DOC-Permit Expired | 8/3/2004 | 8/3/2004 | 8/3/2004 | | DONE |
Dave Hannah
|
|
|
Permit expired by limitations.
|
BLD-Aging Inspection | 6/3/2004 | 6/3/2004 | 6/3/2004 | | PASS |
Dave Hannah
|
|
|
wip 6/3/2004 10:18:00 AM
|
Issue PAID IN FULL permit | | | 3/2/2004 | | DONE |
|
|
|
|
Telephone call | | | 2/26/2004 | | DONE |
|
|
|
talked to a james woodbury & will get someone to pickup permit
|
Telephone call | | | 1/27/2004 | | DONE |
|
|
|
talked to mark gier & he gave me james woodbury to contact in california at ###-#### for pickup
|
Telephone call | | | 1/7/2004 | | DONE |
|
|
|
talked to mark gier will let g.c. know that permit is ready
|
Telephone call | | | 11/14/2003 | | DONE |
|
|
|
talked to sylvester will pickup plans
|
Plan assigned to (KMM) | 6/4/2003 | | 11/13/2003 | | PASS |
Kathy Miller
|
|
|
11/13/2003 09:28:27 KMM - activity updated through activity BLDA022 from case BLD03-01299.
|
Routing - PLAN CHECK | 8/12/2003 | | 11/13/2003 | | DONE |
|
|
|
plans in hold box.
|
Routing - PUBLIC WORKS | 11/13/2003 | | 11/13/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/13/2003 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/13/2003 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/13/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/13/2003 | | |
|
|
|
|
Telephone call | | | 11/13/2003 | | DONE |
|
|
|
left mess for mark gier ###-#### that permit is ready
|
Routing - PLAN CHECK | 7/2/2003 | | 8/12/2003 | | |
|
|
|
Waiting for PW to sign off on plans. Plans in hold box. kmm
|
Routing - PUBLIC WORKS | 8/12/2003 | | 8/12/2003 | | FAIL |
|
|
|
Plug permits required. Plans for sewer modifications required as a seperate submittal. Per John Jonson. kmm
|
Routing - PLANNING | 7/2/2003 | | 7/2/2003 | | PASS |
|
|
|
Approve - note that applicant needs to comply with conditions of DRH03-60 for street and streetscape work.
|
Routing - PLAN CHECK | 6/19/2003 | | 7/2/2003 | | |
|
|
|
Plans in hold box. Waiting P&Z and Public Works approval
|
Routing - FIRE | 6/17/2003 | | 6/19/2003 | | PASS |
|
|
|
|
Routing - PLUMBING | 6/16/2003 | | 6/17/2003 | | PASS |
|
|
|
1. Grease interceptor to building 4 needs vent and cleanout on outlet side. 2. Water sizing to building 7 may need to be increased depending on usage in building. 3. Building 7 may need grease interceptor depending on usage in building.
|
Routing - PLANNING | 6/12/2003 | | 6/13/2003 | | FAIL |
|
|
|
Final approval by staff with input from CCDC still needs to be obtained per conditions of DRH03-60 and DRH03-61. Have contacted Mark Geir. Plans should continue to be routed and returned later to Planning.
|
Routing - Erosion and Sediment | 6/12/2003 | | 6/12/2003 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 6/11/2003 | | 6/12/2003 | | FAIL |
|
|
|
plug permits required.
|
Routing - PUBLIC WORKS | 6/5/2003 | | 6/9/2003 | | FAIL |
|
|
|
Plug permits required. Plans for sewer medifications required as a separate submittal. John Johnson. Requires drainage plan revisions. Per Brian Murphy. kmm
|
Plan resubmittals received | | | 6/6/2003 | | DONE |
|
|
|
Received 2 copies of revised sheets C1.6A, C1.6B, C1.6C. Put with plans. kmm
|
Plan routing begun/NEW & ADDTN | | | 6/4/2003 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 6/4/2003 | | 6/4/2003 | | PASS |
|
|
|
Approved for grading and site work. No new structures are allowed under this permit.
|
Application received | | | 6/4/2003 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/4/2003 | | DONE |
|
|
|
|