BLD-Final | 10/22/2003 | 10/22/2003 | 10/22/2003 | | DONE |
|
|
|
Final - ok for perm. occ.
|
First Notice | | 10/22/2003 | 10/22/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 10/22/2003 | 10/22/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/22/2003 | | DONE |
|
|
|
Perm. Occ. cert. #9850 issued 10-22-03 to the Broadway Baptist Church for a modular classroom bldg.
|
Code Occupancy Approval | 10/21/2003 | 10/21/2003 | 10/21/2003 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met. 10/21/2003 3:53:17 PM
|
PubWorks Occupancy Approval | 10/20/2003 | 10/20/2003 | 10/20/2003 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 10/20/03. R.Rokovitz
|
BLD-Other | 10/16/2003 | 10/17/2003 | 10/17/2003 | P | NR |
Jim Storey
|
|
|
Gutters// ###-#### bob
|
FIRE-Final Inspection | 10/13/2003 | 10/13/2003 | 10/13/2003 | P | PASS |
Rick Jackson
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
FIRE-Final Inspection | 10/9/2003 | 10/9/2003 | 10/9/2003 | P | FAIL |
Rick Jackson
|
|
|
###-#### jeff###-#### jeff extinguishers and fire alarm system is not required but has local alarm system with pulls and one pull is needed at south exit 10/9/2003 1:10:13 PM
|
BLD-Framing/Rough-in | 10/3/2003 | 10/6/2003 | 10/6/2003 | A | FAIL |
Jim Sly
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Darla Downs called left message......No one at office.......Left note to re-call. 10/6/2003 11:11:04 AM
|
BLD-Final | 10/3/2003 | 10/3/2003 | 10/3/2003 | P | NR |
Jim Storey
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Framing/Rough-in | 9/17/2003 | 9/17/2003 | 9/17/2003 | P | PASS |
Jim Storey
|
|
|
jef; Phone #: ###-#### Internet Inspection Request from: Annette Moore blk and tie and tag ok. 9/17/2003 1:34:14 PM
|
Inspection Record Card- Bld | | | 6/12/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/12/2003 | | DONE |
|
|
|
|
Telephone call | | | 6/12/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
CHANGE ISSUED DATE | | | 6/11/2003 | | |
|
|
|
|
Plan assigned to (MLO) | 5/15/2003 | | 6/11/2003 | | PASS |
Mike Otto
|
|
|
6/11/2003 14:01:26 MLO - activity updated through activity BLDA022 from case BLD03-01105.
|
Routing - Erosion and Sediment | 6/11/2003 | | 6/11/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
ISSUE ACTIONS | | | 6/11/2003 | | |
|
|
|
|
Case Summary (BLD) | | | 6/11/2003 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2003 | | DONE |
|
|
|
|
Routing - FIRE | 6/2/2003 | | 6/10/2003 | | PASS |
Bill Alexander
|
|
|
With special conditions. See review notes, items #1 and 2! Fxed copy of review to Teal Architects, ###-####.
|
Plan Review Completed(1st rev) | | | 6/10/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/6/2003 | | DONE |
|
|
|
ESC resubmittals received and forwared to Jim Rogers. Info includes cover memo, grading and drainage calcs, sediment plan, 1 copy of foundation plan, 2 copies of site plan.
|
Routing - PLAN CHECK | 5/22/2003 | | 6/2/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/23/2003 | | DONE |
|
|
|
letter of transmittal from MTC inc. two copies of sediment plan and two copies of ESC narrative and taken to Mike O.
|
Routing - PLANNING | 5/21/2003 | | 5/22/2003 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 5/20/2003 | | 5/21/2003 | | FAIL |
|
|
|
ESC Plan does not meet requirements of BCC 8-17 or Appendix A & C of plan designer manual. Contacted project manager.
|
Routing - PUBLIC WORKS | 5/19/2003 | | 5/19/2003 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 5/15/2003 | | 5/16/2003 | | PASS |
|
|
|
Approved. Portion of Lot 14 of Veazy Park created prior to 10/30/65.
|
Plans ACCEPTED BY PLAN TECH | | | 5/15/2003 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 5/15/2003 | | DONE |
|
|
|
|
Application received | | | 5/14/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/14/2003 | | |
|
|
|
|
Fee Review-notes | 5/14/2003 | 5/14/2003 | | | |
|
|
|
|