Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD03-01218
StatusVoid/No Violation
Name KEILTY CONSTRUCTION
Site Address 4061 W OVERLAND RD
Project NameWIDDISON DENTISTRY
Customer Number 
ePlanReviewNo
Description
Widdison Dentistry Remodel & Addition - to construct 1,074 sq. ft. of additions to the north and south ends of an existing 1,617 sq. ft. one story type VB medical office building with an existing basement. Other work includes remodeling of the existing first floor with new handicapped restroom and to correct the existing stair to the basement, construct a non-useable under floor area to reduce floor area of the basement to not exceed 1500 sq. ft. thereby not requireing fire sprinklers. All work is per approved plans and attachments. DRH02-00142
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval1/21/20051/21/20051/21/2005 DONE
no inspections, drive-by shows complete 1/21/05 R.Rokovitz
Voucher Form  6/9/2004 DONE
not doing job refund to keilty cont
VOIDED CHANGE STATUS  6/9/2004 DONE
not doing job per Keilty const
BLD-Aging Inspection6/3/20046/3/20046/3/2004 NR
DetailsTom Arcoraci
(F) Reprint permit  5/27/2004 DONE
Issue PAID IN FULL permit  3/2/2004 DONE
Telephone call  1/29/2004 DONE
talked to pat mckeegan to verify plans are ready
Telephone call  1/8/2004 DONE
Spoke with Pat to remind him that permit is ready & fees//1/8/04 10:44am BAM
Plan assigned to (MLO)6/2/2003 10/23/2003 PASS
DetailsMike Otto
10/23/2003 11:11:02 MLO - activity updated through activity BLDA022 from case BLD03-01218.
PLANS/APPL TAKEN TO FRONT DESK  10/23/2003 DONE
Telephone call  10/23/2003 DONE
called Pat permit ready & fee given 10-23-03 11:38
CHANGE STATUS TO (R)  10/23/2003 DONE
Inspection Record Card- Bld  10/23/2003 DONE
Print Occupancy Form  10/23/2003 DONE
Routing - PLANNING Land Div10/21/2003 10/22/2003 PASS
Approved. North and south portions of parcel were created in 1957. Parcels were combined in 2003.
Routing - PUBLIC WORKS10/14/2003 10/15/2003 PASS
Routing - PLAN CHECK9/30/2003 10/6/2003 PASS
Routing - PUBLIC WORKS9/19/2003 9/30/2003 FAIL
Requires drainage plan revision per Brian M. kmm
Plan resubmittals received  9/29/2003 DONE
Received response letter with two sets of A3.0,A5.0,A6.0, A6.1. taken to Mike O
Plan resubmittals requested  9/25/2003 DONE
CAll from the architect on status: Corrections of 8/11 never responded to. Re sent corrections to architect. MLO
Routing - FIRE9/4/2003 9/11/2003 PASS
Approved per resubmittal. Review comments faxed to architect.
Routing - PLAN CHECK8/19/2003 9/4/2003 FAIL
Corrections not done, resubmitted sheets addressing fire dept corrections for floor area and construction of walls in basement inserted and plans sent to fire. MLO
Plan resubmittals received  8/29/2003 DONE
Received one copy of cover letter and two copies of revised sheets A2.0 & A6.1. Routed to Mike O. kmm
Routing - PLANNING8/15/2003 8/19/2003 PASS
Approved per DRH02-142.
Routing Off Site -Energy8/12/2003 8/14/2003 PASS
contacted Ron O for energy review of revised mech. calcs. received on 8-6-03
Routing - FIRE8/12/2003 8/14/2003 FAIL
Reveiw of 8/5/03 resubmittal. Bsmt still requires automatic sprinklers. Revised review comments faxed to architect.
Routing - PLAN CHECK8/6/2003 8/11/2003 FAIL
corrections sent to architect
Plan resubmittals requested  8/11/2003 DONE
IBC corrections and plans not stamped and signed by architect.
Plan resubmittals received  8/6/2003 DONE
Received one copy of HVAC calculations, structural engineer's calculations, response letter and one copy of letter to Sam. Three copies of revised sheets T1.0, A1.0, A1.1, A2.0, A3.0, A3.1, A3.2, A5.0, A6.0, A6.1. Routed to Mike O. kmm
Routing Off Site -Energy7/30/2003 8/2/2003 FAIL
Contacted Ron O for revised energy review. kmm
Plan resubmittals requested  7/23/2003 DONE
Energy corrections
Routing Off Site -Energy6/2/2003 7/23/2003 FAIL
Contacted Ron O. for outside energy. Corrections sent to architect MLO
Routing - FIRE6/23/2003 6/26/2003 FAIL
Review comments faxed to architect; re.bsmt AS, FD access, hydrant location & flow, egress lighting.
Plan resubmittals requested  6/23/2003 DONE
IBC corrections
Routing - PLAN CHECK6/16/2003 6/23/2003 FAIL
corrections sent to architect
Routing - PLUMBING6/13/2003 6/13/2003 PASS
additional cross connection protection may be required, all work to comply with 2000 upc
Routing - PLANNING6/11/2003 6/12/2003 FAIL
Proposed parking at south yard does not comply with minimum driveway width standards.
Routing - Erosion and Sediment6/9/2003 6/10/2003 PASS
ESC approved with conditions attached to plans.
Routing - PUBLIC WORKS6/3/2003 6/9/2003 FAIL
Requires drainage plan revisions per Brian M. kmm
Routing - PLANNING Land Div6/2/2003 6/3/2003 FAIL
Need proof of legal land division. Parcel of portion of platted lot.
Plans ACCEPTED BY PLAN TECH  6/2/2003 DONE
Plan routing begun/NEW & ADDTN  6/2/2003  
Recd Pcfee & Taken To Pln CK  5/27/2003 DONE
Fee Review-notes5/27/20035/27/2003