Second Notice BLD | 4/26/2005 | 4/26/2005 | 4/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 5/27/2004 | 4/26/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/15/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 1/18/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 8/4/2004 | | |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 5/27/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10166 issued 5-27-04 to Hyde Park Place.
|
Permanent Occupancy | | 5/26/2004 | 5/26/2004 | | DONE |
|
|
|
|
BLD-Final | 5/19/2004 | 5/20/2004 | 5/20/2004 | A | PASS |
Dave Hannah
|
|
|
FRANKO; Phone #: ###-#### Internet Inspection Request from: Annette Moore ok for perm occ 5/21/2004 10:31:21 AM
|
BLD-Final | 5/6/2004 | 5/7/2004 | 5/7/2004 | A | FAIL |
Dave Hannah
|
|
|
Cathy has the card - David Southers, ###-#### if questions still needs to finish in stalling hand rails 5/7/2004 11:20:34 AM
|
Temporary occupancy | | | 4/9/2004 | | DONE |
|
|
|
Temp. Occ. Cert. #5099 issued 4-9-04 to Hyde Park Place Apts.
|
BLD-Final | 4/8/2004 | 4/8/2004 | 4/8/2004 | P | PART |
Dave Hannah
|
|
|
darrell; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok for temp occ ok for perm occ after others go final and hand rails installed 4/8/2004 5:22:06 PM
|
FIRE-Final Inspection | 4/2/2004 | 4/5/2004 | 4/5/2004 | A | PASS |
Rick Jackson
|
|
|
darryl; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Final | 4/2/2004 | 4/5/2004 | 4/5/2004 | A | FAIL |
Dave Hannah
|
|
|
darryl; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 3/16/2004 | 3/16/2004 | 3/16/2004 | A | PART |
Dave Hannah
|
|
|
ceilling grid in garage ok to start dropping in panels 3/16/2004 10:35:43 AM
|
BLD-Framing/Rough-in | 12/4/2003 | 12/5/2003 | 12/5/2003 | A | PART |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 12/4/2003 | 12/4/2003 | 12/4/2003 | P | PART |
Dave Hannah
|
|
|
Darrell; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
FIRE-Conference | 11/20/2003 | 11/21/2003 | 11/21/2003 | A | PART |
Rick Jackson
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes about exit/emergency lights in basement and corridors and identified with electrical contractor 11/21/2003 2:27:46 PM
|
BLD-Framing/Rough-in | 11/17/2003 | 11/17/2003 | 11/17/2003 | P | PART |
Dave Hannah
|
|
|
Darrell; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes int walls that need shear ok to insulate 11/17/2003 4:44:59 PM
|
Case Summary (BLD) | | | 10/30/2003 | | |
|
|
|
|
BLD-Conference | 10/14/2003 | 10/14/2003 | 10/14/2003 | P | DONE |
Dave Hannah
|
|
|
darryl; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Conference | 10/14/2003 | 10/14/2003 | 10/14/2003 | P | PART |
Alan Hauser
|
|
|
meet with hvac contractor about new heating systems 10/14/2003 2:03:40 PM went over heating system and duct to be allowed, bldg super to find out icbo decision on use of air connector ducting 10/14/2003 6:15:20 PM
|
BLD-Conference | 9/17/2003 | 9/17/2003 | 9/17/2003 | P | DONE |
Dave Hannah
|
|
|
|
Issue PAID IN FULL permit | | | 9/10/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/8/2003 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/8/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/8/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/8/2003 | | DONE |
|
|
|
permits ready and fees due
|
Plan assigned to (M_P) | 5/30/2003 | | 9/5/2003 | | PASS |
Mike Phillips
|
|
|
9/5/2003 11:38:08 M_P - activity updated through activity BLDA022 from case BLD03-01231.
|
Routing - PLAN CHECK | 8/29/2003 | | 9/5/2003 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/29/2003 | | 9/5/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/5/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/5/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/4/2003 | | DONE |
|
|
|
Received three copies of revised sheets SW0.1, SW2.2, SW2.3 SW2.4 and three copies of calcs. Routed copies to Mike P.
|
Routing - PLAN CHECK | 8/21/2003 | | 8/29/2003 | | PEND |
|
|
|
Waiting for outside structural review approval prior to issuing permit.
|
Routing Off Site -Energy | 8/22/2003 | | 8/29/2003 | | DONE |
|
|
|
contacted PDQ to take resubmitted plans of 8/21/03 to outside engineering.
|
Routing Off Site - STRUCTURAL | 8/25/2003 | | 8/27/2003 | | FAIL |
|
|
|
Contacted PDQ to take calcs received on 8/25/03 to outside engineering. kmm
Second review failed. E-mailed copy to architect requesting additional information be submitted for further review by our outside engineering firm.
|
Plan resubmittals received | | | 8/25/2003 | | DONE |
|
|
|
Resubmittal Sheets A0.1, A8.0, M1.0, M1.1, M1.2, M1.3, cover letter from John Price, supporting details, and engineering from Dale Swink received and forwarded to Mike Phillips.
|
Additional plans submitted | | | 8/25/2003 | | DONE |
|
|
|
Received two copies of struct. calcs. Routed one copy to Mike and the other to engineering,
|
Routing - PLAN CHECK | 7/15/2003 | | 8/21/2003 | | FAIL |
|
|
|
Second review failed additional informaiton required for further review prior to issuing permit. Sent comments to architect.
|
Plan resubmittals received | | | 8/21/2003 | | DONE |
|
|
|
Transmittal letter, plan check response letter, two copies of structural calcs, Three sets of SW0.1,SW2.2,SW2.3,SW2.4 taken to Mike P.
|
Routing Off Site - STRUCTURAL | 8/7/2003 | | 8/13/2003 | | FAIL |
|
|
|
Contacted PDQ to take revised plans of 8/6/03 to outside engineering. kmm
Secind review failed additional information required for further review.
|
Plan resubmittals received | | | 8/6/2003 | | DONE |
|
|
|
Received three copies of revised sheets SW0.1, SW2.0, SW2.1, SW2.2, SW2.3, SW2.4, SW3.0, SW3.1. One copy of structural plan check response and three copies of revised structural calculations. Routed to Mike P. kmm
|
Plan resubmittals received | | | 7/24/2003 | | DONE |
|
|
|
Received transmittal page from Tamura & Associates, 7 page response letter, Unit floor plans, two pages of accessible routes, REScheck compliance certificate, four pages of restroom documents, two sets of AO.1,A1.1,A2.0,A2.1, A2.2,A2.3,A.0,A3.1, A3.2,A3.3,A3.4,A3.5, A3.6,A3.7, A3.8, A3.9,A3.10, A3.11, A3.12, A3.13, A3.14, A6.0, A8.0, A8.1, A9.0, A10.0, M1.0, M1.1,M1.2, M1.3, taken to Mike P.
|
Routing - FIRE | 7/9/2003 | | 7/14/2003 | | PASS |
|
|
|
|
Routing Off Site -Energy | 6/2/2003 | | 7/9/2003 | | FAIL |
|
|
|
Received energy certificate.
Additional information requested for further review.
|
Routing Off Site - STRUCTURAL | 6/3/2003 | | 7/9/2003 | | FAIL |
|
|
|
contacted PDQ to take to outside engineering
Additional informaiton required for further review by outside engineering firm.
|
Routing - PLAN CHECK | 6/23/2003 | | 7/9/2003 | | FAIL |
|
|
|
PLan review completed sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLUMBING | 6/20/2003 | | 6/23/2003 | | PASS |
|
|
|
1. water service needs 2 1/2 inch double check valve backflow preventor. 2. is an st-210v expansion tank large enough for this project? have engineer check design.
|
Routing - PLANNING | 6/12/2003 | | 6/19/2003 | | PASS |
|
|
|
Approved per CUP02-96 (Susan Riggs) and per DRH02-221 (Martin Santoyo).
|
Plan resubmittals received | | | 6/13/2003 | | DONE |
|
|
|
Received one copy of REScheck Compliance Certificate. Routed to Mike P. kmm
|
Routing - Erosion and Sediment | 6/10/2003 | | 6/11/2003 | | PASS |
|
|
|
ESC approved on 5/30/03 under ESC03-00691. A complete set of two plans and 2 narratives need to be attached to this submittal.
|
Routing - PUBLIC WORKS | 6/2/2003 | | 6/9/2003 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/6/2003 | | DONE |
|
|
|
1 copy of kitchen and bathroom elevations detail booklet received and forwarded to Mike Phillips.
|
Plans ACCEPTED BY PLAN TECH | | | 6/3/2003 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 6/2/2003 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/2/2003 | | DONE |
|
|
|
contacted John to bring in another set of plans for outside engineering
|
Plan resubmittals received | | | 6/2/2003 | | DONE |
|
|
|
received 4th set of plans and put with set.
|
Routing - PLANNING Land Div | 6/2/2003 | | 6/2/2003 | | PASS |
|
|
|
Approved. Deed recorded with one legal description and one new tax parcel #.
|
Application received | | | 5/28/2003 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2003 | | |
|
|
|
took hold off per Jenifer--hold said--STOP WORK PER CARL per Judges court order\rad Do not release unless you talk with Teresa Sobika per Bob/lh
|
Recd Pcfee & Taken To Pln CK | | | 5/28/2003 | | |
|
|
|
|
Override - Parcel Holds | | | 5/28/2003 | | |
|
|
|
|
Fee Review-notes | 5/28/2003 | 5/28/2003 | | | |
|
|
|
|