PubWorks Occupancy Approval | 1/21/2005 | 1/21/2005 | 1/21/2005 | | DONE |
|
|
|
no inspections, drive-by shows complete 1/21/05 R.Rokovitz
|
Voucher Form | | | 6/9/2004 | | DONE |
|
|
|
not doing job refund to keilty cont
|
VOIDED CHANGE STATUS | | | 6/9/2004 | | DONE |
|
|
|
not doing job per Keilty const
|
BLD-Aging Inspection | 6/3/2004 | 6/3/2004 | 6/3/2004 | | NR |
Tom Arcoraci
|
|
|
|
(F) Reprint permit | | | 5/27/2004 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/2/2004 | | DONE |
|
|
|
|
Telephone call | | | 1/29/2004 | | DONE |
|
|
|
talked to pat mckeegan to verify plans are ready
|
Telephone call | | | 1/8/2004 | | DONE |
|
|
|
Spoke with Pat to remind him that permit is ready & fees//1/8/04 10:44am BAM
|
Plan assigned to (MLO) | 6/2/2003 | | 10/23/2003 | | PASS |
Mike Otto
|
|
|
10/23/2003 11:11:02 MLO - activity updated through activity BLDA022 from case BLD03-01218.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/23/2003 | | DONE |
|
|
|
called Pat permit ready & fee given 10-23-03 11:38
|
CHANGE STATUS TO (R) | | | 10/23/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/23/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/23/2003 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 10/21/2003 | | 10/22/2003 | | PASS |
|
|
|
Approved. North and south portions of parcel were created in 1957. Parcels were combined in 2003.
|
Routing - PUBLIC WORKS | 10/14/2003 | | 10/15/2003 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/30/2003 | | 10/6/2003 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/19/2003 | | 9/30/2003 | | FAIL |
|
|
|
Requires drainage plan revision per Brian M. kmm
|
Plan resubmittals received | | | 9/29/2003 | | DONE |
|
|
|
Received response letter with two sets of A3.0,A5.0,A6.0, A6.1. taken to Mike O
|
Plan resubmittals requested | | | 9/25/2003 | | DONE |
|
|
|
CAll from the architect on status: Corrections of 8/11 never responded to. Re sent corrections to architect. MLO
|
Routing - FIRE | 9/4/2003 | | 9/11/2003 | | PASS |
|
|
|
Approved per resubmittal. Review comments faxed to architect.
|
Routing - PLAN CHECK | 8/19/2003 | | 9/4/2003 | | FAIL |
|
|
|
Corrections not done, resubmitted sheets addressing fire dept corrections for floor area and construction of walls in basement inserted and plans sent to fire. MLO
|
Plan resubmittals received | | | 8/29/2003 | | DONE |
|
|
|
Received one copy of cover letter and two copies of revised sheets A2.0 & A6.1. Routed to Mike O. kmm
|
Routing - PLANNING | 8/15/2003 | | 8/19/2003 | | PASS |
|
|
|
Approved per DRH02-142.
|
Routing Off Site -Energy | 8/12/2003 | | 8/14/2003 | | PASS |
|
|
|
contacted Ron O for energy review of revised mech. calcs. received on 8-6-03
|
Routing - FIRE | 8/12/2003 | | 8/14/2003 | | FAIL |
|
|
|
Reveiw of 8/5/03 resubmittal. Bsmt still requires automatic sprinklers. Revised review comments faxed to architect.
|
Routing - PLAN CHECK | 8/6/2003 | | 8/11/2003 | | FAIL |
|
|
|
corrections sent to architect
|
Plan resubmittals requested | | | 8/11/2003 | | DONE |
|
|
|
IBC corrections and plans not stamped and signed by architect.
|
Plan resubmittals received | | | 8/6/2003 | | DONE |
|
|
|
Received one copy of HVAC calculations, structural engineer's calculations, response letter and one copy of letter to Sam. Three copies of revised sheets T1.0, A1.0, A1.1, A2.0, A3.0, A3.1, A3.2, A5.0, A6.0, A6.1. Routed to Mike O. kmm
|
Routing Off Site -Energy | 7/30/2003 | | 8/2/2003 | | FAIL |
|
|
|
Contacted Ron O for revised energy review. kmm
|
Plan resubmittals requested | | | 7/23/2003 | | DONE |
|
|
|
Energy corrections
|
Routing Off Site -Energy | 6/2/2003 | | 7/23/2003 | | FAIL |
|
|
|
Contacted Ron O. for outside energy. Corrections sent to architect MLO
|
Routing - FIRE | 6/23/2003 | | 6/26/2003 | | FAIL |
|
|
|
Review comments faxed to architect; re.bsmt AS, FD access, hydrant location & flow, egress lighting.
|
Plan resubmittals requested | | | 6/23/2003 | | DONE |
|
|
|
IBC corrections
|
Routing - PLAN CHECK | 6/16/2003 | | 6/23/2003 | | FAIL |
|
|
|
corrections sent to architect
|
Routing - PLUMBING | 6/13/2003 | | 6/13/2003 | | PASS |
|
|
|
additional cross connection protection may be required, all work to comply with 2000 upc
|
Routing - PLANNING | 6/11/2003 | | 6/12/2003 | | FAIL |
|
|
|
Proposed parking at south yard does not comply with minimum driveway width standards.
|
Routing - Erosion and Sediment | 6/9/2003 | | 6/10/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 6/3/2003 | | 6/9/2003 | | FAIL |
|
|
|
Requires drainage plan revisions per Brian M. kmm
|
Routing - PLANNING Land Div | 6/2/2003 | | 6/3/2003 | | FAIL |
|
|
|
Need proof of legal land division. Parcel of portion of platted lot.
|
Plans ACCEPTED BY PLAN TECH | | | 6/2/2003 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 6/2/2003 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/27/2003 | | DONE |
|
|
|
|
Fee Review-notes | 5/27/2003 | 5/27/2003 | | | |
|
|
|
|