL
Plan resubmittals received  5/6/2003 DONE
Received copies of HVAC calculations. Put one with plans and one to Mike O. kmm
Routing - PLANNING Land Div4/30/2003 5/1/2003 FAIL
Need to completed Record of Survey. Waiting for revised site plans for CUP.
Plan routing begun/NEW & ADDTN  4/30/2003 DONE
Plans ACCEPTED BY PLAN TECH  4/30/2003 DONE
Application received  4/29/2003  
Recd Pcfee & Taken To Pln CK  4/29/2003  
Fee Review-notes4/29/20034/29/2003