Permit Information
Permit NumberBLD03-01204
StatusFinaled
Name ST LUKES RMC (CENTRAL PLANT)
Site Address 140 E JEFFERSON ST
Project NameST LUKES-CENTRAL PLANT
Customer Number22-647
ePlanReviewNo
Description
(ST LUKES RMC)(CENTRAL PLANT UPGRADE)(This permit for Phase I & 2 with preparation for future Phase 3) "PROVIDE SPECIAL INSPECTION PER SHEET 'S1.0'". To replace mechanical and electrical upgrades and replace roof membrane system with Class 'B' membrane on the Central Plant per approved plans and DRH03-00074. Work to include replacement of 2 existing cooling towers with 1 new one; provide structural support system per engineering; relocate 2 evaporative coolers & provide new penetrations for duct work to existing Boiler room; selective demolition & replace of existing water chiller in basement;build new equipment screen wall at roof perimeter; and run electrical to new pad for future generator unit / facility. All work is exterior to the building or within the existing rated construction with sprinkler protection. 'Letter of Compliance' required for this project when completed. PC03-302/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  8/4/2004 DONE
Letter of Compliance issued 8-4-04.
FIRE-Final Inspection7/29/20047/30/20047/30/2004APASS
DetailsRick Jackson
ron; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Final7/30/20047/30/20047/30/2004PPASS
DetailsTroy James
Ron; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
FIRE-Final Inspection6/14/20046/14/20046/14/2004PFAIL
DetailsRick Jackson
ron; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Needs a new R-123 sensor at new chiller; the exsisting R-123 panel on west side of new chiller doesn't appear to be operational 6/14/2004 2:23:16 PM
Code Occupancy Approval6/8/20046/8/20046/8/2004PPASS
DetailsWm. Michael Meloy
Compliance met. 6/8/2004 2:28:37 PM
BLD-Final6/3/20046/4/20046/4/2004ACANC
DetailsDave Hannah
Ron; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD-Final6/4/20046/4/20046/4/2004PNR
DetailsDave Hannah
Ron; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
Print Occupancy Form  5/20/2004 DONE
BLD-Concrete2/27/20043/1/20043/1/2004APASS
DetailsDave Hannah
ron ; Phone #: ###-#### Internet Inspection Request from: Annette Moore gen pad 3/1/2004 9:46:52 AM
BLD-Concrete1/27/20041/28/20041/28/2004APART
DetailsDave Hannah
ron; Phone #: ###-#### Internet Inspection Request from: Annette Moore done with spec inspection 1/29/2004 8:02:45 AM
BLD-Aging Inspection12/5/200312/5/200312/5/2003 PART
DetailsDave Hannah
work in progress 12/5/2003 8:13:09 AM
Case Summary (BLD)  9/22/2003  
Inspection Record Card- Bld  9/4/2003 DONE
Permit Ready to Issue  9/4/2003 DONE
Telephone call  9/4/2003 DONE
permit ready and fees due by email to Curtis
(F) Reprint permit  9/4/2003  
Issue & PRINT to be Invoiced  9/4/2003 DONE
Routing - FIRE8/27/2003 9/3/2003 PASS
Resubmittal acceptable.
Routing - PLAN CHECK9/3/2003 9/3/2003 PASS
Approved as noted on plans and attached plan review comments.
PLANS/APPL TAKEN TO FRONT DESK  9/3/2003 PASS
To permit desk to issue.
Plan assigned to (DRS)5/30/2003 9/3/2003 PASS
DetailsDan Stuart
9/3/2003 18:27:29 DRS - activity updated through activity BLDA022 from case BLD03-01204.
Routing - PLAN CHECK7/11/2003 8/27/2003 PEND
Resubmittals for fire code analyst received. Inserted into plans & routed to fire code analyst.
Plan resubmittals received  8/26/2003 DONE
Resubmitted 1 each of the following: M-1, M-2, M-3, M-4, M-5 and E4.0 along with cover letter. Forwarded to Dan Stuart.
Telephone call  7/30/2003 DONE
Call from Josh Howe, ZGA checking on status of this permit.Reviewed with him that I had received a final letter of review approval on structural review and energy code review but no entry in computer or resubmittals to my desk on fire code analyst plan review requiring additional information on refrigerants & refrigeration system to show compliance with IFC 606. Josh said he thought the response had been provided. I told Josh I would check with Sam rogers & front desk to see if they had been received but not yet sent to me if he would check on his end to make sure a response was provided.
Meeting  7/30/2003 DONE
Checked with Sam Rogers to see if he had received response to his plan review for this project. He has not.
Meeting  7/30/2003 DONE
Checked with Rita & Kathy to see if submittals had been received but not yet processed. No resubmittal for this project.
Telephone call  7/30/2003 DONE
Called Josh to let him know that we do not have resubmittals. Josh had found fire code analyst plan review on Art Zabala's desk. In there first cursory review they had not understood that resubmittals were required. They would work with SLRMC Mintenance engineers & mechanical engineer to get iformation for response.
Routing - FIRE7/3/2003 7/10/2003 FAIL
Refrigerant and system details required to verify compliance with IFC 606. Review comments faxed to architect.
Routing Off Site -Energy6/11/2003 7/8/2003 PASS
7/8/03 - received notice from Eric Makela approving architect & mechanical engineers responses to his original plan review. Copy attached to plans.
Routing Off Site - STRUCTURAL7/1/2003 7/7/2003 PASS
Contacted PDQ to take resubmitted calcs of 6/26/03 to outside engineering. kmm
7/7/2003-Received approved review comments and forwarded to Dan Stuart.
Routing - PLAN CHECK6/11/2003 7/3/2003 FAIL
6/11/03 - Copy of structural engineers report faxed & mailed to architect of record for response.
Waiting for approvals / resubmittals for structural & energy outsource plan reviews. Routing to fire code analyst for review.
Plan resubmittals requested  7/3/2003 FAIL
Plan resubmittals for energy code compliance review were sent to applicant on 6/11/03. Waiting for response.
Resubmittals request for structural engineering on 6/11/03. Response received on 6/26/03 & routed to outsource structural engineer for re-review on 7/1/03.
Telephone call  7/2/2003 DONE
PHONE CALL TO CURTIS WEEDOP, SLRMC, TO DETERMINE IF MECHANICAL WORK IS BEING DONE. NO VALUE ON C.V. BUT RELOCATION OF EVAPORATIVE COOLERS WITH NEW OPENINGS CUT THROUGH CONCRETE ROOF DECK INDICATES NEW DUCT WORK WILL BE INSTALLED FROM UNITS TO THE BOILER ROOM. CURTIS TO FIND OUT AND CALL ME BACK.
Plan resubmittals received  6/26/2003 DONE
Resubmittal of structural calcs and cover letters received and forwarded to Dan S.
Routing - PLUMBING6/11/2003 6/11/2003 PASS
all drains from cooling towers and coolers to be piped to s.s., all equipment make-up water to be from down stream of an r.p..
Routing Off Site - STRUCTURAL5/29/2003 6/11/2003 FAIL
Contacted PDQ to take plans to outside engineering.
6/11/03 - Received comments from out source structural engineer. Resubmittals / clarification required. Copy sent to architect for response.
Routing Off Site -Energy  6/11/2003 FAIL
Will contact Erik M. for pick up for energy review when forth set of plans received. kmm
6/11/03 - Received copy of required items needing to be re-addressed for energy code review for approval. Copy was sent to applicant on this date also by enrgy code plan reviewer.
Routing - Erosion and Sediment6/10/2003 6/10/2003 PASS
ESC approved with conditions attached to plans.
Routing - PLANNING6/5/2003 6/9/2003 PASS
Approve per DRH03-74
Routing - PUBLIC WORKS5/30/2003 6/5/2003 PASS
Plans ACCEPTED BY PLAN TECH  5/29/2003 PEND
Requires forth set of plans for energy review per Dan S. Also requires ESC application. Contacted Curtis W. of these needs. kmm
Application received  5/23/2003  
Recd Pcfee & Taken To Pln CK  5/23/2003 DONE
Fee Review-notes5/23/20035/23/2003