First Notice | | 4/7/2004 | 4/7/2004 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/7/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10088 issued 4-7-04 to the Fed Ex Freight bldg.
|
Permanent Occupancy | | 3/30/2004 | 3/30/2004 | | DONE |
|
|
|
|
BLD-Final | 11/25/2003 | 11/26/2003 | 11/26/2003 | A | PART |
Jim Sly
|
|
|
RON; Phone #: ###-#### Internet Inspection Request from: Darla Downs OK for Temp Occ. Need Perm Occ status from Electr.......After Electr final for Perm, OK for Perm Occ On structural. C/N Obtain Perm Occ status within 90 days of this notice. 11/26/2003 8:57:29 AM 11/26/2003 8:57:54 AM
|
Temporary occupancy | | | 11/26/2003 | | DONE |
|
|
|
Temp. Occ. Cert. # 5029 issued 11-26-03 to FedEx Freight Shop Building.
|
BLD-Final | 11/25/2003 | 11/25/2003 | 11/25/2003 | P | NR |
Jim Sly
|
|
|
ron ###-#### Need signatures from ACHD Public works and code enforc....... 11/25/2003 1:17:26 PM
|
FIRE-Final Inspection | 11/25/2003 | 11/25/2003 | 11/25/2003 | A | PASS |
Troy Cobbley
|
|
|
fire life safety ok
|
Code Occupancy Approval | | | 11/25/2003 | | PASS |
|
|
|
LOOKS OK FINAL SIGNED OFF.
|
FIRE-Final Inspection | 11/21/2003 | 11/24/2003 | 11/24/2003 | A | FAIL |
Troy Cobbley
|
|
|
Provide fire extinguishers and final fire alarm system 11/24/2003 12:26:08 PM
|
BLD-Framing/Rough-in | 9/29/2003 | 9/29/2003 | 9/29/2003 | P | PASS |
Jim Sly
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Darla Downs All framing and shear panels...OK 9/29/2003 4:06:11 PM
|
BLD-Framing/Rough-in | 9/23/2003 | 9/24/2003 | 9/24/2003 | A | PART |
Jim Sly
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Darla Downs inspection of metal studs (12" O.C.) at perimeter (shear) walls of Mezzanine....OK to sheath. 9/24/2003 8:38:10 AM
|
BLD-Foundation | 7/14/2003 | 7/15/2003 | 7/15/2003 | A | PASS |
Dave Hannah
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Dixie Fellows strata on site testing concrete i also checked rebar all looked good 7/15/2003 12:29:54 PM
|
BLD-Footing | 7/10/2003 | 7/11/2003 | 7/11/2003 | A | PART |
Russ Owen
|
|
|
GAIL- ###-#### footings in place and Strata will be performing special inspection.11/2003 11:14:43 AM 7/11/2003 11:15:23 AM
|
(F) Reprint permit | | | 7/11/2003 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/10/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/10/2003 | | DONE |
|
|
|
|
Telephone call | | | 7/10/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Issue PAID IN FULL permit | | | 7/10/2003 | | |
|
|
|
|
Routing - PLAN CHECK | 7/9/2003 | | 7/9/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2003 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 5/23/2003 | | 7/9/2003 | | PASS |
John Menard
|
|
|
7/9/2003 09:24:23 JCM - activity updated through activity BLDA022 from case BLD03-01206.
|
Routing - PLAN CHECK | 7/2/2003 | | 7/3/2003 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 7/3/2003 | | PASS |
|
|
|
Plan revisions as approved as submitted. JCM
|
Routing - FIRE | 6/25/2003 | | 7/1/2003 | | FAIL |
|
|
|
Resubmittal relative to Haz Mat's required to determine occupancy of Shop. Review comments faxed to architect.
|
Plan resubmittals received | | | 6/26/2003 | | DONE |
|
|
|
letter of transmittal from Larson Arch, Response letter with a letter of Accreditation, two set of O,SP-1, SA-1, SA-4 and taken to John M.
|
Routing - PLAN CHECK | 6/18/2003 | | 6/25/2003 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 6/24/2003 | | |
|
|
|
E-mailed the architect a copy of the plan review comment list requesting revisions. JCM
|
Routing - PLUMBING | 6/13/2003 | | 6/18/2003 | | PASS |
|
|
|
see bld03-00986 for comments
|
Routing - PLANNING | 6/11/2003 | | 6/13/2003 | | PASS |
|
|
|
Approve per DRH02-219
|
Routing - Erosion and Sediment | 6/9/2003 | | 6/10/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans. Original ESC 03-00556
|
Routing - PUBLIC WORKS | 5/29/2003 | | 6/9/2003 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 5/27/2003 | | 5/29/2003 | | PASS |
|
|
|
Parcel is over 5 acres in size.
|
Plan routing begun/NEW & ADDTN | | | 5/27/2003 | | DONE |
|
|
|
|
Application received | | | 5/23/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/23/2003 | | DONE |
|
|
|
|
Routing - FIRE | 7/3/2003 | | 7/8/2002 | | PASS |
|
|
|
Satisfactory Haz Mat report provided.
|
Routing Off Site - STRUCTURAL | 5/27/2003 | | | | |
|
|
|
Contacted PDQ to take plans to outside engineering. kmm
|
Plan routing begun/NEW & ADDTN | | | | | |
|
|
|
|