BLD-Final | 10/1/2003 | 10/3/2003 | 10/3/2003 | A | PASS |
Jim Storey
|
|
|
larry; Phone #: ###-#### Internet Inspection Request from: Annette Moore final ok card on site. 10/3/2003 10:39:49 AM
|
First Notice | | 10/3/2003 | 10/3/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 10/3/2003 | 10/3/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/3/2003 | | DONE |
|
|
|
Perm. Occ. Cert. # 9832 issued 10-3-03 to Dr. David Munro on the 3rd floor of the Anderson Plaza bldg.
|
FIRE-Final Inspection | 9/30/2003 | 10/1/2003 | 10/1/2003 | A | PASS |
Rick Jackson
|
|
|
larry; Phone #: ###-#### Internet Inspection Request from: Annette Moore GC will have door hardware and smoke seal for structural inspector as it was just painted; penetrations in corridor wall require fire stopping 10/1/2003 3:02:08 PM
|
BLD-Framing/Rough-in | 9/30/2003 | 10/1/2003 | 10/1/2003 | A | PART |
Dave Hannah
|
|
|
larry; Phone #: ###-#### Internet Inspection Request from: Annette Moore ceiling grid needs spreader bars 10/1/2003 12:41:47 PM
|
FIRE-Final Inspection | 9/25/2003 | 9/25/2003 | 9/25/2003 | P | FAIL |
Rick Jackson
|
|
|
larry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie penetrations reuire fire stopping; duct opening in corridor wall requires smoke/fire damper with detection to operate damper; hang fire extinguisher 9/25/2003 4:06:41 PM
|
Inspection Record Card- Bld | | | 8/28/2003 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 8/8/2003 | 8/8/2003 | 8/8/2003 | P | PART |
Carl Dependahl
|
|
|
larry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore...ok to cover walls, patch floor/clg & walls for 1hr const as req'd...continuous gypsum req'd 8/8/2003 2:51:14 PM
|
BLD-Conference | 8/5/2003 | 8/6/2003 | 8/6/2003 | A | PASS |
Carl Dependahl
|
|
|
LARRY; Phone #: ###-#### Internet Inspection Request from: Darla Downs...1hr bldg, need patch gyp & firestop penetrations...may req fire damper at exh duct. ok to cover int partitions pending elec/plbg 8/6/2003 12:03:23 PM
|
Issue & PRINT permit | | | 7/7/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/3/2003 | | DONE |
|
|
|
|
Telephone call | | | 7/3/2003 | | DONE |
|
|
|
permit ready
|
Routing - PLAN CHECK | 6/11/2003 | | 7/2/2003 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2003 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 5/15/2003 | | 7/2/2003 | | PASS |
Carl Westfall
|
|
|
7/2/2003 13:58:32 CJW - activity updated through activity BLDA022 from case BLD03-01060.
|
Plan resubmittals received | | | 6/26/2003 | | DONE |
|
|
|
Transmittal from Russ Powers, two sets of A2.0, A3.0, A3.1, A5.0, and taken to Carl.
|
Routing - FIRE | 6/9/2003 | | 6/11/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/22/2003 | | 6/9/2003 | | |
|
|
|
Failed first IBC review. IBC plan review started June 6, 2003 and finished June 9, 2003. A response from the architect was required. See the plan review report.
|
Routing - PLUMBING | 5/19/2003 | | 5/21/2003 | | PASS |
|
|
|
sht, P1.0, too many fixture units on a 2" waste line serving s-1, fs-1, b-1, cc-1, ss-1, ew-1, ls-1, incerase to 3". compressed air and vacuum only, no other medical gas systems.
|
Routing - PUBLIC WORKS | 5/15/2003 | | 5/16/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/12/2003 | | DONE |
|
|
|
Application has a Mechanical value, does not have a mechanical plan.
|
Application received | | | 5/8/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/8/2003 | | DONE |
|
|
|
|
Fee Review-notes | 5/8/2003 | 5/8/2003 | | | |
|
|
|
|