Permit Information
Permit NumberBLD03-01020
StatusFinaled
Name SWOPE REAL ESTATE
Site Address 602 W IDAHO ST (3RD FLR)
Project NameEAGLES CENTER
Customer Number 
ePlanReviewNo
Description
(SWOPE REAL ESTATE - EAGLES CENTER - 3RD FLR) The fire sprinkler system is used to substitute for 1-hr fire-resistance rated construction. To create a new 664 square foot office tenant space located on the 3rd floor (5,464 square feet) of an existing historic building. Work is to include interior nonbearing walls, re-opening a bricked in historic window, a new structural concrete header over the re-opened window, a new window, and interior finishes all per approved drawings and plan review conditions on file. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection5/11/20095/11/20095/19/2009 PASS
DetailsDave Hannah
DOC - Permit Finaled5/19/20095/19/20095/19/2009PPASS
DetailsDave Hannah
BLD-Aging Inspection2/20/20092/20/20092/27/2009 PART
DetailsDave Hannah
waiting for fire
BLD-Aging Inspection12/5/200812/5/200812/9/2008 DONE
DetailsForrest France
Okay for final
BLD-Aging Inspection9/9/20089/9/20089/11/2008 CANC
DetailsForrest France
BLD-Aging Inspection7/7/20087/7/20087/9/2008 DONE
DetailsForrest France
Pending fire sprinkler permit final- verification of system main control valve supervision.
FIRE-Final Inspection1/24/20081/25/20081/30/2008APART
DetailsForrest France
Pending verification of a fire alarm supervisory switch at the main control valve for the fire sprinkler system.
BLD-Aging Inspection1/18/20081/18/20081/24/2008PDEFR
DetailsForrest France
Inspection scheduled.
BLD-Aging Inspection1/15/20081/15/20081/18/2008PDEFR
DetailsForrest France
Scheduled.
BLD-Aging Inspection1/15/20081/15/20081/18/2008 DEFR
DetailsDave Hannah
needs fire finals sent to fire
BLD-Aging Inspection10/10/200710/10/200710/15/2007 DEFR
DetailsDave Hannah
BLD-Aging Inspection8/10/20078/10/20078/14/2007 PASS
DetailsDave Hannah
BLD-Aging Inspection8/2/20068/2/20068/8/2006 DEFR
DetailsForrest France
BLD-Aging Inspection4/4/20064/4/20064/4/2006 DEFR
DetailsDave Hannah
waiting for fire dept sign off
BLD-Aging Inspection1/16/20061/16/20061/18/2006 DEFR
DetailsForrest France
BLD-Aging Inspection9/28/20059/28/20059/30/2005 PASS
DetailsForrest France
waiting on fire
BLD-Aging Inspection7/7/20057/7/20057/8/2005 DONE
DetailsForrest France
Left message with Dennis at ###-#### for requirements to final this permit.
FIRE-Final Inspection4/28/20054/29/20054/29/2005AFAIL
DetailsTroy Cobbley
Contact: ###-####. Inspection was a conference to see what items are needed for a final. Dennis is to provide verification that min control valve for the fire sprinkler system is monitored by the fire alarm system
BLD-Aging Inspection4/27/20054/27/20054/28/2005 NR
DetailsTroy Cobbley
I spoke to Dennis. He is going to call in an inspection to go over all outstanding issues.
BLD-Aging Inspection9/17/20049/17/20049/17/2004 PASS
DetailsRick Jackson
contractor out of town until october 2nd 9/17/2004 9:34:08 AM
BLD-Aging Inspection7/13/20047/13/20047/13/2004 PART
DetailsRick Jackson
Talked to Dennis and he will get the inspections called as the fire alarm panel has been installed and sprinkler system has received an annual inspection 7/13/2004 4:13:01 PM
BLD-Final7/31/20038/1/20038/1/2003APART
DetailsCarl Dependahl
ok for t/o...need fire ok 8/1/2003 2:14:45 PM
FIRE-Final Inspection7/30/20037/31/20037/31/2003APART
DetailsTroy Cobbley
Fire alarm and fire life safety given a temporary occupancy per Dave Miller until the main control vavle has been supervised by the fire alarm system. This will require city approved drawings. Contractor still needs to provide the annual inspection report so any other major issues can be addressed 7/31/2003 9:51:07 AM
BLD-Final7/30/20037/31/20037/31/2003PNR
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 7/30/2003 at 12:57:21 PM. Contact: ###-####.
Telephone call  7/30/2003 DONE
Documenting 7/30/03 (and other) telcon's with Bryan Connor, (Thornton Oliver Keller), Ken Webster, (Allied General), Dave Miller, and consultation with Carl Westfall regarding alarm requirements for this building. Concluded we need to have a discussion with the owner and architect to determine extent of existing protection, under what code it was installed, if it was required at the time of installation, the original occupancy of the building, and whether it met the existing code at that time, as well as what the anticipated occupancy(s) is intended to be., Then we can properly determine the code requirements. Until otherwise approved by the PDS/FD, the existing alarm system shall be maintained in service. Bryan will work with the building owner to set up such a meeting.
BLD-Conference7/18/20037/21/20037/21/2003APASS
DetailsCarl Dependahl
dennis ###-####..rec'd concrete test report from Strata, ok. 7/21/2003 4:09:24 PM
BLD-Framing/Rough-in7/21/20037/21/20037/21/2003PPASS
DetailsCarl Dependahl
BLD-Framing/Rough-in7/17/20037/18/20037/18/2003APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 7/17/2003 at 1:32:16 PM. ..walls ok 7/21/2003 1:32:53 PM
BLD-Framing/Rough-in7/15/20037/16/20037/16/2003AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 7/15/2003 at 1:10:22 PM. Contact: ###-####....need actual spec insp data 7/16/2003 10:24:42 AM
BLD-Concrete6/19/20036/20/20036/20/2003PCANC
DetailsCarl Dependahl
lintel
BLD-Conference6/18/20036/19/20036/19/2003ACANC
DetailsCarl Dependahl
Dennis
BLD-Concrete6/19/20036/19/20036/19/2003PNR
DetailsCarl Dependahl
BLD-Conference6/17/20036/18/20036/18/2003APASS
DetailsCarl Dependahl
need spec insp for lintel...5000psi concrete spec'd. 6/18/2003 3:50:16 PM
BLD-Concrete6/16/20036/17/20036/17/2003PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 6/16/2003 at 4:44:48 PM. Contact: ###-####.
Issue PAID IN FULL permit  6/6/2003 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/5/2003 PASS
Telephone call  6/5/2003 DONE
LEFT MESS THAT PERMIT IS READY
Inspection Record Card- Bld  6/5/2003 DONE
Print Occupancy Form  6/5/2003 DONE
Routing - PLAN CHECK6/3/2003 6/4/2003 PASS
Plan assigned to (CJW)5/8/2003 6/4/2003 PASS
DetailsCarl Westfall
6/4/2003 16:21:13 CJW - activity updated through activity BLDA022 from case BLD03-01020.
Routing - FIRE5/22/2003 6/2/2003 PASS
Routing - PLAN CHECK5/9/2003 5/22/2003  
Failed first UBC plan review. UBC plan review started May 21, 2003 and finished the next day. A response from the architect was required. See the plan review report.
Plan resubmittals received  5/14/2003 DONE
received letter of transmittal, two copies of concrete rectangular & tee beam design, along with two A2.1 plans and taken to Carl W.
Routing - PUBLIC WORKS5/8/2003 5/9/2003 PASS
DetailsBrandi Dominguez
Application received  5/6/2003  
Recd Pcfee & Taken To Pln CK  5/6/2003 DONE
Plans ACCEPTED BY PLAN TECH  5/6/2003 DONE
First Notice5/19/20095/19/2009   
DetailsDave Hannah
Fee Review-notes5/6/20035/6/2003